HK CourtDB
HomeDirectoryMCP
Hong Kong CourtDB
Back to directory
Civil Action2008

SUN FOOK KONG (CIVIL) LTD v. MULTIPIPE RENOVATION LTD

Related cases with same parties

  • HCA1030/2023MULTIPIPE RENOVATION LTD v. KWAN ON CONSTRUCTION COMPANY LTD
  • HCCT17/2010HONG KONG ASPHALT (GREEN) LIMITED (formerly known as ADRIAN ENVIRONMENTAL & WASTE TECHNOLOGIES LTD) v. SUN FOOK KONG (CIVIL) LTD
  • HCCT20/2002MAK\'S CONSTRUCTION CO LTD v. SUN FOOK KONG (CIVIL) LTD
  • HCCT94/1997THE SECRETARY FOR JUSTICE v. SUN FOOK KONG (CIVIL) LTD

Files (2)

67443-EN-2009-08-28

SUN FOOK KONG (CIVIL) LTD v. MULTIPIPE RENOVATION LTD

HTML content

   HCA 2504/2008

IN THE HIGH COURT OF THE

HONG KONG SPECIAL ADMINISTRATIVE REGION

COURT OF FIRST INSTANCE

ACTION NO.2504 OF 2008

_____________________________

BETWEEN

 SUN FOOK KONG (CIVIL) LIMITEDPlaintiff
 and 
 MULTIPIPE RENOVATION LIMITEDDefendant

_____________________________

 IN THE MATTER of an application on behalf of SUN FOOK KONG (CIVIL) LIMITED against MULTIPIPE RENOVATION LIMITED and CHAN WAH TAT CARLMEN for an order of committal

_____________________________

Before : Hon Sakhrani J in Court

Date of Hearing : 28 August 2009

Date of Judgment : 28 August 2009

_____________________

J U D G M E N T

_____________________

 

1.  This is the plaintiff’s motion against the defendant and Mr. Carlmen Chan Wah Tat (“Mr. Chan”) for committal for their contempt of court for failing to comply with my order of 24 December 2008 (“the order”). Mr. Chan is the sole shareholder and director of the defendant.

2.  The order was made after a contested hearing where the parties were represented by counsel and solicitors. The order that I made included an order by paragraph 1 that:

“ the Defendant do forthwith deliver or cause to be delivered or take steps to deliver all construction plant, machineries and equipment directly or indirectly purchased by the plaintiff under the subcontract in relation to the drainage, maintenance and construction works in the Mainland South Districts under the Main Contract No. DC/2007/11 (the “Subcontract”) as set out in the list attached hereto as Appendix I (the “Equipment”).”

3.  The order also included an order by paragraph 3 that :

“ the Defendant do forthwith deliver or cause to be delivered or take steps to deliver all pipe lining materials directly or indirectly purchased by the Plaintiff under the Subcontract which has not yet been used in the Subcontract (the “Material”).”

4.  Appendix I of the order listed out the eight items said to constitute the Equipment.

5.  The facts leading up to the grant of the order are set out in the Reasons for Judgment handed down on 6 January 2009 which I shall not repeat here. Briefly, the plaintiff is the main contractor of the drainage project in respect of the drainage, maintenance and construction works in the Mainland South Districts under the Main Contract No. DC/2007/11. The employer is the Drainage Services Department of the Government. The defendant is a specialist subcontractor in pipe lining works. The defendant was the subcontractor of the plaintiff in respect of works under a subcontract.

6.  I was concerned with an application for an injunction by the plaintiff which included mandatory orders for the defendant to deliver the Equipment and the Material to the plaintiff. On 24 December 2008 I made the order.

7.  The defendant failed to comply with the order despite demands made on it by the plaintiff to do so.

8.  Mr. Chan was also served with the order with a penal notice endorsed thereon.

9.  The plaintiff applied for leave ex parte to commit the defendant and Mr. Chan for their contempt.

10.  On 16 January 2009 I made an order that personal service of the order on the defendant was to be dispensed with and that leave be granted to the plaintiff to apply for committal of the defendant and Mr. Chan for their contempt in failing to comply with the order.

