HK CourtDB
HomeDirectoryMCP
Hong Kong CourtDB
Back to directory
Civil Action2012

SIMNEX INDUSTRIAL LTD v. THE CONTINUITY CO LTD

Related cases with same parties

  • HCA2326/2008THE CONTINUITY CO LTD v. K T ENTERPRISE GROUP LTD

Files (2)

91960-EN-2014-02-21

SIMNEX INDUSTRIAL LTD v. THE CONTINUITY CO LTD

HTML content

HCA 2038/2012

IN THE HIGH COURT OF THE

HONG KONG SPECIAL ADMINISTRATIVE REGION

COURT OF FIRST INSTANCE

ACTION NO 2038 OF 2012

________________

Between

 SIMNEX INDUSTRIAL LIMITEDPlaintiff

and

 THE CONTINUITY COMPANY LIMITEDDefendant

________________

Before: Mr Recorder Houghton SC in Chambers
Date of Hearing: 5 February 2014
Date of Decision: 5 February 2014
Date of Reasons for Decision: 21 February 2014

____________________________________

REASONS FOR DECISION

____________________________________

 

1. This is an application for security for costs which is made on behalf of the defendant against the plaintiff. The plaintiff is a Hong Kong company and the basis for the application is section 357 of the Companies Ordinance (Cap 32) and/or the inherent jurisdiction. As is well known, that section makes provision for “sufficient security” to be provided for the costs of the defendant in circumstances in which it appears “by credible testimony that there is reason to believe that the company will be unable to pay the costs of the defendant” if the defendant succeeds in his defence.

Background

2. This has been summarised in the decision of Seagroatt DJ given on 7 November 2013 in Order 14 proceedings brought on behalf of the plaintiff.  In essence both parties are Hong Kong companies who have had a trading relationship since 2007, although it appears that business relationship ended with the matters which are in dispute in this litigation.  The defendant purchased for on sale from the plaintiff a large quantity of marbles of a particular design and specification.  Payment was to be by purchase order, and deliveries were made in instalments.

3. The goods were subject to 3rd party inspection by STR, and passed those tests.  However following delivery to one of two sub‑purchasers (CZ Albert) some of the consignments became the subject of complaint as to defects.  Further testing was carried out by Bureau Veritas which apparently revealed a rate of defects considerably higher than allowed by the Generic Inspection Specification said by the defendant to form part of the agreement between the parties.

4. There was an exchange of correspondence between the parties which, as summarised by the Seagroatt DJ, involved the plaintiff in accepting “that goods were substandard and that it would have to remedy the situation, one way or another.  Financial compensation was conceded.  Furthermore, the plaintiff shipped replacement goods… at its own expense.” (see paragraph 12 of the Decision).  The key email from the plaintiff was one dated 20 July 2012, and this reads as follows:

“… We totally agree this is our responsibility to compensate to your company due to our poor management. Pls kindly understand the effort that we involved. We have tried our best, but the case is totally out of expectation. We only focused to try our best to save the project without any cost reviewing. That’s true, it is negative margin. But it is our fault. The most that we can afford is USD 24,000 (around 500k pcs marble). Hope you can understand the situation. Thx.”

5. That offer did not resolve the situation however.  The defendant, through its agent, negotiated with CZ Albert and ultimately agreed to settle its dispute with that company for €120,000 and, in addition, to pay the cost of the Bureau Veritas testing (€2,036).  Those are the sums which form the basis of the plaintiff’s claim against the defendant, and they do so because the defendant proceeded to deduct the equivalent amount in US dollars from payments to the plaintiff.

The legal principles

6. This is a well-trodden area of law and, despite the extensive citation of authority, unsurprisingly, there is little dispute between the parties as to the key principles.  They do differ as to their application to the facts.  It is therefore common ground that the defendant bears the initial burden of establishing, by credible evidence, that there is reason to believe that the plaintiff company will not, as opposed to might not, be able to pay the defendants costs if required to do so.  If this is established, then the jurisdiction to order security arises, and the court is to have regard to the overall circumstances of the case in considering whether, or how, to exercise that discretion.  As is well known, at that stage there is no burden one way or the other as between plaintiff and defendant.  The court has a very wide discretion calling for a review of the overall circumstances of the case including of course matters such as admissions, and the scope of matters requiring determination according to the parties pleaded cases.

