HK CourtDB
HomeDirectoryMCP
Hong Kong CourtDB
Back to directory
Civil Action2012

SNE ENGINEERING CO LTD v. CHIM KEE MACHINERY CO LTD

Related cases with same parties

  • CACV101/2016SNE ENGINEERING CO LTD v. CHIM KEE MACHINERY CO LTD
  • CACV88/2014SNE ENGINEERING CO LTD v. HSIN CHONG CONSTRUCTION Co LTD AND ANOTHER
  • HCA1312/2012ELITT ENGINEERING CONSULTANTS LTD v. SNE ENGINEERING CO LTD
  • HCA1466/2012SNE ENGINEERING CO LTD v. HSIN CHONG CONSTRUCTION CO LTD AND ANOTHER
  • HCA2025/2012SNE ENGINEERING CO LTD v. CHIM KEE MACHINERY CO LTD
  • HCA603/2012ELITT ENGINEERING CONSULTANTS LTD v. SNE ENGINEERING CO LTD
  • HCCW308/2012CHIM KEE MACHINERY CO LTD v. SNE ENGINEERING CO LTD

Files (2)

84713-EN-2012-12-06

SNE ENGINEERING CO LTD v. CHIM KEE MACHINERY CO LTD

HTML content

HCA 1313/2012

IN THE HIGH COURT OF THE

HONG KONG SPECIAL ADMINISTRATIVE REGION

COURT OF FIRST INSTANCE

ACTION NO 1313 OF 2012

____________

BETWEEN

 SNE ENGINEERING CO. LTDPlaintiff

and

 CHIM KEE MACHINERY CO., LTDDefendant

____________

Before: Hon Chung J in Chambers
Date of Hearing: 15 November 2012
Date of Decision: 6 December 2012

______________

D E C I S I O N

______________

 

INTRODUCTION

1. This is the plaintiff’s application for leave to appeal to the court of appeal.  The subject-matter of the intended appeal was the costs order I made on 23 August 2012 (“the said costs order”).  By the said costs order, costs of the ex parte injunction order and the inter partes injunction order were awarded against the plaintiff.

BACKGROUND

2. The background leading to this action has been briefly stated in the decision on costs handed down on 23 August 2012 (“the 23 August decision”).  The background leading to this application is briefly stated below.

3. This action arose from a sub-contract concerning a construction site the owner of which was the MTR Corporation Ltd (“MTR”) and the main contractor of which was Hsin Chong Construction Co Ltd (“Hsin Chong”) (“the said site”).  The plaintiff was one of Hsin Chong’s sub-contractors whereas the defendant was one of the plaintiff’s sub-contractors.  The defendant was to supply certain machinery to the plaintiff for use at the said site (“the said machinery”).

4. This action was commenced in July 2012.  Shortly before the issuance of the writ herein, the plaintiff sought, and was granted, an ex parte injunction order in short enjoining the defendant to immediately remove the said machinery from the said site.

5. By 30 July 2012 (the hearing of the defendant’s application to discharge the ex parte order), however, Hsin Chong has earlier (on 25 July (according to the plaintiff) or 26 July (according to the defendant)) taken back a major part of the said site from the plaintiff. Further, Hsin Chong has engaged the defendant to supply the said machinery to itself (on 27 July).  The ex parte order has to be, and was, varied on 30 July as a result.

6. Further, by the time of the hearing leading to the said costs order (10 August 2012), the ex parte order and the inter partes injunction order no longer served any useful purpose.  They were discharged by the parties’ consent.

7. Finally, by the time of hearing of this application, there was the unusual situation that it was the defendant (and not the plaintiff) who remained at the said site.

THE SAID COSTS ORDER

8. In gist, the said costs order was premised on:

(a)   the plaintiff’s failure to make full and frank disclosure (para 6 to 20, the 23 August decision);

(b)   a lack of sufficient urgency to justify an ex parte application (para 21 to 26, the 23 August decision).

As will be made apparent below, the above two aspects were related.