11.  The notice of the motion was issued on 13 January 2009. I have since given directions for the filing of evidence.

12.  Mr. Chan has relied on his 2nd affirmation filed on 25 June 2009 in opposing the plaintiff’s application. He has also given oral evidence and has been cross-examined.

13.  Mr. Chan disclosed in his 2nd affirmation that the Equipment and the Material were, in fact, stored in a rented yard since November 2008, that is before the order.

14.  At paragraph 8 of his 2nd affirmation he said that due to the poor financial status of both the defendant and himself they were unable to meet the monthly rental of the yard since December 2008 and that the landlord of the yard was keeping the Equipment and the Material as a lien for the rental and deposit. He said that the items could be recovered upon payment of the outstanding rental and deposit but that the defendant and he himself were unable to make such payments due to their financial condition. He also proposed that the plaintiff should settle the outstanding rental with the landlord to obtain release of the same from the landlord of the yard. This was rejected by the plaintiff.

15.  A few days ago Mr. Chan made another proposal to the plaintiff whereby he would contribute $30,000 towards the outstanding rental and deposit payable to the landlord of the yard and the plaintiff to pay the balance. Subject to working out some matters of detail, I have been informed by Mr. Wong, counsel for the plaintiff, that an agreement in principle has been reached as to the release of the goods from the yard without prejudice to proceeding with the plaintiff’s motion for committal.

16.  I accept that even though the order would now be complied with, the plaintiff is entitled to proceed with the motion.

17.  The obligation is on the plaintiff to prove beyond reasonable doubt that the defendant and Mr. Chan are guilty of contempt of court in failing to comply with the order. The defendant and Mr. Chan do not have to prove anything.

18.  There is no requirement on the part of the plaintiff to show that the defendant and Mr. Chan intended to disobey the order. It is sufficient to prove that they knew the facts which were said to make their act or omission a contempt and that such act or omission was not accidental. The defendant and Mr. Chan should, however, be aware of the order and the consequences of breaching it (Citybase Property Management Ltd v Kam Kyun Tak and others (No. 1) [2003] 2 HKC 98 at page 103 per Ma J (as he then was)).

19.  And in Kao, Lee & Yip (a firm) v Donald Koo Hoi Yan & Ors, FACV 27 of 2007, Court of Final Appeal, 25 June 2009, Sir Gerard Brennan NPJ said at paragraph 45 that

“...... it is clear that liability for civil contempt does not depend on a contumacious intent.”

20.  There is no doubt that the defendant and Mr. Chan were aware of the order and the consequences for failing to comply with it. There was a penal notice endorsed on the order.

21.  That the order has not been complied with until the very recent agreement in principle is not really disputed.

22.  Mr. Chan’s evidence is to the effect that the defendant and he himself are financially unable to pay the rental charges and deposit to the landlord of the yard to secure the release of the Equipment and the Material.

23.  Mr. Chan submitted that he has used his best endeavours to try and comply with the order. I do not accept this. In any event, this does not provide a defence. The order was to forthwith deliver or cause to be delivered or take steps to deliver the Equipment and the Material. The order was not to use best endeavours to do so.

24.  Despite being ordered to forthwith deliver or cause to be delivered or take steps to deliver the Equipment and the Material, it was only after the contempt proceedings were well under way that the defendant wrote on 2 March 2009 to the plaintiff asking the plaintiff to collect the Equipment and the Material from the storage yard.

25.  I have heard the evidence and the cross-examination of Mr. Chan. I do not believe that he and the defendant were financially incapable of paying the storage charges and deposit to seek release of the Equipment and the Material after the order was made.

26.  Mr. Chan confirmed in evidence what he had said in paragraph 18 of his 1st affirmation to the effect that the defendant had fixed assets worth $10,000,000, although they may not fetch anywhere near that in a forced sale.

27.  I bear in mind that the storage fees are $26,000 per month with a deposit of one month’s storage fees. I reject Mr. Chan’s evidence that the defendant and he himself are financially unable to raise money to pay the outstanding storage charges for the Equipment and the Material.

