REALTY HARVEST LTD. AND OTHERS v. GOLD MARGIN DEVELOPMENT LTD. AND ANOTHER
HTML content
CACV212/2000
IN THE HIGH COURT OF THE
HONG KONG SPECIAL ADMINISTRATIVE REGION
COURT OF APPEAL
CIVIL APPEAL NO. 212 OF 2000
(ON APPEAL FROM HCA 11197 OF 1998)
_________________________
BETWEEN | ||
REALTY HARVEST LIMITED | 1st Plaintiff | |
WAI MING CONTRACTING CO LTD | 2nd Plaintiff | |
WAI MING SERVICES LTD | 3rd Plaintiff | |
AND | ||
GOLD MARGIN DEVELOPMENT LIMITED | 1st Defendant | |
AU YU PING | 2nd Defendant |
_________________________
Date of Hearing: 16 January 2001
Date of
_______________
J U D G M E N T
_______________
Hon Leong CJHC (giving the
1. The 2nd defendant (the appellant) is the owner and the 1st defendant is the
2. The 1st plaintiff is the owner of Unit 12 on the floor directly below. The 2nd and 3rd plaintiffs are the
3. The 1st defendant installed two weaving machines on its rented premises to manufacture labels and these weaving machines generated noise and vibrations when they were in operation. It is not
4. Complaints about the level of noise and vibrations were made by the plaintiffs to the management of the building, the Environmental Protection Department as well as to the Labour Department but of no avail. The plaintiffs themselves attempted to reduce the noise and vibrations by installing insulating materials on the ceiling of their premises but this was not effective. The defendants were made aware of the problem and it is not in dispute that in April and in July 1998, after they consulted the supplier of the weaving machines for a solution, the defendants installed paddings beneath the machines in an attempt to reduce the noise and vibration level.
5. In July 1998, the 1st defendant's technicians went into the plaintiffs' premises to assess the situation and the readings obtained showed a maximum of 77 db(A) when both weaving machines were in operation. By this time, the plaintiffs had already issued a
6. The Labour Department considered that in an industrial building, a noise level of not more than 85 db(A) was acceptable to a person working on the premises but beyond that, workers on the premises should be provided with ear mufflers for protection. In August 1998, the 2nd defendant informed the plaintiffs that better vibration insulators had been installed to the machines. However, the plaintiffs did not accept that the defendants had made sufficient amends to reduce the level of noise and vibrations. They proceeded with their legal claim against the defendants. While these
7. The case against the 2nd defendant is that he was in
8. The relevant clauses are as follows:
"9. No Owner shall do or
permit orsuffer to be done and each Owner will take allpossible steps to prevent histenants , occupiers orlicensees from doing any act, deed, matter or thing which in any way interferes with or affects or which is likely to interfere with or affect the maintenance of the Building or the proper use and enjoyment of the Building or any part or parts thereof by other owners or occupiers of the Building.33. No Owner shall do anything in the Unit whereby excessive noise vibration or resonance or other form of disturbance is created to the detriment of the Building or other manufacturing processes or to the other persons in or outside the Building Provided that..... in the event of a
breach thereof by the Owner such Owner shall immediately rectify such default and make good any damage caused thereby to the Building or any part or parts thereof or to the manufacturing processes therein or to the occupants thereof; and provided further that the making good of such damage as aforesaid shall bewithout prejudice to any further rights available to the Owner(s) who have sufferedloss and damages and/or to the Managerby virtue of the Deed"
9. The main question at the trial was whether the plaintiffs had proved the 2nd defendant committed a
10. In the proceedings below, both the plaintiffs and the defendants had engaged their own experts to assess the noise and vibration level in the plaintiffs' premises and their reports were put before the
11. After reviewing the evidence and the reports of these experts, the
12. The judge found it proved against the 2nd defendant that he was in
"1. ...
2. The 2nd defendant to forthwith take steps to prevent the emission from his premises in Yue Fung Industrial Building between the hours 9 a.m. and 5 p.m. on Mondays to Saturdays, but excluding holidays, noises whose level is more than 10 db(B) above the background noise level and vibrations whose level exceeds 0.4 m/s 1.75;
3. ....
4. ....
5. The lst and/or 2nd defendants do pay the 2nd plaintiff
damages in the sum of HK$13,000.00; and6. Order nisi that the lst and 2nd defendants do pay the plaintiffs the costs of this action...."
13. The 2nd defendant appeals.
14. In the
15. Mr Chau, Counsel for the plaintiffs, concedes that the order to pay
16. On the rest of the appeal, the question for our
17. Mr Siu for the 2nd defendant, relying on Berton v Alliance Economic Investment Co [1922] 1 KB 742 which was applied in Kwan Shung King v Housing Appeal Tribunal [2000] 2 HKLRD 764,
18. In Berton v Alliance Economic Investment Co, one of the questions for the consideration of the Court was the meaning of "
"It is not suggested that there is any difference between the words '
permit ' and 'suffer ' in this context, and I treat them as having the same meaning. It is clear that a person under acovenant not to use premises in a particular way cannot commit abreach of thecovenant except by his own act or that of his agent. The same is true of acovenant not topermit . The user in one case and the permission in the other must be something which can bepredicated of the defendant or the defendant's agent. It is not sufficient to show that the premises have been used in a way which wouldconstitute abreach of thecovenant ; it must further be shown that the user is by the defendant or his agent, or that it is permitted by the defendant or his agent. ..... To my mind the word 'permit ' means one of two things, either to giveleave for an act which without thatleave could not be legally done, or to abstain from takingreasonable steps to prevent the act where it is within a man's power to prevent it. Acts which fall short of that, though they be acts of sympathy or assistance, do notamount to permission at any rate in thecovenants with which we are dealing..."
19. InYu Yuk Sun v Wing Shing Firm [1951] HKLR 136, a case also relied on by Mr Siu, Scholes J in referring to what Bankes LJ said in Berton, quoted from the
"The onus being on the plaintiff to establish a permission or sufferance what is the meaning of a
covenant not topermit orsuffer an act? It does not mean that thecovenantor will not sympathize with the person who is doing the act, or that he will not tell that person what he honestly believes his legal position to be. It does not include an obligation at all costs to take steps to prevent the act. Its scope is less extensive than that. ....."
20. On these
21. On the question of whether the
22. Mr Chau, on the other hand, submits that Clause 9 requires the 2nd defendant to take all
23. The
24. We are unable to accept that the 1st plaintiff had proved that the 2nd defendant had been in
25. We make a costs order nisi that the 2nd defendant's costs of this appeal and his
( Arthur Leong ) | ( Michael Wong ) | ( K H Woo ) |
Chief Judge, High Court |
Representation:
Mr Chau Hing Pang, instructed by Messrs Philip T F Wong & Co for the 1st to 3rd Plaintiffs (1st to 3rd Respondents)
Mr Stanley C K Siu, instructed by Messrs Anthony Kwan & Co for the 2nd Defendant (Appellant)