THIS APPLICATION

(a)  Full and frank disclosure

9. The plaintiff’s first main complaint is that full and frank disclosure has been made in its supporting affirmation used at the ex parte application.  This, so it is argued, shows that the part of the 23 August decision summarized in para 8(a) is wrong.

10. The fact referred to in the above complaint has not been overlooked in the 23 August decision; in fact, it was expressly dealt with there (para 6 to 9, 11 and 16 thereof).  The criticism in the 23 August decision was in essence directed at the 4-page ex parte skeleton argument not having fairly put forth the rather complicated factual background which preceded the ex parte application.  The summary given therein at para 7 to 8 (concerning the said skeleton argument) and that given at para 9 and 11 (concerning the supporting affirmation and some of its exhibits) shows the main differences between them.

11. The plaintiff has obtained, and relies heavily on, the transcript of the ex parte hearing at this application (it was not available at the earlier hearing before me, though the 23 August decision already noted that the ex parte hearing lasted for about 8 minutes only (para 12 thereof)).  The transcript confirms the length of the ex parte hearing.

12. Before discussing this complaint further, it should be mentioned that two things are shown by the transcript:

(1)   the hearing lasted from 5:04pm to 5:12pm;

(2)   about half of the hearing time was spent on parts of the contents of the draft ex parte order.

13. The plaintiff emphasized the part of the transcript (at the beginning of the ex parte hearing) where the court indicated it has read “the papers” (referring to the court documents placed before the court (which would include the skeleton argument, the supporting affirmation and the exhibits)).

14. It is true the court made that indication. However, there were two remarks made by the court almost immediately afterwards which should reasonably have alerted the plaintiff to its duty of full and frank disclosure.

15. First, the court then said:

“The simple basis is you say the defendant terminated the contact 7 July. It’s his [sic] machinery; he [sic] should have taken it away if he’s [sic] terminated”.

Thus, it must be obvious to the plaintiff the court thought it to be a simple case of trespass.

16. As has been observed in the 23 August decision, the case was more complicated than that:

(a)   the plaintiff already suspected there was a secret agreement between Hsin Chong (the plaintiff’s main contractor) and the defendant conferring a right for the defendant to remain at the said site (para 9(10), 10 and 16(c) thereof);

(b)   the quantity, size and weight of the said machinery was such that its removal would require detailed planning and supervision (not only by Hsin Chong (the main contractor) but also the MTR (the employer) (para 16(a) and (b) and 20, the 23 August decision)).

17. Para 16(a) above can affect the ex parte court’s assessment of the plaintiff’s case in trespass.  Para 16(b) above is relevant to the grant of relief (for example, whether the removal of the said machinery should be immediate and/or whether such removal should be subject to the consent and/or direction of Hsin Chong and/or the MTR, and so on); this may also be relevant to the suitability of an ex parte application (see para 34 to 35 and 36(4) below).

18. If it is said that the court’s remark quoted at para 15 above was not sufficiently obvious to the plaintiff, the second remark ought to be.  The court also said at the ex parte hearing:

“Is [Hsin Chong] giving the notice tomorrow, or has it already given the notice?”

The query was very probably about Hsin Chong’s notice to terminate the plaintiff’s sub-contract (judging from the plaintiff’s reply at the ex parte hearing, it was probably also how the plaintiff understood the query).

19. The plaintiff’s justification for making the application on an ex parte basis was built wholly on Hsin Chong’s imminent termination of its sub-contract.  This is made apparent by the plaintiff’s ex parte skeleton argument (para 3 to 6 thereof (under the heading “Ex Parte application for Mandatory injunction”) and para 14 and 16 (“Background”)).

20. As has been noted in the 23 August decision, the said skeleton argument was a short 4-page document (para 6 thereof).  The skeleton argument says this about the risk of sub-contract termination:

“… there is a real risk … [Hsin Chong] will terminate its Sub-contract with P, on Wednesday 25 July 2012” (para 3 thereof);

“On 18 July … Hsin Chong threatened to determine the Sub-Contract by giving P 7 days notice of its intention to do so. This notice will expire on Wednesday 25 July 2012” (para 14 thereof);

“As Hsin Chong has now given P 7 days notice of its intention to determine the Sub-Contract with P … ” (para 16 thereof).