Contentions of the parties

7. The plaintiff’s own email of 20 July 2012 quoted above is, in many senses, central to the defendant’s contentions.  Mr Harry Liu, appearing on behalf of the defendant, takes the position that this e-mail indicates weakness in the plaintiff’s claim (since it constitutes an apparent admission that the goods were substandard), and also indicates the plaintiff’s inability to meet an order for costs in the event of the defendant succeeding at trial.  Mr Liu does not rest on this fact alone however, and among other things he places some emphasis on the paucity of accounts information supplied on behalf of the plaintiff.

8. This was a point taken by counsel in his skeleton submissions, but was also one which had been canvassed in correspondence considerably earlier in time without any adequate response having been made on behalf of the plaintiff.  The plaintiff’s evidence has provided audited accounts for the years ending 2008, 2009, 2010 and 2011, but no audited accounts since that date.  A “certificate” from the plaintiff’s accountants was issued in January 2013 addressing the plaintiff’s financial position as at 31 December 2012, but without supporting documents.  Very late in the day the plaintiff appears to have come to the conclusion that there was a lacuna in its evidence in this respect.  Mr Adrian Leung, counsel for the plaintiff, sought to place before the court at the commencement of the hearing the 2012 audited accounts.  This was objected to by the defendant due to the lateness of the application, and the inability to be able to analyse the accounts, or to take instructions on them.  Mr Leung was left in the unfortunate position of seeking to have the court grant an indulgence to his client in circumstances in which there was no affirmation in support explaining the delay or the circumstances in which these accounts were presented without the slightest advance notice.  In those circumstances while the accounts were of obvious relevance this was outweighed by the prejudice to the defendant in such a last minute application.  There was simply no countervailing basis in evidence on which the court could exercise its discretion, and the plaintiff’s application for leave to adduce those accounts was refused.

9. The case therefore proceeded on the premise that there was no evidence as to the plaintiff’s financial position more recent than the January 2013 Certificate of the accountants.

10. In addition to the question mark which the defendant contended arises over the plaintiff’s financial position because of the absence of recent, relevant evidence, the defendant also pointed to the limited paid up capital of the plaintiff; the fact that the plaintiffs evidence suggests that it depends on outside (directors and shareholders) sources of finance; the existence of a mortgage charge over the plaintiff’s assets and the fact that the plaintiff has no landed property.

11. Mr Leung contends that the evidence which is available shows that the plaintiff is very much a going concern, carrying on a “vibrant business” since its establishment in 2003, specialising in the sale of toys and novelty products for export.  The evidence establishes that the plaintiff has, or had as at the date of the affirmation evidence a number of substantial and prestigious clients outside Hong Kong.  The plaintiff accepts that it has relatively little by way of a “set up” in Hong Kong but says that this is a reflection of the nature of its business, which sources manufactured products from China and Taiwan and which it sells overseas.  The plaintiff points to the fact that it had a business relationship with the defendant itself for several years.

12. The available accounts show, according to the plaintiff, a rising trend of turnover with annual profits, at least in 2010 and 2011 in excess of HK$2 million. The plaintiff’s auditors stated in their Certificate that the plaintiff had “net assets” of HK$3.2 million, for the year ended 31 December 2011 and HK$4.2 million as at end 2012.  The Certificate stated that the plaintiff should have sufficient financial capacity to pay the amount of legal costs sought by the defendant in the summons.

Inability to Pay?

