HK CourtDB
HomeDirectoryMCP
Hong Kong CourtDB
Back to directory
Civil Action2009

LEE YUM SANG v. YEUNG FOOK HONG AND ANOTHER

Files (3)

105737-EN-2016-09-07

LEE YUM SANG v. YEUNG FOOK HONG AND ANOTHER

HTML content

HCA 638/2009

IN THE HIGH COURT OF THE

HONG KONG SPECIAL ADMINISTRATIVE REGION

COURT OF FIRST INSTANCE

ACTION NO. 638 OF 2009

____________

BETWEEN  
 LEE YUM SANGPlaintiff
 and 
 YEUNG FOOK HONG1st Defendant
 LEUNG YUK SIN2nd Defendant

____________

Before: Hon L Chan J in Chambers
Date of Hearing: 7 June 2016
Dates of filing of submissions: 3, 20 June and 31 August 2016
Date of Decision: 7 September 2016

_____________

D E C I S I O N

_____________

1.  This is an application in relation to a right of way over Section C of Lot No. 397 in DD 94 (“Lot 397C”) in favour of the owner of Section D of Lot No. 397 in DD 94 (“Lot 397D”). The defendants are the owners of Lot 397C with House 83E erected thereon. The plaintiff is the owner of Lot 397D with House 83A erected thereon. The right of way was granted by the defendants as owners of Lot 397C to the plaintiff as owner of Lot 397D in a consent order made in this action on 1 June 2011. The consent order was for settling this action and it was made on the first day of the trial of the action.

The consent order, right of way and related constructions

2.  There was a “Partition Wall” standing between Lots 307C and 307D.  It was not standing correctly on the correct boundary line dividing the two lots.  The consent order allowed the defendants to pull down this wall and rebuild a new wall on the boundary line between the lots.

3.  At the western end of the old Partition Wall was the entrance from the western portion of Lot 307C into Lot 307D.  The entrance was guarded by a metal twin gate.  Each wing of the gate was anchored on a concrete column.  One column stood at the western end of the old Partition Wall (“Column C”).  The other column stood on the other side of the entrance and against the western boundary wall of Lot 397D (“Column D”).

4.  Since the old Partition Wall had to be rebuilt, the two columns and the plaintiff’s metal twin gate had to be relocated.  The consent order provided that this relocation work was to be done by a contractor to be engaged by the plaintiff but at the defendants’ costs.

5.  The consent order further gave the right of way to the plaintiff to go over the western portion of Lot 397C for access to and from Lot 397D.  This portion is called the “Protruded Area” in the consent order and so marked in the annexed plan.

6.  The right of way is for the plaintiff’s access on foot or by car from Lot 397D over the Protruded Area to a “Public Way” and vice versa.  The Public Way is marked as “Road” in the annexed plan and is on the other side of the Protruded Area.  It is also part of and situates at the north-west portion of Lot 397C.  There is a kerb separating the Public Way from the rest of Lot 397C as shown in the annexed plan.

7.  If the plaintiff would like to drive from Lot 397D to the public roads, he has to drive through his entrance onto the Protruded Area, make a right turn and drive onto the Public Way.  He can then drive along the Public Way to the public roads.  If he wants to go home from the public roads, he should drive in the vice versa manner.

8.  The parts of the consent order relevant to this application are as follows:

“1. In respect of the Partitioning Wall between Lot 397C and Lot 397D ...

...

(b) The 1st and 2nd Defendants shall on or before 8 August 2011 give written notice to the Plaintiff informing the Plaintiff the date of commencement of the relevant work (mentioned in paragraph (c) below). The Plaintiff shall permit the 1st and 2nd Defendants and/or their agents to erect protective hoarding wooden boards 2 feet alongside the boundary between Lot 397C and Lot 397D at the 1st and 2nd Defendants’ own costs and expenses without damaging the floor tiles of the Plaintiff. The Plaintiff shall permit the1st and 2nd Defendants and/or their agents to enter the area in Lot 397D enclosed by the said hoarding boards for the purpose of demolishing and rebuilding the Partitioning Wall as mentioned in paragraph (c) below.

(c) The 1st and 2nd Defendants shall within 30 days from the completion of the erection of the said hoarding wooden boards, at their own costs and expenses, remove the existing Partitioning Wall between Lot 397D and Lot 397C and rebuild a new Partitioning Wall (of similar height f the existing Partitioning Wall) in accordance with Annex IV to the Defence and Counterclaim.

(d) Upon due completion of para (c) above, for the relocation by the Plaintiff of Plaintiff’s metal gate and the 2 concrete columns for the anchoring of the metal gate, the 1st and 2nd Defendants shall obtain a quotation from a contractor and recommend that said contractor to the Plaintiff, who shall engage the same contractor on the said quotation and the 1st and 2nd Defendants shall be responsible for the costs and expenses of the contractor for the said relocation.

2. Further,

(a) The 1st and 2nd Defendants shall grant (free of consideration) a right of way to the Plaintiff, his successor and assigns as owner of Section D of Lot No. 397 in D.D. 94 (Lot 397D) to use the Protruded Area within Section C of Lot No. 397 in D.D. 94 (Lot 397C) (as defined in the Amended Defence and Counterclaim) for access (on foot and by car) to and from the Public Way within Lot 397C and the Remaining Portion of Lot No. 397 in D.D. 94 (Lot 397RP) (as defined in the Amended Defence and Counterclaim).

...

4.   Liberty to [apply]”

The defendants’ construction works

9.  After the action was settled by the consent order, the defendants rebuilt part of the Partition Wall.  It is marked “Rebuilt Wall” in the annexed plan.  There was a dispute on whether the defendants should also demolish and rebuild the remaining part of the Partition Wall (marked “Original Wall” in the annexed plan).  But the plaintiff does not insist on it now. 

10.  The Rebuilt Wall is now on the boundary between the two lots, but the defendants in rebuilding it have extended it to the west.  It is now longer than the original Partition Wall by 1.7 metres.  The defendants have also built a new column at the edge of the Rebuilt Wall (“Concrete Column E” on the annexed plan) (“New Column E”).  New Column E is within Lot 397C.  The Rebuilt Wall and New Column E have reduced the width of the plaintiff’s entrance by about 1.7 metres (§5(iii) on p 183). 

11.  The kerb which separated the Public Way or Road from the rest of Lot 397C have likewise been extended to the west by 1.7 metres with a new column erected at its western end (“Concrete Column F” on the annexed plan) (“New Column F”). 

12.  The two New Concrete Columns E and F guarded the entrance from the Protruded Area to the defendants’ Lot 397C and House 83E.  The extensions of the Rebuilt Wall and kerb each at 1.7 metres reduced the Protruded Area by 1.7 metres by 5 metres as shown in the annexed plan.

The plaintiff’s summonses

13.  The plaintiff was unhappy about the defendants’ constructions.  He issued a summons on 19 September 2013 seeking an order that the defendants should remove New Columns E & F and the 1.7 metre extensions to the Rebuilt Wall and kerb.  He also wanted the defendants to perform paragraph 1(d) of the consent order and rebuild the remaining part of the Original Wall on the boundary of the lots (“the first summons”).