(emphasis supplied)

21. The significance of the above quotes is that they made clear the sub-contract between Hsin Chong and the plaintiff provided for a 2-stage procedure for termination: a 7-day notice of intention to do so, followed by the actual notice of termination (the supporting affirmation and the exhibits for use at the ex parte hearing are consistent with that; Hsin Chong’s said notice of intention to terminate was referred to at para 25 to 26 of the supporting affirmation (a 12-page document (consisting of 41 paragraphs)) (para 6, the 23 August decision)).  They also made clear that the earliest time for Hsin Chong to exercise its termination right would be 25 July (the day following the ex parte hearing).

22. What the query ought to have shown to the plaintiff was that the court might not have fully understood the said 2-stage procedure (perhaps because the court documents were read within a short time period).  This should alert the plaintiff to the real possibility the court might not have had the opportunity to read the rest of the court documents as thoroughly as desired.

23. Having been so alerted, and bearing in mind the duty to make full and frank disclosure, the plaintiff ought to have given more assistance to the court in the manner set out below.

24. As observed in the 23 August decision, the duty of full and frank disclosure is trite (para 13 to 15 thereof).  Ultimately it rests on the rationale that, appearing as the only litigant, an applicant must act with the highest good faith (see also, for example, NCS Co Ltd v Bao Harvest Holding Ltd [2012] 5 HKLRD 138, para 30).

25. In Falcon Private Bank Ltd v Borry Bernard Edouard Charles Ltd and Another HCA1934/2011 (9 July 2012), it was said this duty will entail (among other things):

“… identify any defences which, although not yet taken, would be available to be taken by the defendant had he been present at the application provided that the defence is one which can reasonably be expected to be raised in due course by the defendant and not one which can be dismissed as without substance or importance: New Asia Energy Limited And Concord Oil (Hong Kong) Ltd, CACV 347/1998, 3 November 1999 (CA), per Keith JA” (emphasis supplied) (para 53).

26. The plaintiff also argues in this application that the quantity, size and weight of the said machinery have specifically been drawn to the court’s attention at the ex parte hearing.  But I notice that the submission was made apparently with a view to justify the need for a mandatory injunction (rather than to drew the court’s attention to the matters mentioned in para 17 above).

27. In view of the above, I consider that:

(1)   the transcript confirms the conclusion reached in the 23 August decision in that the manner in which the plaintiff’s case was put forth at the ex parte hearing was inadequate to discharge the onerous duty of highest good faith;

(2)   the exchange between the court and the plaintiff shows that the inadequacy ought to be apparent to the plaintiff;

(3)   there is therefore insufficient merits in this aspect of this application to justify leave to appeal to be given.

28. Finally, although the passages in Hong Kong Civil Procedure 2012, Vol 1 (quoted in the 23 August decision (para 13 to 15)) referred to disclosing the material facts in the supporting affidavit (as opposed to its exhibits), I do not consider the learned authors to be saying that the law limits the applicant’s duty to do only that; rather, that was only meant to be an instance of his broader duty of highest good faith.  What the law requires of him is to present the case in the fairest possible manner (see para 24 to 25 above).  As to what precisely needs to be done is a matter which varies with the circumstances of each case.

(b)  Urgency

29. Before considering this aspect, the underlying legal principles should be re-stated.  During the hearing of this application, the parties’ attention has specifically been drawn to the following authorities (in chronological order):

(a)   Seapower Resources International Ltd and Others v Lau Pak Shing and Others HCA 10715/1993 (15 December 1993) (especially para 15 to 16, p 9);

(b)   L v C CACV 333/2003 (27 April 2004) (especially para 6 to 7);

(c)   Slik Hong Kong Co Ltd v Gerald Merlyn Rhoslyn Evans and Others HCA 1424/2005 (25 July 2005) (especially para 1 to 6).

