HK CourtDB
HomeDirectoryMCP
Hong Kong CourtDB
Back to directory
Construction and Arbitration Proceedings2004

CHEUNG KEE FUNG CHEUNG CONSTRUCTION CO LTD v. THORN SECURITY (HONG KONG) LTD

Related cases with same parties

  • CACV100/2006GRANDEUR ELECTRICAL CO LTD v. CHEUNG KEE FUNG CHEUNG CONSTRUCTION CO LTD
  • CACV211/2003THORN SECURITY (HONG KONG) LTD v. CHEUNG KEE FUNG CHEUNG CONSTRUCTION CO LTD
  • HCA7968/1999THORN SECURITY (HONG KONG) LTD v. COMTECH ENGINEERING & CONSULTANT CO LTD
  • HCCT53/1999COMTECH ENGINEERING & CONSULTANT CO LTD v. THORN SECURITY (HONG KONG) LTD
  • HCCT8/2016CHEUNG KEE FUNG CHEUNG CONSTRUCTION CO LTD v. PERMANENT INVESTMENT CO LTD
  • HCMA498/2018HKSAR v. CHEUNG KEE FUNG CHEUNG CONSTRUCTION CO LTD
42766-EN-2004-08-20

CHEUNG KEE FUNG CHEUNG CONSTRUCTION CO LTD v. THORN SECURITY (HONG KONG) LTD

HTML content

HCCT000052/2004

HCCT 52/2004

IN THE HIGH COURT OF THE

HONG KONG SPECIAL ADMINISTRATIVE REGION

COURT OF FIRST INSTANCE

CONSTRUCTION AND ARBITRATION PROCEEDINGS

NO. 52 OF 2004

____________

IN THE MATTER of Section 6B of the Arbitration Ordinance, Cap 341

AND

IN THE MATTER of Arbitrations

BETWEEN
CHEUNG KEE FUNG CHEUNG CONSTRUCTION COMPANY LIMITEDPlaintiff
(Respondent in Arbitration)
AND
THORN SECURITY (HONG KONG) LIMITED1st Defendant
(Claimant in Arbitration)

BETWEEN
CHEUNG KEE FUNG CHEUNG CONSTRUCTION COMPANY LIMITEDPlaintiff
(Respondent in Arbitration)
AND
KONE ELEVATOR (HONG KONG) LIMITED2nd Defendant
(Claimant in Arbitration)

BETWEEN
CEHUNG KEE FUNG CHEUNG CONSTRUCTION COMPANY LIMITEDPlaintiff
(Claimant in Arbitration)
AND
HONG KONG HOUSING AUTHORITY3rd Defendant
(Respondent in Arbitration)

____________

Coram: Hon Reyes J in Chambers

Date of Hearing: 20 August 2004

Date of Judgment: 20 August 2004

_______________

J U D G M E N T

_______________

1. I refuse the application for consolidation. In my view, the application for consolidation was not made as soon as practicable.

2. The 3 arbitrations are at different stages of preparedness, with the 3rd arbitration (which the Plaintiff wishes to be the lead arbitration) being only at an initial stage. The 1st and 2nd arbitrations are nearly ready for substantive hearing.

3. The situation in which the Plaintiff finds itself seems to me to have been largely self-induced. Had the Plaintiff taken steps to apply for consolidation sooner, the risk of inconsistent judgments which it now says that it faces would have been obviated. Thus, the Plaintiff could have taken steps to progress its arbitration with the Housing Authority at a much earlier stage, rather than simply agreeing with the Housing Authority over a period of some 2 years to suspend the running of time for the bringing of an arbitration.

4. It was also open to the Plaintiff at an earlier stage to apply for the consolidation of the 1st and 2nd arbitrations at the very least, if it was genuinely concerned about the possibility of inconsistent judgments. It did not do so.

5. In all the circumstances, it does not seem to me appropriate to consolidate the 3 arbitrations. That would inevitably cause substantive delay to the 1st and 2nd Defendants of the order of 12 to 18 months. It would also expose the 1st and 2nd Defendants to far greater expense, relative to their more modest claims, if there were to be a consolidation of their respective arbitrations into a significantly larger multi-party arbitration at this late stage.

(A. T. Reyes)
Judge of the Court of First Instance
High Court

Representation:

Ms Roxanne Ismail, instructed by Messrs Sidley Austin Brown & Wood, for the Plaintiff

Mr Anthony Chow, instructed by Messrs Au Yeung, Cheng, Ho & Tin, for the 1st Defendant

Mr Geoffrey Shau, of Messrs Deacons, for the 2nd Defendant

Mr Boyle and Mr K K Cheung, of Messrs Johnson, Stokes & Master, for the 3rd Defendant