14.  However, the plaintiff issued a fresh summons on 25 April 2014 (“the second summons”) to replace the first summons.  The second summons seeks the following order:

“1. [T]he Defendants do relocate and retreat the Defendants’ New Concrete Column (towards the house in Lot 397C) [New Column F] and the extended kerb newly erected on the Protruded Area within Section C of Lot No. 397 in D.D. 94 (“Lot 397C”) and referred to in the plan marked as “Appendix 3” annexed hereto (“the said Plan”) by 20 inches from the driveway (“Relocation Work”) at the Defendants’ own costs;

2. [A] survey plan to be prepared by the Plaintiff’s surveyor at the Plaintiff’s own costs be annexed to the order to be made herein showing the measurements that the actual width of the driveway after the Relocation Work is not less than 12 feet;

3. [T]he Plaintiff’s surveyor be at liberty to mark the above measurements at the scene with coloured nails in the presence of the parties; surveyors (if necessary). Once the locations and measurements are marked upon the agreements of the parties, no further changes can be made and the parties must be abided by it;

4. [T]he Defendants do complete the Relocation Work within 21 days from the date of the order to be made herein and provide the quotation referred to in clause 1(d) of the order of the Deputy High Court Judge L. Chan (as he then was) made on 1st June 2011 to the Plaintiff (“the said Order”) within 7 days thereafter;

5. [U]pon compliance of paragraph 4 above, the relocation of the Plaintiff’s gate column at the far side (point C marked on the plan annexed hereto) [Column D] be dispensed with and the Defendants shall bear reasonable costs of converting the existing twin gates (or a new set of gates with matching design and quality) occasioned by the reduction of the width of the gate column at the entrance of Lot No. 397D in D.D. 94;”

15.  The first relief sought in the second summons seeks the relocation of New Column F for 20 inches from the driveway (to the east). It was in fact first suggested by the defendants in a without prejudice letter dated 11 November 2013.  (All the without prejudice correspondence have now been disclosed by the parties.)

16.  The plaintiff filed his 5th affirmation on 2 May 2015 to confirm that he would rely on his second summons in place of his first summons. But as I will explain below, that is not what he wants.  He also produced a report by a surveyor Mr Poon to say that the concrete on the driveway was strong enough for motor cars to go over it.

17.  He further filed his 6th affirmation on 10 July 2015 to produce two expert reports.  One report was by a land surveyor Mr Leung who opined that the Rebuilt Wall and kerb had both been extended by 1.7 metres into the Protruded Area.  The plaintiff had relied on this report earlier when he sought relief in the 1st summons.  The plaintiff further said that the extended kerb and New Column F blocked part of the right of way and rendered the way extremely difficult for his son to drive his vehicle through.  The way with the reduced width was also dangerous for a vehicle to pass through.

18.  He also complained that the extended Rebuilt Wall had reduced the width of the entrance to Lot 397D by 1.7 metres.  It was difficult and unsafe for his original twin gate to be reinstalled on new columns to be positioned on the sides of the narrow entrance.  He thus asserted that the defendants had breached §2(a) of the consent order which provided for him the right of way over the Protruded Area.

The traffic engineer’s report

19.  The plaintiff further produced an expert report by a traffic engineer Mr Lai.  The report contained a swept path analysis by computer simulation.  Mr Lai conducted computer simulations of the ingress and egress paths of two vehicle types.  One is a Honda Stream 1.8 RSZ 7-Seats Sporty Sedan and the other is a Toyota Hiace. They are vehicles driven by the plaintiff’s son.  The travel speed used for the simulations was 3-5 km/hr and the minimum clearance on each side of the vehicles was 300 mm (or 11.8 inches).

20.  The simulations based on these criteria showed that there was little problem in driving the cars from the Public Way over the Protruded Area into Lot 397D.

21.  However, the simulations of egress showed that the two cars could not just drive through the way but had to make a 7-point or even 9-point turn so as to get round New Column F.  Mr Lai said in the conclusion of his report that the driver should not be required to make more than a 3-point turn.

22.  Mr Lai suggested that New Column F should be moved eastward by 1.3 metres (or 51 inches) and the kerb should be realigned correspondingly. He also suggested that New Column E should be moved eastward for 0.4 metre (or 16 inches) with the removal of the same length of the Rebuilt Wall.  These suggestions can provide a smooth driveway for egress of the vehicles with minimum clearance of 300 mm on each side.

23.  I, however, notice that from the computer simulations that both the Flower Bed and Column D inside Lot 397D have made the ingress of the two vehicles inconvenient and contributed to the need to make the seven-point and nine-point turns in their egress.

24.  Mr Lai also commented on on-site trial test in his conclusion as follows:

“On-site trial test on the ingress and egress paths may be a way to demonstrate the practical difficulties of the maneuvering movements in the real life situation. However, the acceptability on the results of ingress and egress paths in the trial test will be largely dependent on the skill of the driver in controlling the vehicle to negotiate the passage and the judgment of the driver on his own minimum horizontal clearance to the surrounding obstacles.”

25.  Mr Lai’s suggestions were adopted by the plaintiff through counsel Ms Lam who contested throughout that the suggestions of Mr Lai should be implemented (§13 of the plaintiff’s closing submissions) instead of the relief sought in the plaintiff’s second summons, namely to move New Column F to the east for 20 inches only.

The defendants’ stance

26.  The defendants opposed the plaintiff’s second summons and the suggestions of Mr Lai.

27.  The 1st defendant set out their position in his 5th affirmation.  They disagreed that computer simulations were a proper way to determine the proper width of the right of way for the plaintiff’s use.  Their solicitors had instead suggested simple on-site trial tests to find out the width of a proper way, but the plaintiff declined the suggestion.

28.  He further said that the corner of the driveway at New Column F was wide enough for light goods vehicles to go straight into the plaintiff’s Lot 397D.

29.  He also said that the driveway in question was in a village area.  For about 150 metres of the road beyond the driveway; it was highly likely that a driver had to stop and reverse to make way for on-coming traffic.

30.  He also pointed out that the plaintiff’s Column D at the entrance to Lot 397D was too big.  There were also kerb tiles extending from Column D into the driveway.  If the plaintiff should trim or do away with Column D and trim the kerb, driving through the driveway would be facilitated.

31.  The 1st defendant also complained that the plaintiff had used the right of way for business purpose when it was only for domestic purpose. The reason being that the plaintiff’s son was driving his van over the driveway and the van was used to transport construction materials.

32.  I do not think this complaint is fair.  The van used by the plaintiff’s son is just as like an ordinary saloon car.  It can be parked inside an ordinary parking space for a private car.  Driving this van through the right of way is just like the driving of a private car through it.  What is carried inside the car is not really important on the facts of this case.

33.  The 1st defendant further said that his solicitors had already advised the plaintiff by letter of 14 November 2014 that the defendants would proceed with the remaining works in Lot 397C unless the plaintiff should respond within 21 days.  Since the plaintiff did not respond, the 1st defendant claimed that the plaintiff had acquiesced in these works and cannot pursue the relief in the second summons now.

34.  I do not agree with this assertion.  The plaintiff has already issued the second summons on 25 April 2014 requiring the defendant to move New Column F for 20 inches eastward.  That summons was heard on 30 April 2014 and was adjourned to a date to be fixed.  If the plaintiff did not fix the date for the resumed hearing, the defendants could fix it.  I do not think the defendants can argue that the second summons has been defeated by the plaintiff’s acquiescence.