28.  I would also refer to Re Texgar Ltd [2001] 2 HKC 426 where it was held that if a company were financially incapable of meeting the order, the proper course was to depose to the same on affirmation giving full and frank disclosure of the financial means. That was not done in that case and has also not been done in this case.

29.  The bank statements in evidence disclosed by Mr. Chan are selective and do not show the financial position for the whole period from the time of the order.

30.  I should, however, mention that I place no reliance on the fact that school fees were paid by Mr. Chan for his son in England. I accept this part of Mr. Chan’s evidence that the payment in and withdrawal on 16 April 2009 from the defendant’s bank account of about $100,000 represented a loan that his wife had obtained from her relatives for the specific purpose of paying school fees for their son.

31.  However, as the bank statements of the defendant show, there were other payments made by the defendant in April and May 2009. Mr. Chan said that these were payments to staff of the defendant who were owed money by the defendant. That, however, shows that it was a conscious and intentional decision to deploy the income received by the defendant for its expenses rather than for the storage and deposit charges to release the Equipment and the Material so as to comply with the order.

32.  I am satisfied beyond reasonable doubt that the defendant and Mr. Chan are guilty of contempt of court in failing to comply with the order and I so find.

[After hearing submissions]

33.  I have found the defendant and Mr. Chan guilty of contempt of court. I bear in mind that the order has now been complied with, although belatedly and only after the plaintiff has brought these contempt proceedings right up to this day. The primary purpose for instituting these contempt proceedings was to enforce the order. That has now been done. Failing to comply with a court order is, of course, a serious and not a trivial matter.

34.  I bear in mind the sentences that have been passed in other cases. Each case, however, depends on its own facts. I am satisfied that Mr. Chan has tried to comply with the order at a late stage and the matters that he has raised really go to mitigation rather than an excuse for not complying with the order.

35.  In the circumstances of this case I think that justice will be served if I do not impose any penalty on the defendant and Mr. Chan but simply make an order against both of them that the costs of all these proceedings be paid by the defendant and Mr. Chan such costs to be taxed on an indemnity basis and to be paid forthwith. To make it clear, the costs of the plaintiff’s application, including the costs reserved when obtaining ex parte leave and the costs reserved on 23 February 2009 and 30 June 2009 and to-day are all to be the plaintiff’s costs to be paid by the defendant and Mr. Chan to be taxed on an indemnity basis and to be paid forthwith.

 (Arjan H. Sakhrani)
 Judge of the Court of First Instance,
 High Court

Mr. Jonathan Wong, instructed by Messrs Li & Partners, for the Plaintiff

Defendant, absent

Chan Wah Tat Carlmen, in person, present

63897-EN-2009-01-06

SUN FOOK KONG (CIVIL) LTD v. MULTIPIPE RENOVATION LTD

HTML content

                             HCA 2504/2008

 

IN THE HIGH COURT OF THE

HONG KONG SPECIAL ADMINISTRATIVE REGION

COURT OF FIRST INSTANCE

ACTION NO.2504 OF 2008

_____________________

BETWEEN

 SUN FOOK KONG (CIVIL) LIMITEDPlaintiff
 and 
 MULTIPIPE RENOVATION LIMITEDDefendant

_____________________

Before : Hon Sakhrani J in Chambers

Date of Hearing : 24 December 2008

Date of Judgment : 24 December 2008

Date of Handing Down Reasons for Judgment : 6 January 2009

                  

________________________________________

R E A S O N S  FOR  J U D G M E N T

________________________________________

 

1. On 24 December 2008 after hearing arguments on the plaintiff’s application by summons dated 3 December 2008 I made the following orders :

(1)             that the Defendant do forthwith deliver or cause to be delivered or take steps to deliver all construction plant, machineries and equipment directly or indirectly purchased by the plaintiff under the subcontract in relation to the drainage, maintenance and construction works in the Mainland South Districts under the Main Contract No. DC/2007/11 (“the subcontract”) as set out in the list attached to the draft order handed up to the Court in Appendix I (“the Equipment”);