30. The court in the Seapower decision made a graphic description of what “urgency” should mean in this context:

“Ex parte applications should only be made where either the delay would cause to the Applicant injustice or the Defendant would take action which would nullify the effect of the injunction. An ex parte injunction goes against the normal way litigation is conducted. It is an infringement of the rights of natural justice of each party to be heard. Those making such applications have a duty to bear that in mind and they cannot pass their responsibility to the Court when they do so.

The need for an ex parte application in this case was sought to be put upon the following grounds. First of all, urgency. For an ex parte application for an injunction to be urgent on the grounds of urgency it must be so urgent but you cannot give even five minutes warning to the other side. Here, solicitors were instructed for the Defendants, at least the 1st Defendant. The Plaintiffs’ solicitors well knew it. The partners of the firm well knew it. There was no justification for not even making a telephone call or sending a fax, let alone giving 48 hours notice that an application was to be made” (emphasis supplied) (p 9 thereof).

31. The court in effect echoed this in the Slik Hong Kong decision:

“[after referring to passages in Brand, Farrar Buxbaum v Samuel-Rozenbaum Diamond HCA 5191/1998 (8 May 2002), para 24 (‘where … there is literally no time to warn the defendant’) and 28 (‘if there was genuine urgency … the proper course was … to take out an inter parte application, … with time abridged, or … to make an ex parte application on notice …’); and to those in the Seapower decision (above)].

As mentioned above [para 5 (nowadays it does not need to wait very long to list a matter for an inter partes hearing)], an inter parte hearing can be arranged within a relatively short time …” (para 3, 5 and 10 thereof).

32. The L v C decision contains quotes from the English authorities TRP Ltd v Thorley (unrep) (English court of appeal, 13 July 1993) and Re First Express Ltd [1991] BCC 782, 785.  Thus,

“In view of the importance of this point I would like to quote from the judgments of Hoffmann LJ, as he then was, and Sir Thomas Bingham MR in the case of TRP Limited v Thorley (Court of Appeal, 13 July 1993). The judgments are, regrettably, unreported but the Lexis Transcript records Hoffmann LJ as saying:

‘In my judgment the judge should not have entertained the application ex parte and I venture to repeat what I said in Re First Express Limited which was reported in [1991] BCC 782 at page 785.

‘It is a basic principle of justice that an order should not be made against a party without giving him an opportunity to be heard. The only exception is when two conditions are satisfied. First, that giving him such an opportunity appears likely to cause injustice to the applicant, by reason either of the delay involved or the action which it appears likely that the respondent or others would take before the order can be made. Secondly, when the court is satisfied that any damage which the respondent may suffer through having to comply with the order is compensatable under the cross-undertaking or at the risk of uncompensatable loss is clearly outweighed by the risk of injustice to the applicant if the order is not made.

There is, I think, a tendency among applicants to think that a calculation of the balance of advantage and disadvantage in accordance with the second condition is sufficient to justify an ex parte order. In my view, this attitude should be discouraged. One does not reach any balancing of advantage and disadvantage unless the first condition has been satisfied. The principle audi alterem partem does not yield to a mere utilitarian calculation. It can be displaced only by invoking the overriding principle of justice which enabled the court to act at once when it appears likely otherwise injustice will be caused.’

The rules require only two clear days’ notice and leave can, if necessary, be obtained for abridgement.  Even in cases which are too urgent for formal notice of any kind there is no reason why informal notice of an application should not be given by facsimile or telephone.”

“Sir Thomas Bingham MR had this to say:

‘So far as the substance of this matter is concerned I agree with the judgments which My Lords have delivered and I agree with the order which they propose. I do, however, wish to endorse and highlight the observations of My Lord, Lord Justice Hoffmann, concerning the procedure which was adopted in this case. Applications for injunctions are governed by Ord.29 of the Rules of the Supreme Court and in Ord.29 r.1(2) one finds the following:

‘(2) Where the applicant is the plaintiff and the case is one of urgency such application may be made ex parte on affidavit but, except as aforesaid, such application must be made by a motion or summons.’