35.  The 1st defendant further filed his 6th affirmation on 30 November 2015 to produce a VCD showing an on-site trial test of a light goods vehicle over the driveway.

The on-site trial tests

36.  At the hearing on 7 June 2016, the defendant’s solicitor, Mr Chu did not cross-examine Mr Lai on his report but instead pursued his request for on-site trial tests.  I agreed that an on-site trial tests should be conducted so that the reality can be contrasted with the virtual reality.

37.  The on-site trial tests were conducted in the afternoon of 7 June 2016.  That was a rainy day, but there was only a drizzle when the tests were conducted.  The same or similar vehicles as used in the computer simulations were used for the tests.

38.  The first test was conducted with a Toyota Hiace. It was driven by a driver engaged by the defendants.  The driver drove slowly round New Column F and over the Protruded Area into Lot 397D without any problem although the near side (left) front wheel was quite close to the kerb that enclosed the bottom of New Column F.

39.  For the egress, the vehicle’s initial position was parallel to the Rebuilt Wall.  The driver made a right turn to go through the entrance of Lot 397D.  He then made a three-point turn slowly and carefully to realign the car to point to the Public Way before getting round New Column F and driving away.

40.  The 2nd trial was with a Honda Stream saloon owned by the plaintiff’s son.  The vehicle was driven by a taxi driver who was a stranger to both sides and just happened to be around.  He agreed to assist in the conduct of the tests for a small consideration and after the insurer of the car had given the clearance.  He was obviously new to both the vehicle and the driving path.

41.  For the ingress, the driver conducted it very slowly but without any problem.

42.  For the egress, the vehicle’s initial position was also parallel to the Rebuilt Wall.  After coming out of Lot 397D, the driver also had to make a three-point turn to realign the car to point to the Public Way.  He then attempted to get round New Column F but the rear wheel rim of the car got stuck with the kerb covering the bottom of New Column F.  He had to reverse to make another three-point turn before driving away.  Fortunately, the rear wheel rim suffered no damage.

43.  The need to make the first three-point turn for both cars was obviously because of the location of Column D at the western end of the entrance to Lot 397D.  If this column were not there, the vehicles could have moved further to the west before turning right into the Protruded Area and the first three-point turn could have been avoided.

44.  Regarding the scratching of the rear wheel rim, it was partly contributed to by the presence of people standing at the corner of the wall opposite New Column F watching intensely at the conduct of the trials.  After the rear wheel rim got stuck, these people stood further back to the corner and the vehicle then made a three-point turn slowly but comfortably and drove away without problem.

Danger to pedestrians

45.  Ms Lam submitted that the driving of a car through the Protruded Area has made it dangerous for pedestrians to walk pass that area and they had to stay close to the corner of the walls opposite New Column F to make way for the vehicle.  The scenario described by Ms Lam had indeed happened in the egress test with the 2nd vehicle Honda Stream.  But I do not think that it is really a problem. 

46.  The way over the Protruded Area only leads to Lots 397C and 397D.  The open area in Lot 397D can only accommodate one car.  The open area in Lot 397C can accommodate at most two vehicles.  Hence, the number of vehicles that will go pass this area is very limited.  Furthermore, only people who live in Houses 83A and 83E will walk through this area.  Hence, the number of people walking through this area is also limited.  The occasions when a vehicle and a pedestrian are passing this short way together should be few and far between.

47.  Furthermore, a driver can only drive slowly over the Protruded Area.  He can certainly stop for a short while for the pedestrian to walk pass first or the pedestrian can wait outside the area for the car to go pass first.  If neither the driver nor pedestrian would behave sensibly, the danger anticipated by Ms Lam will still be present even if the right of way is widened as suggested by Mr Lai.  Assessing the situation realistically, I think the anticipated danger is a very remote one and does not justify any remedial measure to deal with it.

Consideration

48.  Having referred to the on-site trial tests and the computer simulations, I note that the right of way round New Column F and over the Protruded Area is just wide enough for private cars to be driven through to the open area in Lot 397D and also for private cars to turn further to the left into the open area in Lot 397C.

49.  However, I would point out that the on-site tests were conducted in relatively fine weather conditions.  There was only a drizzle when the tests were conducted.  I also note that the two drivers had conducted the trials runs with extreme care and drove very slowly.

50.  There is no doubt that drivers must drive with care, but if the conditions of a road should demand the utmost care and attention from the drivers, then this road may not be regarded as reasonably safe for the purpose of driving.  This is particularly so when there is heavy rain and the driver cannot stick his neck out of the window to watch his way or at night when the lighting is poor as there is no street light around.  In such situations, there is a real risk that the vehicle may be damaged in one way or another in the course of being driven through this right of way and in particular when navigating round New column F.  That means the way is not reasonably safe for use as a right of way.

51.  The defendants’ solicitor, Mr Chu has in his closing submissions advised the court that the defendants had since the on-site tests carried out two improvement works; namely:

“(a) installation of mirrors to cover all blind spots to enable the driver to keep track of the distance/space between the vehicle and the walls throughout the ingress and egress manoeuvring (road kerb and the Green Column could be monitored through side mirrors of the vehicle); [and]

(b) trimming of the section of the road kerb that adjoins the Green Column to increase the clearance with the wheels.

52.  However, I do not consider these measures as sufficient to make the right of way safe.  The mirrors are of little use in heavy rain or darkness. The trimming of a few inches of the kerb wrapping round the base of New Column F is insufficient.

Construction work to be carried out

53.  I am fully aware of the dilemma that if I should require the widening of the way, it will be at the expense of the defendants who will lose their exclusive possession of the widened part.  However, if they have agreed to give a right of way to the plaintiff, it must be a safe way.

54.  Though I consider that the way should be widened to make it safe, I do not think it has to be widened by pushing New Column F to the east by 1.3 m (or 51 inches) as suggested by Mr Lai (pp 378 and 429).  That will allow ordinary private cars to go round New Column F at one go and with a clearance of 300 mm (or 11.80 inches) on each side.  That is too generous bearing in mind that this is a short way and in a village area where the roads are narrow and winding and drivers should drive slowly.  Drivers often have to stop or reverse to make way for on-coming traffic too.

55.  Balancing the conflicting interests, I think it is fair and just to require the relocation of New Column F eastward by 20 inches. That will make the right of way including the turning round of New Column F safe for the use of any ordinary private car though, depending on their driving skill, drivers at times may still have to make a three-point turn to get round the column.

56.  I am also not concerned about the suitability of the way for any particular model of vehicle as currently used by the plaintiff or his son.  The right of way is for the driving of a private car.  Hence, it should be suitable for any ordinary private car.

57.  Regarding New Column E and the Rebuilt Wall, Mr Lai’s conclusion is that they should both be moved to the east for 0.4 metre (or 16 inches).

58.  The entrance to Lot 397D is guarded by the Rebuilt Wall on one side and Column D on the other.  It is wide enough for vehicles to go into and out of Lot 397D.  However, the presence of Column D on the western side necessitates the drivers to swerve more to the right in coming out of Lot 397D. This swerving in turn creates the need to do a three-point turn on the Protruded Area to align the vehicle towards the Public Way.  The problem is thus created by the presence of Column D. 