(2)             that unless and until the defendant has delivered or caused to be delivered or taken steps to deliver all the Equipment to the plaintiff, the defendant whether by itself, its directors, officers, servants, agents or otherwise howsoever be restrained from selling, causing or permitting to sell or taking steps to sell any of the Equipment unless with the plaintiff’s prior written consent;

(3)             that the defendant do forthwith deliver or cause to be delivered or take steps to deliver all pipe lining materials directly or indirectly purchased by the plaintiff under the subcontract which has not yet been used in the subcontract (the “Material”);

(4)             that unless and until the defendant has delivered or caused to be delivered or taken steps to deliver all the Material to the plaintiff, the defendant whether by itself, its directors, officers, servants, agents or otherwise howsoever be restrained from selling, causing or permitting to sell or taking steps to sell any of the Material unless with the plaintiff’s prior written consent.

2. Appendix 1 is the list of the Equipment consisting of 8 items.

3. I indicated at the time that reasons in writing would be given later.  These are my reasons.

4. The application before me was the adjourned hearing of the plaintiff’s summons whereby the plaintiff sought a mandatory injunction for the delivery up by the defendant to the plaintiff of the Equipment and the Material.

5. By an order made by Suffiad J on 5 December 2008 a prohibitory injunction was granted against the defendant prohibiting the defendant from in effect selling or taking steps to sell the Equipment and the Material until after the adjourned hearing of the plaintiff’s summons on 12 December 2008 or further order.

6. On 12 December 2008 Deputy Judge Mayo continued the prohibitory injunction granted by Suffiad J on 5 December 2008 until after the adjourned hearing of the plaintiff’s summons on 24 December 2008 and he also gave directions for the filing of evidence in relation to the plaintiff’s summons.

7. The plaintiff is the main contractor of a drainage project in respect of the drainage maintenance and construction works in the Mainland South Districts under the Main Contract No. DC/2007/11.  The employer is the Drainage Services Department of the Government.

8. The defendant is a specialist subcontractor in pipe lining works.

9. The defendant was a subcontractor of the plaintiff in respect of the works under the subcontact being subcontract No. 002111S006 which subcontracted works commenced in around January 2008.

10. Chan Wah Tat is the sole shareholder and the sole director of the defendant.

11. Apart from engaging the defendant as the plaintiff’s subcontractor for the works under the subcontract, the plaintiff had also been negotiating with Chan Wah Tat a share acquisition plan for the plaintiff to purchase 60% shareholding of the defendant since about November 2007 subject to a satisfactory due diligence result.

12. The plaintiff’s case is that it was not satisfied with the defendant’s financial position and that it decided not to proceed with the share acquisition plan.  It is the plaintiff’s case that at a meeting on 5 November 2008 Chan Wah Tat was informed that the plaintiff would not proceed with the share acquisition plan.

13. The defendant’s case on the share acquisition plan is that the plaintiff did in fact agree to go ahead with the share acquisition plan.  In his affirmation Chan Wah Tat said that in January 2008 Mr Patrick Lee of the plaintiff told him that the plaintiff’s Group was in the final stage of its application for listing at the Hong Kong Stock Exchange and that they did not want any agreement to be signed for the share acquisition for the time being but that the acquisition was to go ahead.  Chan Wah Tat also said that in reality a joint venture was formed between the plaintiff and the defendant to work on the relevant jobs under the main contract.

14. There was no written share acquisition agreement ever signed between the parties.  Whether the share acquisition plan was ever finalized or not is a matter of dispute between the parties.  Be that as it may, it is important to bear in mind what the main issue in this action and in the application before me is.  It is important to bear in mind that this action and the application before me is about the ownership of the Equipment and the Material.  The plaintiff asks for the return of the Equipment and the Material which on the plaintiff’s case is owned by it and not owned by the defendant.  The main issue is whether it is the plaintiff or the defendant who is the owner of the Equipment and the Material.

15. The plaintiff accepts that before granting an interlocutory mandatory injunction the Court has to be satisfied to a high degree of assurance that at trial it will appear that the injunction was rightly granted.