That rule is the subject of comment in para 29/1/8 on page 514 in volume 1 of the current White Book where one finds among other statements the following:

‘Though this rule authorises ex parte applications by the plaintiff, such an application for an injunction will not be granted unless it is made promptly, and it must be shown that there are strong grounds to justify its being made ex parte.’

Again, ex parte injunctions are for cases of real urgency where there has been a true impossibility of giving notice of motion.

These statements are unsurprising since it is on the face of it plainly contrary to the principles of natural justice that any judicial order adversely affecting a party’s interests should be made against him without his being given a reasonable opportunity of being heard. That is the simple overriding rule on which our system of justice depends. The rule is not, however, absolute and unqualified. Derogations are permitted in certain very limited and exceptional circumstances, the most obvious of these so far as the granting of injunctions is concerned being where the situation is one of such extreme urgency that there is literally no time to warn the defendant of what is proposed or where the purpose of the injunction will or may well be frustrated if the defendant is informed of what is proposed or where the defendant simply cannot be found. The exceptional nature of the circumstances must, however, be stressed. They are the exception and not the norm. Even when time does not permit application on full notice it is highly desirable to inform the other party that the application is to be made ex parte so that he can if he wishes attend and make such representations as he wishes.’

I have quoted extensively from these judgments because, although they contain what is clear and well-established law which has been reiterated in judgments in Hong Kong, it is apparent and confirmed by the submissions made by counsel that these highly important principles are being disregarded” (emphasis supplied) (para 6 to 8 thereof).

The quoted passages were probably the origin from where the courts’ observations (also quoted above) in the Seapower decision and the Slik Hong Kong decision were founded.

33. In this connection, the following part of the plaintiff’s submission in this application is also relevant:

“… the Plaintiff was aware that the Defendant needed time to remove its machinery from [the said site], and would have always allowed them reasonable time to do so” (para 42 thereof).

34. It is unclear from the quoted passage if the plaintiff is agreeable to such a period being given to the defendant for complying with the ex parte order (despite the use of the word “immediate” in the order).  As a matter of reality (that is, considering the quantity, size and weight of the said machinery), it seems the plaintiff would have not much choice but to so agree.

35. In any event, since it is the plaintiff’s own case Hsin Chong regarded the failure to secure the removal of the said machinery as a contractual breach, any removal commencing from 25 July would not necessarily have prevented Hsin Chong from terminating the contract (Hsin Chong having served the notice of intention to do so earlier); this is because, by then, the breach would have already taken place.

36. Despite the plaintiff’s arguments in this application, I do not find any substance in the complaint to the effect I erred in concluding there was no “such extreme urgency that there is literally no time to warn the defendant”:

(1)   there has been on-going correspondence (involving at times cross-allegations of contractual breach) among Hsin Chong, the plaintiff and/or the defendant commencing (at the earliest) from March 2012, or (at the latest) from May or June 2012 (para 9, the 23 August decision);

(2)   the defendant’s lawyers already indicated to the plaintiff they would vigorously defend any injunction application (para 25, the 23 August decision);

(3)   the first “summons day” (Friday 27 July 2012) was only 3 days after the ex parte hearing (Tue 24 July) (para 26, the 23 August decision);

(4)   the matters mentioned in para 16 to 17 above and 33 to 35 above.

37. This aspect of this application thus has no reasonable prospect of success at the intended appeal either.

CONCLUSION

38. Accordingly, this application for leave is refused.

COSTS ORDER

39. The plaintiff agrees that the costs of this application should be awarded to the defendant if this application is refused.  There will thus be an order that those costs be paid by the plaintiff to the defendant.

40. I consider summary assessment of costs to be appropriate. The above costs shall be so assessed.  For this purpose:

(a)   the defendant be at liberty to lodge with court and serve a statement of costs within 7 days from today;

(b)   the plaintiff be at liberty to lodge with court and serve a statement of objections within 7 days thereafter.

 (Andrew Chung)
 Judge of the Court of First Instance
High Court

Mr Anthony James Sherry, instructed by Robert Lee Law Offices, for the plaintiff

Mr Sam Tsui, of Tsui & Co, for the defendant

Please refer to HCMP2863/2012 for the relevant appeal(s) to the Court of Appeal.