59.  From the simulation sketches produced by Mr Lai show that the removal of the plaintiff’s Flower Bed from the open area of Lot 397D will further enhance the ease of driving through its entrance onto the Protruded Area and over to the Public Way. 

60.  Subject to the moving of New Column F eastward for 20 inches, the right of way is wide enough for any ordinary private car to go in and out of Lot 397D.  The need to do a three-point turn (or a seven-point or nine-point turn in the computer simulations) in the egress is partly caused by the presence of the plaintiff’s Column D and Flower Bed.  I do not think it fair to require the defendants to sacrifice more by relocating Column E and the Rebuilt Wall when the problem can be solved by removing Column D with further enhancement by removing the Flower Bed.  If the plaintiff would like to keep Column D and the Flower Bed at where they are, then he has to make the turns when driving out from his lot.  It is a choice open to him.

Order of relocation of Column F and kerb

61.  Having come to the above conclusions, I order that the defendants do relocate New Column F by 20 inches straight to the east and realign the kerb accordingly at their own costs within 48 days from the date hereof.

62.  After the defendants have complied with the above order, the plaintiff will be at liberty to engage a surveyor to prepare a survey plan recording the positions of the kerb, New Column F after the relocation, New Column E and the Rebuilt Wall.  The plaintiff may also register this plan with the consent order above-mentioned at the Land Registry as an order giving him the right of way.

63.  I do not intend to make any order permitting the plaintiff or requiring the defendants to mark any measurement or location of anything by colour nails on Lot 397C.  I do not think it is necessary to have such colour nails to be nailed on the defendant’s lot.  The survey plan that the plaintiff may prepare and register at the Land Registry will be enough to protect his interest in the right of way.

The new gate

64.  The matters remaining in the consent order are for the defendants to provide the plaintiff with a quotation of the costs from a contractor for relocating the plaintiff’s metal gate and Columns C and D (or if Column C has been destroyed by the defendant in the removal, remake it in the same dimension and position it wholly within Lot 397D) and for the plaintiff to engage the contractor to carry out these works.

65.  The plaintiff has been asked whether he would still require the defendants to perform this obligation if the court would not order the relocation of New Column E or the cutting short of the Rebuilt Wall.  The plaintiff has advised the court that if New Column E and the Rebuilt Wall are not to be moved, he would not require the defendants to discharge the above obligation, but he would like to acquire and install at the entrance to Lot 397D a sliding gate of his design and/or choice at the defendants’ costs including the costs for digging a grove for the gate subject to a maximum of HK$31,800.

66.  The defendants have also advised the court that if New Column E and the Rebuilt Wall are not to be moved, they would agree to bear the costs for the plaintiff to acquire and install a sliding gate at the entrance to Lot 397D including the costs for digging a grove for the gate at HK$31,800 with adjustment for inflation for three years.  They proposed an adjustment rate of 8% per annum.  I think that is in excess of actual inflation.  I consider that the sum adjusted for inflation should be in the region of HK$36,000.

67.  Though the defendants have agreed to pay for the sliding gate, they through their solicitor Mr Chu have raised in further submissions the issue of safety for installing such a gate behind and running parallel to the Rebuilt Wall.  They suggested that the plaintiff could consider installing a cantilever sliding gate.  However, there is no expert evidence saying that such gate cannot be installed safely there.  In any event, it is a gate to be installed by the plaintiff. Hence, the plaintiff, or his contractor has the duty not to install it negligently. The plaintiff may of course take up the defendants’ suggestion and install a cantilever sliding gate also at the defendants’ costs subject to a maximum of HK$36,000.

68.  The defendants in addition also proposed that the plaintiff may build a top mounted vertical roller shutter gate instead of sliding gate.  They also agree to bear the costs for acquiring and installing such a gate including the costs for building a New Column C to support the gate up to a maximum of HK$60,000.

Order for the new gate

69.  In the light of the offers by the defendants and the fact that the plaintiff does not want the defendants to perform §1(d) of the consent order, I make the following orders in place and in discharge of §1(d) of the consent order.

70.  I order that the plaintiff may, within three months after the completion by the defendants of the relocation of New Column F and the kerb ordered above, acquire and install a sliding gate or cantilever sliding gate of his own design and/or choice and in such event, the defendants shall reimburse the plaintiff the costs for acquiring and installing such gate and for digging the necessary grove up to a maximum of HK$36,000 and to pay the said sum or instalment of the same within two weeks upon being advised by the plaintiff of the plaintiff’s receipt of the relevant invoice(s) from the plaintiff’s contractor.

71.  I further order that the plaintiff may, in the alternative to installing a sliding or cantilever sliding gate, choose to install a top mounted vertical roller shutter gate with the construction of a new supporting column as suggested by the defendants in §§4 to 6 of their further submissions dated 31 August 2016 and that the terms of the above order for the sliding or cantilever sliding gate shall apply to this order subject to substituting HK$60,000 for HK$36,000.

Costs order nisi

72.  On the question of costs, I have to consider the conduct of the parties.

73.  After the plaintiff had issued the first summons on 19 September 2013 seeking relocation of New Column E and F each for 1.7 metres to the east, rebuilding the Original Wall and performance of §1(d) of the consent order, the defendants’ solicitors made on 11 November 2013 a sanctioned offer (which has now been disclosed to the court) offering a partial concession to relocate New Column F eastward for 20 inches. 

74.  However, the offer requires a warranty from the plaintiff that the additional surface area made available by the relocation would be structurally strong enough for vehicles to go over it.  I do not see why the plaintiff should provide such warranty.  The consent order only requires the defendants to give the plaintiff the right of way, it does not require any such warranty from the plaintiff.

75.  Furthermore, the defendants, in making this offer of partial concession, were not offering any costs incurred by the first summons. They instead proposed no order as to costs.

76.  My order for relocation today is more or less in the same terms as offered by the defendants in the sanction offer.  If the defendants should have offered the relocation concession without demanding the warranty and have also offered at least half of the costs of the first summons, then their position on costs today would be much better.  The fact that they had to offer relocation of New Column F for 20 inches showed that the first summons was not groundless though it had asked for too much.  It was the defendants’ conduct in making the area for the right of way too narrow that had necessitated the summons.  My relocation order today also vindicates the issuance of the first summons.

77.  Regarding the conduct of the plaintiff, he was asking for too much in his first summons.  But it was right for him to have issued the second summons.  Nevertheless, he, after having obtained the report of the traffic engineer Mr Lai, was not contented with what he had asked for in the second summons. He instead relied on Mr Lai’s report and insisted on a relocation of New Column F for 1.3 m (or 51 inches) and relocation of New Column E and cutting short of the Rebuilt Wall by 0.4 metre (or 16 inches).  He also refused the defendants’ suggestion of conducting on-site trial tests to find out on the ground how much the right of way has to be widened.  Such attitude was unreasonable and not conducive to a reasonable dialogue between the parties.  In the end, a full hearing was required and the resolution of the dispute much delayed adding to the agony of the parties.

78.  Since neither party has behaved reasonably, I consider that the proper course to take is to make no order as to costs.  I therefore make a costs order nisi that there be no order as to costs.