16. The plaintiff’s case is that it was agreed between the plaintiff and the defendant that the plaintiff would purchase certain plant, machinery and equipment and pipe lining materials for the defendant’s use during the subcontract while the ownership of such plant, machinery and equipment and pipe lining materials would remain vested in the plaintiff.  As Mr Wong, for the plaintiff, demonstrated by reference to the evidence, the plaintiff paid for the equipment and pipe lining materials and from time to time deductions were made from payments due to the defendant from the plaintiff in respect of works under the subcontract.  Once deductions were in fact made by the plaintiff, the plaintiff no longer claimed ownership of the equipment in respect of which deductions were made.

17. By letter dated 26 November 2008 the plaintiff originally claimed the return of 15 items as listed in the enclosure to the letter.  As deductions had been made in respect of 7 of those items, the plaintiff no longer pursued the claim for those 7 items.  Hence the application was for the return of the 8 items listed in Appendix 1 as well as for the Material which is the pipe lining materials which has not yet been used in the subcontract.

18. The defendant does not dispute that the plaintiff purchased and paid for the Equipment and pipe lining materials for the defendant’s use under the subcontract.

19. In the course of his submissions Mr Cheung, for the defendant, submitted that the defence to the plaintiff’s claim to ownership of the Equipment and Materials was that deductions had in fact been made by the plaintiff from payments due to the defendant for all of the Equipment.  He relied on the plaintiff’s documents produced in exhibit CKM-1 to the affirmation of Chan Kwok Mun made on 2 December 2008.

20. In my view, the documents relied on by the defendant to show that deductions had in fact been made for all of the Equipment do not assist the defendant.  At paragraph 43 of the third affirmation of Chan Kwok Mun he made it clear that the sums paid for the Equipment and Materials have not been deducted from the contract sum certified to be payable to the defendant.  This is supported by exhibit CWT-11 which contains all the deductions made by the plaintiff.  The total deductions made under the subcontract was in the sum of $2,007,978.07 and these do not include the deductions for the 8 items of the Equipment listed in Appendix 1 and the Material.

21. The defendant has been unable to adduce any documentary evidence showing that the ownership of the 8 items in Appendix 1 and the Material no longer remained with the plaintiff because deductions for those 8 items and the Material had in fact been made by the plaintiff.

22. According to the plaintiff, since about 16 November 2008 the defendant has abandoned the subcontract works and evinced an intention not to be bound by the subcontract and the plaintiff has accepted the defendant’s repudiation of the subcontract.

23. By letter dated 19 November 2008 from the plaintiff to the defendant the plaintiff referred to a meeting with Chan Wah Tat on 18 November 2008 and said :

“  We note with grave concerns that all your sites were left idle since 16 November 2008.  During the above meeting, you expressed that you are incapable to carry out the outstanding lining works as listed below due to your financial problem.”

24. After listing out the 14 works order numbers in the letter, it went on to state :

“ As agreed in the meeting, your subcontracted works will be terminated with effect from 18 November 2008.  We will arrange another subcontractor to execute the above outstanding works.  All expenses properly incurred will be recoverable by us from you.”

25. In the letter of demand for the return of the Equipment dated 26 November 2008 from the plaintiff to the defendant, the plaintiff said :

“  We refer to our meeting with your Mr Chan Wah Tat on 18 November 2008 at our office.

 As you will recall, you had abandoned the Sub-Contract works since 16 November 2008 and therefore had repudiated the Sub-Contract.  We accepted such repudiation at the meeting and the Sub-Contract came to end.  You agreed that such termination took effect from 18 November 2008 as recorded in our letter dated 19 November 2008.”

26. Although the defendant denies that it has repudiated the subcontract, the defendant did not reply to the letters dated 19 November and 26 November 2008.

27. There can be no doubt that the subcontract has been terminated.  What I am concerned with is the ownership of the Equipment and the Material.

28. On the material before the Court the plaintiff has satisfied me that it has a strong case in establishing that it rather than the defendant is the owner of the Equipment and the Material.