83253-EN-2012-08-23

SNE ENGINEERING CO LTD v. CHIM KEE MACHINERY CO LTD

HTML content

HCA 1313/2012

IN THE HIGH COURT OF THE

HONG KONG SPECIAL ADMINISTRATIVE REGION

COURT OF FIRST INSTANCE

ACTION NO 1313 OF 2012

____________

BETWEEN

 SNE ENGINEERING CO. LTDPlaintiff

and

 CHIM KEE MACHINERY CO., LTDDefendant
____________

Before: Hon Chung J in Chambers

Date of Hearing: 10 August 2012

Date of Decision on Costs: 23 August 2012

___________________________

DECISION ON COSTS

___________________________

 

Introduction

1.  This decision on costs concerns the costs of and occasioned by:

(a)  an ex parte injunction order dated 24 July 2012 (a Tuesday);

(b)  an inter partes injunction order dated 30 July 2012 which continued the said ex parte order (but with amendments).

2.  The main issues raised by the defendant during the hearing on 10 August were:

(1)  there was material non-disclosure by the plaintiff at the ex parte hearing;

(2)  there was no urgency to justify the ex parte hearing.

Background

3.  It is common ground the dispute in this action was concerned with an MTR Corporation Ltd. (“MTR”) construction site known as “Nam Cheong Property Foundation Removal and Reprovisioning site — the Express Rail Link 802” (“the Site”).

4.  MTR was the Site’s employer and Hsin Chong Construction Co Ltd (“Hsin Chong”) was its main contractor.  The plaintiff was one of Hsin Chong’s sub-contractors.  The plaintiff entered into a machinery hire agreement with the defendant for the supply of some of the equipment and machinery needed by the plaintiff (“the hiring agreement”).

5.  The injunction order (as amended) in short compelled the defendant to remove certain construction equipment and machinery (“the deft’s machines”) from the plaintiff’s part of the Site.

Material non-disclosure

6.  At the ex parte hearing, the plaintiff lodged with court a 4-page skeleton argument.  There was also a supporting affirmation of about 12 pages; attached to this were over 370 pages of documentary exhibits.

7.  The ex parte skeleton argument has the following headings:

(a)  documents before the court;

(b)  ex parte application for mandatory injunction;

(c)   background;

(d)  principles to be applied;

(e)   application of the principles.

8.  The plaintiff’s case set out in the part of the skeleton argument at para 7(e) above can be summarized as follows.  The defendant has no right to be present at the Site since 3 July 2012, the date of termination of the hiring agreement.  Any continued presence of the defendant would (at worst) cost the plaintiff its contract with Hsin Chong, and (at best) cause delays to the works at the Site.

9.  The history leading to the ex parte application was more complicated than that set out in the plaintiff’s skeleton argument.  Parts of the history can be found in the plaintiff’s supporting affirmation:

(1)  exhibit “WK-3” (defendant’s letter dated 30 March 2012) shows a complaint of the plaintiff’s non-payment of the defendant’s contract sums;

(2)  exhibit “WK-4” (statutory demand) shows the amount allegedly due to the defendant to be over $10.399 million;

(3)  exhibit “WK-5” (rental arrangement dated 23 May 2012) shows a tripartite agreement whereby the plaintiff, the defendant and Hsin Chong agreed that Hsin Chong would pay to the defendant (for the plaintiff) the hiring charges;

(4)  Hsin Chong complained on 26 June 2012 the plaintiff was in breach of the sub-contract by failing to make payment to the sub-sub-contractors, that some essential equipment would be withdrawn from the Site as a result and the withdrawal might affect work progress.  The complaint was denied by the plaintiff (para 12 and 13);

(5)  the defendant’s said letter of termination of 3 July 2012 (exhibit “WK-8”) (see also para 8 above);

(6)  Hsin Chong stating on 3 July 2012 the plaintiff was in breach of the sub-contract and Hsin Chong had to take control of the plaintiff’s sub-contract works immediately (para 15);