 (Louis Chan)
 Judge of the Court of First Instance
  High Court

Miss Yanky S Y Lam, instructed by George Y C Mok & Co, for the plaintiff

Mr Raymond Chu, of Raymond Chu & Co, for the 1st and 2nd defendants

82162-EN-2012-06-04

LEE YUM SANG v. YEUNG FOOK HONG AND ANOTHER

HTML content

HCA 638/2009

IN THE HIGH COURT OF THE

HONG KONG SPECIAL ADMINISTRATIVE REGION

COURT OF FIRST INSTANCE

ACTION NO 638 OF 2009

-------------------------------

BETWEEN

 LEE YUM SANGPlaintiff

and

 YEUNG FOOK HONG1st Defendant
 LEUNG YUK SIN2nd Defendant

-------------------------------

Before: Mr Recorder A. Chow, SC in Chambers

Date of Hearing: 4 June 2012

Date of Reasons for Decision: 4 June 2012

-------------------------------------------------------

REASONS FOR DECISION

-------------------------------------------------------

 

Application

1.  I have before me an application taken out by the defendants by summons dated 7 December 2011 (the “Summons”) seeking various orders or directions arising out of a Consent Order previously made by Deputy High Court Judge L Chan on 1 June 2011 (the “Consent Order”).  The basis of the application, as appears from the Summons, is said to be the Consent Order and the inherent jurisdiction of the court.

Background

2.  The plaintiff and the defendants are the owners of three neighbouring lots of land in the New Territories, namely, (i) Section D and (ii) Section C and the Remaining Portion of Lot 397 in Demarcation District 94 respectively (hereinafter referred to as “Lot 397D”, “Lot 397C” and “Lot 397RP” respectively).  The present action was commenced by the plaintiff by Writ on 6 March 2009.

3.  The background facts and the nature of the disputes between the parties are set out in a written Judgment on Costs by Deputy High Court Judge L Chan dated 3 June 2011 and I shall not repeat them in this decision.

4.  The trial of this action was scheduled to commence on 1 June 2011.  On the first day of the trial, the parties reached a settlement of their disputes the terms of which were embodied in the Consent Order.  The only outstanding matter was the issue of costs, which was resolved by the learned Deputy Judge in his Judgment on Costs.

5.  The Consent Order provides for various acts to be done by the parties.  For the present purpose, the following parts of the Consent Order are material:

“1. In respect of the Partitioning Wall between Lot 397C and Lot 397D and the Slope within 397C,

(a) The Plaintiff shall at his own costs and expenses demolish the Slope (as defined in the Amended Reply and Defence to Counterclaim) on the [Protruded] Area (as defined in the Amended Reply and Defence to Counterclaim) within Lot 397C forthwith but no later than 1 August 2011.

2. Further,

……

(b) The current slope built by the Plaintiff within 397C shall be removed at the Plaintiff’s expenses, and no slope is allowed to be built on the Protruded Area.

(c) The 1st and 2nd Defendants shall continue to maintain and repair the Public Way for public use at the 1st and 2nd Defendants’ own costs and expenses in accordance with the Building Licences in respect of Lot 397C and Lot 397RP.

(d) The 1st and 2nd Defendants shall grant (free of consideration) a right to the Plaintiff, his successors and assigns to discharge rain water (and rain water only) to the rain drainage channel in and underneath Lot 397C.

(e) For the avoidance of doubt, no sewage water (such as flushing water and greasy water from kitchen) shall be discharged to the rain drainage in and underneath Lot 397C.

4. Liberty to [apply].”

6.  There are disputes between the parties as regards what either party may or may not do, or is or is not required to do, under the Consent Order, or the implementation of the Consent Order. Accordingly, the defendants have taken out the Summons to seek the Court’s directions or orders as set out therein.

Paragraphs 1 and 3 of the Summons

7.  These two paragraphs relate to the defendants’ allegation that the plaintiff has, notwithstanding the Consent Order, continued to discharge sewage water to the rain drainage in and underneath Lot 397C. This allegation is disputed by the plaintiff.

8.  By paragraph 1 of the Summons, the defendants seek an order that the plaintiff shall be restrained from discharging anything other than rain water to the rain drainage in and underneath Lot 397C, in accordance with paragraph 2(e) of the Consent Order, and by paragraph 3 of the Summons, the defendants seek an order that the plaintiff shall not, whether directly or indirectly through some other routes, discharge any sewage water to the rain drainage in and underneath Lot 397C.

9.  In my view, it is perfectly plain, from paragraphs 2(d) and (e) of the Consent Order, that the plaintiff has no right to discharge anything other than rain water to the rain drainage in and underneath Lot 397C.  In particular, the plaintiff has no right to discharge sewage water (whether filtered or not) to such drainage.  Miss Yanky Lam for the plaintiff does not dispute this proposition.

10.  However, if it is the defendants’ position that the plaintiff has in fact discharged sewage water to the rain drainage in and underneath Lot 397C contrary to the terms of the Consent Order (which is disputed by the plaintiff), the defendants’ proper remedy is to apply to cite the plaintiff for contempt of court, and not to seek any injunction against the plaintiff.

11.  Once an action has been settled and the settlement has resulted in the making of a consent judgment or order of the Court, the original causes of action of the parties are merged in the judgment or order.  I am not satisfied that the Court has any further jurisdiction to grant an injunction against the plaintiff in the current circumstances.

12.  I should make it clear, however, that I am not making any determination as to whether the plaintiff would be liable for contempt of court should it be proved that the plaintiff has discharged sewage water to the rain drainage in and underneath Lot 397C after the making of the Consent Order.  That is not a matter before me and will have to be determined as and when an application (if any) is made by the defendants to cite the plaintiff for contempt of court.  I merely rule that I do not consider that the defendants are entitled to the relief sought in paragraphs 1 and 3 of the Summons.

Paragraphs 2 and 4 of the Summons

13.  By paragraph 2 of the Summons, the defendants seek the following direction or order:

“(1) The Plaintiff has no right under the [Consent Order] to construct any channel, drainage or manhole in the Protruded Area ...;

(2) The Plaintiff do within 14 days remove or fill up any channel, drainage or manhole constructed in the Protruded Area”.

14.  By paragraph 4 of the Summons, the defendants seek the following direction or order:

“(1) The Plaintiff has no right under the [Consent Order] to install any metal plate in or underneath the Protruded Area.

(2) The Plaintiff do within 14 days remove any metal plate in and underneath the Protruded Area and carry out all the necessary works to cover the surface of the Protruded Area.”

15.  There is a dispute of fact as to whether the plaintiff has constructed any channel or drainage in the Protruded Area, although the plaintiff admits that he has constructed a manhole on, and installed metal plates in or underneath, the Protruded Area.  The plaintiff says that the channel or drainage complained of by the defendants is part of a pre-existing public drainage or channel embedded in the ground of Lot 397C. In so far as the manhole and metal plates are concerned, the plaintiff’s case is that the construction or installation of the manhole and metal plates form part and parcel of the necessary works for the removal of the Slope by the plaintiff under the Consent Order and for the restoration of the road surface of the Protruded Area to a reasonably safe state and condition as impliedly required by the Consent Order.  The plaintiff further says that the Consent Order is silent on the restoration of the road surface after the removal of the Slope on the Protruded Area but it is common sense and implied in the Consent Order that the plaintiff should do so at his own costs and expenses.