29. As regards the balance of convenience, it seems to me that this clearly lies in the plaintiff’s favour.

30. There is no doubt that the subcontract has been terminated and that there have been delays in the subcontract works.  Because of delays in the subcontract works it is likely that the plaintiff will have to pay liquidated damages under the main contract.  The plaintiff anticipates that liquidated damages of about $570,000 up to 9 December 2008 will be charged by the Drainage Services Department with further liquidated damages for the outstanding works left incomplete by the defendant.

31. To prevent further loss, on the evidence the plaintiff needs to have the Equipment and the Material as soon as possible to complete the works order left incomplete by the defendant.  Although the plaintiff may be able to order the Equipment and the Material from other specialist suppliers overseas this no doubt will take time.  The plaintiff estimates that it would take about two and a half months before the Equipment would arrive at the site for the incomplete subcontract works.

32. The plaintiff will also suffer further loss if new works orders are issued by the Drainage Services Department and the plaintiff is unable to complete these because it does not readily have the Equipment and the Material to do so.  The plaintiff estimates that there may be 5 to 10 new works order issued each month.  Such further loss is difficult to quantify.

33. There is the also the question of the impact of continuing delay on the incomplete subcontract works on the reputation of the plaintiff.  Although there is no evidence that this has yet occurred, there is a real risk that if there is further delay in the incomplete subcontract works, the plaintiff’s performance rating with the Drainage Services Department will be adversely affected and if so, damages would not, in my view, be an adequate remedy.

34. The defendant’s case is that it has been using and would use the Equipment in jobs recently awarded by other main contractors (paragraph 17 of the affirmation of Chan Tat Wah).  This, however, is a bald assertion with no particulars provided as to the other jobs or the other main contractors.  No documentary evidence has been provided in support of this bald assertion.  Be that as it may, damages would, in my view, be an adequate remedy for the defendant if the defendant should succeed at trial.

35. I have also considered the relative financial strength of the parties.  There can be no dispute that the plaintiff is a substantial company.  According to the audited accounts of the plaintiff for the year ended 31 March 2008 the plaintiff made a gross profit of $121,513,897.  The plaintiff is, in my view, good for the cross-undertaking in damages and would be in a strong financial position to pay damages to the defendant in the event that the defendant should succeed at trial.

36. On the other hand, the defendant is in a precarious financial position and is unlikely to be able to pay damages to the plaintiff.  The defendant is a small company with a limited capital of $10,000.  According to the audited accounts for the year ended 31 December 2007 the defendant had a loss of $3,365,069.01 for the year.  In the auditor’s report dated 5 May 2008 when auditing the accounts of the defendant for the year ended 31 December 2007, the auditor commented on this and the fact that the defendant’s current liabilities exceeded its current assets by $9,246,994.46 and a deficiency in assets of $4,154,160.12.  The auditor was of the view that there was “the existence of a material uncertainty which may cast significant doubt about the [defendant’s] ability to continue as a going concern”.

37. In addition to the purchase of the Equipment and the Material by the plaintiff it appears on the evidence that the plaintiff has also granted loans to the defendant in order to finance the operation of the defendant under the subcontract.  I was referred to the loan agreements in exhibit CKM-9 to the third affirmation of Chan Kwok Mun of the plaintiff.  The loans were personally guaranteed by Chan Wah Tat.

38. According to the plaintiff, up to the time of the affirmation of Chan Kwok Mun of 2 December 2008 the defendant still owes the plaintiff a total sum of $5,800,000.  Although the defendant disputes this amount and the state of the accounts between the plaintiff and the defendant, Mr Cheung, for the defendant, conceded in his submissions that when proper accounts are taken between the plaintiff and the defendant, it is probable that the defendant will owe money to the plaintiff.

39. I am satisfied that there is a high degree of assurance that at trial it will appear that the mandatory injunction was rightly granted.

40. For those reasons, I made the order set out at paragraph 1 above with costs of the application to be costs in the cause.

                                                                        

                                                                                

 (Arjan H. Sakhrani)
Judge of the Court of First Instance,
High Court

 

Mr Jonathan Wong, instructed by Messrs Li & Partners, for the Plaintiff

Mr Alexander H F Cheung, instructed by Messrs Cheng, Chan & Co., for the Defendant