(7)  Hsin Chong in essence repeated the said allegation on 9 July 2012 (para 16);

(8)  the plaintiff informed Hsin Chong on 11 July 2012 it accepted the defendant’s termination of the agreement (para 18);

(9)  by then, the amount due to the plaintiff appeared to be about $3.5 million odd (para 19 and 20);

(10)   exhibit “WK-18” (plaintiff’s letter dated 19 July 2012) shows that the plaintiff denied its breach of the sub-contract, stated that it was ready to introduce its own machinery and asked Hsin Chong if the defendant had been permitted to remain at the Site by Hsin Chong.  The plaintiff also informed Hsin Chong that an application for an injunction order would be made within 14 days against the defendant if the deft’s machines should continue to wrongfully remain at the Site;

(11)   the plaintiff also demanded on 19 July 2012 that unless the defendant commenced to remove the deft’s machines the following day, an application for an injunction order would be made (para 30).

10.  In relation to para 9(10) above, at the 10 August hearing the plaintiff fairly accepted it asked Hsin Chong if permission to remain had been given because it suspected a secret agreement might have been reached between Hsin Chong and the defendant.

11.  The latter parts of the supporting affirmation then narrated the subsequent correspondence between the plaintiff, the defendant, the Hsin Chong’s project manager concerning the steps to be taken for the removal of the deft’s machines, such as the provision of a demobilization schedule, obtaining MTR’s consent for demobilization, and the plaintiff’s repeated requests for Hsin Chong to withdraw its earlier threat to terminate the sub-contract between itself and the plaintiff.

12.  The court records show that the ex parte hearing on 24 July lasted for about 8 to 10 minutes.

13.  The principles relating to the applicant’s duty to make full and frank disclosure at ex parte applications are trite.  Hong Kong Civil Procedure 2012, Vol 1 says:

“On any ex parte application, the applicant must proceed ‘with the highest good faith’ ” (para 29/1/39).

“Good faith” in such context is shown by the applicant making full and frank disclosure of all material facts.

14.  Hong Kong Civil Procedure 2012 also says:

“Materiality is to be decided by the court and not by the assessment of applicants or their advisers”;

“The disclosure of material facts is not to be confused with discovery and should be made in the affidavit, not in the exhibits … ”

(para 29/1/39).

15.  The decision of the English court of appeal in National Bank of Sharjah v Dellborg (1992) The Times (24 December 1992) was cited as the authority for the last-mentioned legal proposition.  The court also said in that decision:

“The material facts at the ex parte stage were those which were necessary to enable the judge to exercise his discretion properly and fairly between the parties ...

But the place to disclose the facts, both favourable and adverse, was in the affidavit and not in the exhibits. No doubt it would usually be convenient to exhibit a few key documents where it was necessary to do so to explain the case.

...

If the facts were not fairly stated in the affidavit it would not assist the plaintiff to be able to point to some exhibit from which the fact might be extracted.

If they were fairly stated, then it should not avail the defendant to show that some document, relevant on discovery, had been omitted” (emphasis supplied).

16.  As stated above, the supporting affirmation disclosed a history which was much more complicated than that stated in the plaintiff’s ex parte skeleton argument.  In addition, three matters have not been disclosed at the ex parte hearing (at the very least, they were not properly and/or sufficiently brought to the court’s attention):

(a)  the deft’s machines were “sizeable items of substantial weight”;

(b)  probably because of (a) above, any dismantling and removal of the deft’s machines would require (i) assistance from the management of the Site; (ii) the exit permit/consent from the management of the Site; (iii) a demobilization schedule; (iv) several days’ time and a dedicated team of removal workers (see also MTR’s letter dated 27 July 2012 referred to in para 20 below);

(c)   it was not entirely clear who Hsin Chong would regard as the party in breach of the sub-contract, and/or who to further engage for the supply of machinery covered by the hiring agreement

(the defendant’s affirmation dated 30 July 2012, especially at para 8, 11 to 16, 17 to 18, 22 to 26, 28 to 31 and 34 to 35 (and the related exhibits), and at para 10 above).