16.  The Consent Order requires the plaintiff to remove the Slope but does not make provision for the restoration of the road surface or what may or may not be done by the plaintiff to restore the road surface.  In my view, the making good of the road surface should be regarded as something reasonably incidental to the requirement to remove the Slope on the Protruded Area by the plaintiff and is to be implied.  However, details of what may or may not be done by the plaintiff in the carrying out of the restoration works are not defined or set out in the Consent Order.

17.  The Consent Order represented and embodied the terms of settlement reached by the parties and was, as I have been told and would expect in any event, carefully drafted by counsel for the parties.  It is not for this Court to re-write, or add to, the terms of the settlement reached by the parties.  The Consent Order does not authorise the plaintiff to construct or install the manhole or the metal plates, but neither does it prohibit the plaintiff from doing so.

18.  In my view, if the construction or installation of the manhole and the metal plates are to be treated as part of the works reasonably necessary for the restoration of the road surface of the Protruded Area, the defendants have no cause for complaint.  On the other hand, if the construction or installation of the manhole or the metal plates cannot be justified as being works reasonably necessary for the restoration of the road surface of the Protruded Area, the defendants may have a separate cause of action against the plaintiff, on the basis that works have been carried out by the plaintiff in or on the defendants’ land without their consent.  I say nothing about the viability of such cause of action.  The defendants are clearly not entitled to obtain any relief under the current Summons in respect of such possible cause of action, but would have to pursue it (if so advised) in a separate action against the plaintiff.

Paragraph 5 of the Summons

19.  By paragraph 5 of the Summons, the defendants seek the following direction or order:-

“The relocation of the Plaintiff’s metal gate and the 2 concrete columns for the anchoring of the metal gate pursuant to paragraph 1(d) of the [Consent Order] be carried out such that both the metal gate and the 2 concrete columns be within Lot 397D as shown in Annex IV to the Defence and Counterclaim, being a surveyor’s plan in scale and relied on by this Court in paragraph 1(c) of the [Consent Order]”.

20.  Miss Yanky Lam does not dispute that this should be so, and I do not think any order or direction is required to be made.  There are, I understand, other disputes between the parties, including a suggestion by the plaintiff that the defendant has proposed to install their own gate at the Protruded Area which would adversely affect the plaintiff’s right of way as provided for in paragraph 2(a) of the Consent Order.  However, there is no application before me on those other disputes and it would not be appropriate for me to make any comment on them.

Paragraph 6 of the Summons

21.  By paragraph 6 of the Summons, the defendants seek the following direction or order:

“The Plaintiff shall properly level the Protruded Area so that no water puddles be formed”.

22.  It is not in dispute that the plaintiff has levelled the Protruded Area.  The defendants complain that the works have not been done properly and as a result water puddles are formed when there is rain.  This allegation is disputed by the plaintiff.  I have seen photographs of the current state of the Protruded Area, including photographs taken by the defendants on 29 September 2011 which show the existence of a relatively minor water puddle at the boundary between Lot 397C and Lot 397D, which appears to be a low point between the grounds on either side.  Judging from the photographs, it seems to me that the levelling of the ground has been carried out to a standard which can reasonably be expected in the circumstances.  I also note that under paragraph 2(c) of the Consent Order, the obligation to maintain and repair the Public Way for public use falls on the defendants.

23.  I am not satisfied that the defendants have made out their complaint which would justify relief being granted under paragraph 6 of the Summons.

Conclusion

24.  In all, I would dismiss the Summons and I shall now hear the parties on the question of costs.

(A. Chow, SC)
Recorder of the Court of First Instance
High Court

Ms Yanky Lam, instructed by George Y C Mok & Co., for the plaintiff

Mr Lam Chin Ching Gary, instructed by Lo, Wong & Tsui, for the 1st and 2nd defendants

76843-EN-2011-06-03

LEE YUM SANG v. YEUNG FOOK HONG AND ANOTHER

HTML content

HCA 638/2009

IN THE HIGH COURT OF THE

HONG KONG SPECIAL ADMINISTRATIVE REGION

COURT OF FIRST INSTANCE

ACTION NO. 638 OF 2009

____________

BETWEEN

 LEE YUM SANGPlaintiff

and

 YEUNG FOOK HONG1st Defendant
 LEUNG YUK SIN2nd Defendant

____________

Before: Deputy High Court Judge L. Chan in Court

Date of Hearing: 1 June 2011

Date of Judgment on Costs: 3 June 2011

__________________________

JUDGMENT ON COSTS

__________________________

 

1.  This judgment is on costs only as all claims and counterclaims have been settled on the first day of the trial.

2.  The plaintiff and the defendants are neighbours.  The 1st and 2nd defendants are husband and wife.  The dispute arose mainly out of a right of way from a public access road over the land of the 2nd defendant to the land of the plaintiff. 

Background

3.  The plaintiff used to be the sole owner of Lot 397 in Demarcation District 94 (“the Lot”), having been given the same as a gift by his father on 10 October 1987. 

4.  On 24 April 1993, the plaintiff entered into a deed of exchange with Messrs Lee Chi Fai, Chan Chi Shing, the 1st defendant and one Rank Chance Development Limited (“Rank Chance”), and they became tenants in common of the Lot.  The shareholders and directors of Rank Chance were the 1st defendant and Chan Chi Shing.

5.  By a deed poll of the same date but made subsequent to the deed of exchange, the tenants in common divided the Lot into sections A, B, C, D and the remaining portion (“RP”) of the Lot. 

6.  By an assignment dated 11 August 1994, the plaintiff assigned all his interests in sections A, B, C and RP to his fellow tenants in common in return for their assignment to him of all their interests in section D. 

7.  Section D is encircled by section C to the north, section B to the east and other privately owned lots to the south and the west.  It is completely landlocked.  It could have access to the public road system either through section B or section C. 

8.  Section B is relatively small comparing with the other sections of the Lot.  If access from section D to the public road should be over section B, the shortest way is from the western end of section B to its eastern end.  A right of way over section B will substantially affect its use and occupation. 

9.  On the other hand, section C is much larger than section B.  Its shape looks like a trapezoid with a narrow edge pointing to the west.  Access from section D to a public access road can be had over the narrow edge of section C.  Such a way for section D will produce less effect on the use and occupation of section C.

10.  After the assignment of section D to the plaintiff on 11 August 1994, the remaining tenants in common further assigned section C to one Lee Chi Wai on 13 December 1994.  Lee Chi Wai was a nephew of the plaintiff who had already passed away in October 2004. There is no dispute that Lee Chi Wai in fact held the interests in section C on trust for the 2nd defendant. 

11.  The plaintiff was granted a building licence by the District Land Office on 30 January 1995 for him to build a three-storey small house on section D.  He then set about to build a small house and completed it sometime in mid-1996.  He also made a way over the western tip of section C for access by car and on foot from section D to a public access road. 

12.  The way is coloured yellow on a lot index plan produced in annex 2 of the amended defence and counterclaim.  Part of the public access road adjoining the way built by the plaintiff on section C is also within section C.  This is coloured purple on a lot index plan produced in annex 1 of the amended defence and counterclaim.  The public access road land runs from section C into RP and then enters government land.  The part of the public access road in RP is coloured red on a lot index plan produced in annex 3 of the amended defence and counterclaim.  This public access road had been used by the villagers of Hang Tau Village for decades before the plaintiff had become the sole owner of the Lot.

13.  With the way over the western tip of section C and the public access road on both sections C and RP, the plaintiff could have access from section D to the public road system. 

14.  However, the plaintiff also laid an underground drainpipe running from section D through the western tip of section C and discharged to an open rain channel that runs also inside but to the northwestern edge of section C.  The defendants claim that they were unaware of this drainpipe until they dug open the ground at the western tip of section C on about 19 February 2009.

15.  The District Land Officer also granted a building licence to each of the owners of sections C and RP on 4 July 1996. The two building licences impose an obligation on the licensees to keep and maintain the existing public access road as it runs through sections C and RP.

16.  The building of small houses on sections C and RP was completed in about the end of 1996 to early 1997, and the houses were then occupied.  Section C was assigned to the 2nd defendant on 30 October 2002 by Lee Chi Wai, and RP was assigned to the 1st defendant on 25 March 2003.

17.  Regarding the plaintiff’s small house on section D, the DLO refused to issue a certificate to certify its compliance with the terms of the building licence.  The reason being that it had trespassed onto section B to its east by about 7 square metres.  The plaintiff then pulled down this small house and rebuilt it within the boundary of section D in 2001.

18.  The defendants alleged that the plaintiff, in rebuilding his small house, had elevated the ground by some 20 inches.  In order to continue using the way at the western tip of section C, the plaintiff then built a ramp leading from the gate of section D over the way and onto the public access road. 

19.  The plaintiff denied this allegation and insisted that he had not elevated the ground in rebuilding the house and that the ramp was there since he had built the first house in 1996.  In any case, the plaintiff and his family continued to use the ramp over the way and the public access road for access on foot and by vehicle to the public road system.

The disruption of the plaintiff’s access

20.  This was, however, brought to an abrupt halt on about 19 February 2009 when the defendants suddenly dug up the ramp and part of the public access road lying within section C.  The big pieces of broken cement and concrete lying on the way and part of the access road adjoining it made it difficult for people to walk along and impossible for vehicles to pass through the way and the public access road.

This action and the plaintiff’s application for injunction

21.  The plaintiff’s solicitors then issued a demand letter to the defendants requiring restoration and threatened to seek an injunction to compel them to do so.  The demand was ignored.  The plaintiff then issued this action and a summons for an injunction on 6 March 2009.  The summons came before Deputy High Court Judge To (as he then was).  The defendants then gave interim undertakings not to interfere with the plaintiff’s reasonable enjoyment of the way and the public access road or to prevent the plaintiff from restoring the way and the public access road.  Upon these undertakings, the plaintiff’s summons was adjourned and eventually not pursued with save that costs of the summons be in the cause.  The action then continued.

22.  The defendant engaged a surveyor in the preparation of his defence.  The surveyor found that part of section C is enclosed by a boundary wall to the side of section D.  Hence, the plaintiff has been trespassing a small part of section C since about the end of 1996 to early 1997 when the wall was built.  But the wall was built by the defendants and it was the fault of their contractor in positioning the wall within section C rather than on the boundary.

The issues

23.  The joinder of issues on the pleadings showed that there were four issues between the parties (which have now been settled):

(1)  whether the plaintiff had a right of way over the western tip of section C on which there is a ramp (as restored by the plaintiff after the hearing before deputy Judge To);

(2)  even if the plaintiff was entitled to the right of way, whether the plaintiff was entitled to keep the ramp over the way;

(3)  whether the plaintiff was entitled to keep the drain which ran underground through section C and discharged into the open rain drain in section C for discharge of waste water from section D;

(4)  whether the plaintiff had trespassed into section C by virtue of the enclosure of part of it into section D by the defendants’ boundary wall.

24.  For the last issue, the plaintiff never resisted the defendants’ claim for recovery of land.  The only issue was that the problem was created by the defendants.  The plaintiff also wanted the defendants not to cause damage to the plaintiff in rectifying the situation, in particular to the plaintiff’s drains and pipes which are underneath the plaintiff’s boundary wall.  Further, the eastern side of the plaintiff’s gate guarding the entrance to section D is affixed on this wall, and the other side of the gate is affixed by reference to the position of the eastern side.  The rebuilding of the defendants’ wall will necessitate the re-fixing of the plaintiff’s gate, and the plaintiff will require the defendants to be responsible for such costs.

The alleged verbal promise/guarantee and the use of the ramp

25.  In order to justify the right of way over the way in section C and the right to keep the drain that ran underneath section C, the plaintiff pleaded in his amended reply and defence to counterclaim (rather than the statement of claim) that when he executed the assignment on 11 August 1994 to obtain section D, his then fellow tenants in common had verbally promised him or given him a verbal guarantee that he would be permitted to lay a drain and electricity wires and have a right of way on foot and by vehicles over the other sections of the Lot.  It was only because of this promise by them that he had agreed to accept the otherwise landlocked section D.  Hence, the 1st defendant was estopped from denying the plaintiff’s right of way over section C and to have the drain running through section C.  Furthermore, the defendants had knowingly permitted the plaintiff to use a right of way over the way, and the plaintiff enjoyed the right by necessary implication or acquiescence.

26.  In order to justify the keeping of the ramp on section C to facilitate the passing of vehicles over the way, the plaintiff also pleaded that he had been using the ramp uninterrupted since 1996 and that he could not use the way without the ramp.

The defendants’ counter-allegation

27.  The defendants denied the alleged verbal promise/guarantee of right of way and right to lay cables and drain.  The 1st defendant alleged in his witness statement that after the plaintiff had built his house in section D in 1996, the plaintiff had to use the way on section C for access. Furthermore, the plaintiff’s house had trespassed over part of section B which adversely affected the value of the house on section B.  Section B was then registered in the name of one Yip Wong Yau who held it on trust for the 1st defendant and Chan Chi Shing.  The plaintiff’s wall separating section D from section C (which was built by the defendants) also trespassed over part of section C.

28.  The 1st defendant further alleged that after discussion between the plaintiff, Chan Chi Shing and the 1st defendant, it was agreed that the plaintiff would pay $800,000 for the use of the way as an access and also as compensation for his trespass over sections B and C.  But the plaintiff never paid this sum.  This allegation was denied by the plaintiff. 

Discussion on the merits

29.  I think the plaintiff can have a right of way either over section B or C.  It is a right of way implied by necessity.  I refer to the statement of principle by Lord Oliver of Aylmerton in Manjang v Drammeh (1990) 61 P & CR 194 at 196 to 197:

“It seems hardly necessary to state the essentials for the implication of such an easement. There has to be found, first, a common owner of a legal estate in two plots of land. It has, secondly, to be established that access between one of those lots and the public highway can be obtained only over the other plot. Thirdly, there has to be found a disposition of one of the plots without any specific grant or reservation of a right of access. Given these conditions, it may be possible as a matter of construction of the relevant grant (see Nickerson v Barraclough [1981] Ch 426) to imply the reservation of an easement of necessity.”