17.  Finally, the need for the plaintiff to make the application ex parte was the imminence of Hsin Chong’s threat to terminate its sub-contract with the plaintiff (Hsin Chong’s letter of 18 July giving the plaintiff 7 days’ notice to rectify its defaults):

(1)  para 25 to 27 and 38 to 40, supporting affirmation;

(2)  para 3 and 5 to 6, plaintiff’s skeleton argument.

However, a similar threat has in fact been made by Hsin Chong in early July (para 9(6) and (7) above).

18.  Further to the need in the plaintiff’s skeleton argument to draw the court’s attention at the ex parte application to the more complicated history summarized in para 9 above, the plaintiff should also have made proper disclosure of the matters set out in para 16 above.

19.  By reason of the above matters, I am satisfied that there has been material non-disclosure on the plaintiff’s part.

20.  It ought to be mentioned (though this did not affect the determination of this aspect) in a letter dated 27 July 2012, MTR expressed certain surprise about the plaintiff’s action:

“[The plaintiff has] somehow gained a High Court injunction to remove cranes from [the Site]. This is MTR’s work site and under the Contract no equipment, plant or materials or any part thereof shall be removed from [the Site] without the written consent of the Engineer. Did Hsin Chong advised the High Court that this is not [the plaintiff’s] site?”

Probably unknown to MTR, Hsin Chong was not a party to this action and naturally never enjoyed a right to be heard.

Need for ex parte application

21.  The ex parte application was not made on the basis that there was a need to keep the legal proceedings confidential and without warning to the defendant.  Thus, the only basis for so applying must be urgency which justified a departure from the normal mode of application (by way of inter partes hearing).

22.  I also agree with the defendant the plaintiff has failed to establish a proper/sufficient case of urgency.

23.  The matter put forth by the plaintiff as constituting urgency was Hsin Chong’s threat to terminate the sub-contract with the plaintiff (para 8 and 17 above).  But any urgency so arising was at least partly caused by the plaintiff:

(1)  the defendant served the notice of termination as early as on 3 July;

(2)  the plaintiff could have treated the hiring agreement as having been brought to an end since then (the termination was in fact “accepted” by the plaintiff on 11 July (para 9(8) above)).

Thus, any application for an injunction order could have been made much earlier than Hsin Chong’s threat/notice of 18 July (para 16 above).

24.  This is particularly so taking into account Hsin Chong’s threat made in early July (para 9(6) and (7) above).

25.  Moreover, in a letter dated 19 July 2012, the defendant’s solicitors expressly informed the plaintiff the defendant intended to vigorously defend any application for injunction which the plaintiff might make.  Regrettably, this has apparently been ignored by the plaintiff.

26.  Finally, as must have been well known to legal practitioners, a “summons day” is available practically every Friday to deal with interlocutory injunction applications (the Friday following 3 July (para 8, 9(5) and 23(1) above) was 6 July, that following 11 July (para 9(8) and 23(2) above) was 13 July and that following 24 July was 27 July).

Conclusion

27.  By reason of the matters above, both the ex parte injunction order and the inter partes injunction order should have been discharged.

28.  Accordingly, this is an appropriate case for the costs of and occasioned by those orders to be paid by the plaintiff to the defendant to be taxed if not agreed.

Other matters

29.  Events subsequent to the grant of the injunction orders (whether in the original or the amended version) have overtaken the need for the injunction orders.  The parties have thus sensibly consented to their discharge at the 10 August hearing.

30.  The relief sought in the action (which was substantially the same as that sought in the ex parte and inter partes hearings) is likewise rendered academic by now.  The plaintiff has again sensibly sought leave to withdraw this action with costs to the defendant to be taxed if not agreed.

(Andrew Chung)
Judge of the Court of First Instance
High Court

Mr James Sherry, instructed by Robert Lee Law Offices, for the plaintiff

Mr Jonathan Wong, instructed by Tsui & Co, for the defendant

Please refer to HCMP2863/2012 for the relevant appeal(s) to the Court of Appeal.