30.  When section D was assigned to the plaintiff on 11 August 1994, there was no express reservation of right of way over the other parts of the Lot.  Section D was enclosed by sections B and C which were then owned by the same tenants in common.  The plaintiff as the transferee of part of the interests in section D should thereby obtain a way of necessity over either section B or C.  To have the way over section C appeared to be more convenient to all concerned and produced smaller adverse effect to the owners of sections B and C.  The way over section C was indeed made and used since sometime in mid-1996, and the 1st defendant continued to have an interest in section B until 29 September 1997 when the house on it was sold to different owners.

31.  I thus expressed my view to the parties at trial that the plaintiff would be entitled to a right of way over the area over the way in section C as coloured yellow on the lot index plan in annex 2 of the amended defence and counterclaim.  Since this way is a right of way by necessity, the plaintiff need not rely on the alleged verbal promised/guarantee to justify his entitlement.  This alleged promise/guarantee is therefore irrelevant insofar as the right of way is concerned.

32.  Mr Lam, counsel for the defendants, referred to Adealon International Corp Proprietary Limited v Merton London Borough Council [2007] 1 WLR 1898 and submitted that the presumption was that any rights the grantor required over land transferred would have been expressly reserved in the grant.  Counsel further pointed out that the plaintiff was a grantor of his interests in section C to his then fellow tenants in common, and the presumption operated against him.

33.  This submission certainly has support from Adealon International Corp.  However, it ignores the fact that the plaintiff was the grantee of a significant interest in section D and thus was entitled to a right of way by necessity.  I disagree with the submissions of counsel for the defendants.

34.  Regarding the ramp built on the way, the plaintiff’s only justification for it is that he had been given uninterrupted use of it by the defendants since 1996 and he could not use the way without the ramp.  He has not pleaded the alleged verbal promise/guarantee to include the ramp.  Hence, there was no basis for any contractual or proprietary estoppel claim for the ramp.  The mere fact that the plaintiff had been allowed to use it since 1996 to early 2009 is not enough to ground him any right to it.  As the defendants have since early 2009 been objecting to the continued existence of the ramp, I think the plaintiff has no choice but to remove it.  I also think that the plaintiff can build his own ramp inside section D as this section has a large open area behind its entrance gate and there is more than enough space for a ramp to be built there.

35.  Regarding the drainpipe, the plaintiff confirmed through counsel that, save the foul in the water closet, all waste and dirty water from his house would pass through the drainpipe and discharge into the open rain drain in section C.  This is in fact contrary to clause 31 of the building licence granted for the building of the small house on section D. Clause 31 reads:

“31. The Licensee shall not discharge directly or indirectly or cause or permit or suffer to be discharged into any public sewer, storm-water drain, channel, stream-course or sea any trade effluent or foul or contaminated water or cooling or hot water without the prior written consent of the Director of Environmental Protection, who may as a condition of granting his consent require the Licensee to provide, operate and maintain at the Licensee’s own expense, within the lot or otherwise and to the satisfaction of the Director of Environmental Protection suitable works for the treatment and disposal of such trade effluent or foul or contaminated or cooling or hot water.”

36.  Hence, even if there were the alleged verbal promise/guarantee to allow the plaintiff to lay the drainpipe across section C, public policy would not have required enforcement of it as it is contrary to clause 31 of the building licence and creates a health hazard.

The open offer

37.  I should also mention that the defendants on 3 May 2011 made an open offer[1] to the plaintiff.  The defendants by the open offer stated that they would be prepared to take down the wall between sections C and D and to build a new one on the correct boundary at their own costs.  They would also grant the plaintiff a right of way at the existing way but without the ramp which the plaintiff has to remove at his own costs.  The plaintiff could build a drain running through section C for discharge of rainwater only into the open rain drain.  There should also be no order as to costs for the action and the counterclaim.  This open offer could only be accepted en bloc. 

The settlement

38.  The plaintiff did not find this offer acceptable, and the action continued to trial.  On the first day of the trial and after I had expressed my views on the merits of the four issues as summarised above, the parties proceeded to negotiate again.  They eventually settled on the terms that the plaintiff should at his own costs take away the ramp on the way no later than 1 August 2011.  The defendants should then at their own costs take down the existing wall between sections C and D and build a new one on the correct boundary between the two sections.  After the new wall has been built, the plaintiff should engage a contractor to be recommended to him by the defendants to affix his metal gate onto the new anchorage at the defendants’ cost.  The defendants shall grant the plaintiff, his successors and assigns a right of way over the way.  The defendants shall also grant the plaintiff, his successors and assigns a right to discharge only rainwater through the drainpipe underneath section C.  The parties also agreed to discontinue the action and the counterclaim.  The settlement, however, does not deal with the issue of costs which is for me to decide.

Discussion on costs for the application for injunction

39.  Counsel for the plaintiff submitted that the plaintiff should be given the costs of the action, in particular the costs of the application for injunction.  Counsel for the defendants resisted and said that the plaintiff had not succeeded in all the issues.

40.  Though the settlement terms bear a close resemblance to the open offer, I do not think the plaintiff’s entitlement to costs should be adversely affected by the open offer.  The facts of the case do not justify no order as to costs and it is unfair to require the plaintiff to bear all his costs, in particular the costs incurred in applying for the injunction.

41.  Regardless of the merits of the claims and the counterclaims, it was certainly wrong for the defendants to have dug up the ramp and the part of the public access road on section C without any prior notice to the plaintiff.  The consequence of that was obvious.  It created immense difficulties for the plaintiff and his family in gaining access to the public road system.  The defendants themselves suffered no inconvenience as their access to the public road was via another way at the other end of section C and through RP.  Even if the defendants were entitled to cut off the plaintiff’s access, they should not have done so in the way they did it. That was taking the law into their own hands.  This should be discouraged. They should have sought a declaration from the court before taking any step to cut off the access.

42.  Furthermore, I think the plaintiff is entitled to a right of way on the way, and it was certainly wrong for the defendants to have cut it off without notice.  I also make it clear that the defendants were not merely trying to take away the ramp.  They were trying to stop the access through the way.  I think the conduct of the defendants in digging up the ramp and the part of the public access road on section C justified and necessitated the plaintiff’s application for an injunction. 

Judgment on costs for the application of injunction

43.  I therefore order that the defendants do pay the plaintiff the costs of the application for injunction to be taxed.

Discussion on the remaining costs

44.  Regarding the remaining costs of the action and the counterclaim, though the plaintiff has failed in the issues of the ramp and the drain as he could no longer discharge dirty water through the drain, he has indeed succeeded in the most important issue, namely, the right of way.  He can now continue to enjoy access from section D to the public road system though he will have to build a ramp within section C.  For the trespass to section C as caused by the wall built by the defendants, I do not think the plaintiff should be blamed. 

Judgment on the remaining costs

45.  I therefore consider it fair that the plaintiff should have half of the remaining costs of the action and the counterclaim.  I therefore order that the defendants do pay the plaintiff half of the remaining costs of the action and counterclaim to be taxed.

(L. Chan)
Deputy High Court Judge

Ms Yanky Lam, instructed by George Y C Mok & Co., for the Plaintiff

Mr Lam Chin-ching, Gary, instructed by Messrs Lo, Wong & Tsui, for the 1st and 2nd Defendants


[1]  Foskett, The Law and Practice of Compromise, paragraphs. 18-09 to 18-11.