13. In this context I remind myself that it is not a requirement that the applicant for security the costs produce anything tantamount to conclusive evidence of an inability to pay on the part of the plaintiff.  It suffices if the defendant is able to point to surrounding circumstances which evidence a genuine and reasonable belief of such an inability.  If that evidence exists, then the onus lies on the plaintiff to adduce evidence to rebut the inferred inability to pay.  In E Global v Trenda [2012] 2 HKLRD 1211 To J referred to and agreed with the views of Quillam J in Concord Enterprises Ltd v Anthony Motors (Hutt) Ltd (No 2) [1977] 1 NZLR 516 that (in the context of the equivalent New Zealand legislation):

“I think what the statute contemplates is that there should be credible (that is believable) evidence of surrounding circumstances from which it may reasonably be inferred that the company will be unable to pay the costs. This does not, of course, amount to proof that the company will, in fact, be unable to pay them.”

14. That is a relatively low threshold test, and I accept that the plaintiff’s assertion of having only limited funds in its own email of 20 July 2012, coupled with the lack of any detailed evidence supplied by the plaintiff as to the current position, does give rise to a reasonable inference of inability to pay.  I place relatively little weight on the email since, it appears to me, it was written in the context of an attempted negotiation of settlement of the issue as to the defects in the marbles.  Of more significance, it appears to me, is the plaintiff’s insouciant stance in regard to providing evidence of an ability to pay.  While these factors may have motivated the defendant to bring its application, the evidence before me includes the earlier accounts, the affidavit evidence filed on behalf of the plaintiff, and the auditors’ Certificate of January 2013.  Those are among the surrounding circumstances to be considered in deciding whether or not the jurisdiction to order security for costs arises.

15. Also of relevance in this context I believe is the amount of the costs in respect of which security is sought.  The summons seeks security in the amount of approximately HK$1.7 million which counsel for the defendants submitted should be supplemented by an additional HK$400,000, approximately, being the costs of the plaintiff’s unsuccessful summary judgement application (which was dismissed by the judge with an order that the costs be paid forthwith).  Those costs, without any investigation of the detail, encompass the entire course of the (anticipated) litigation.

16. Looked at overall, and notwithstanding the failure by the plaintiff to keep the court updated as to its financial position, it seems to me more likely than not that the plaintiff will in fact be able to meet an order for costs made against it if such a situation arises.

17. On that basis, the jurisdiction to order security for costs does not arise and no exercise of discretion is called for.  The matter was fully argued before me however, and both parties supplied comprehensive written arguments, so I will add a few words as to the way in which I would have been inclined to exercise my discretion had it arisen.

18. The particular feature of the case which gave rise to the greatest discussion between the parties was the fact that the matters in dispute in the claim and the counterclaim are, as it was termed by the parties, two sides of the same coin.  The plaintiff seeks recovery of sums of money deducted by the defendant due to the alleged defects in the marbles, and the defendant resists the claim on the basis that it was entitled to make the set off due to those same defects.  There are other matters raised by the defendant in its counterclaim, essentially consequential losses flowing from the supply of defective goods, and in value terms these considerably exceed the principal issue as to the quality of the goods supplied.  To the extent that the defendant’s costs for which it seeks security have been increased by these consequential matters, then I would have been inclined not to order any security since the defendant is the “attacker” in regard to those matters.

19. So far as the “defective goods” issues are concerned, it seems to me of central importance to any exercise of discretion that the matters to be canvassed by the plaintiff in pursuing its claim will be (perhaps considerably) complicated by the defendant’s assertions of defects in the goods supplied.  As referred to above, those quality issues will be considered in the context of the apparent admission made by the plaintiff that defects existed, but inevitably, on the pleadings as they stand, the plaintiff and defendant will be required to traverse the same issues in the context of the counterclaim.  This was the situation considered by the Court of Appeal in England in BJ Crabtree (Insulation) Ltd v GPT Communication Systems Ltd (1990) 59 BLR 43, by Fung J in Wison (Shanghai) Chemical Engineering Company Limited v Simmons and Simmons [2008] 2 HKLRD 72, and by Yam J in Ai Zhong v Metrofond Ltd [2010] 1 HKLRD 213.  While I do not understand those cases to demonstrate a principle that security for costs will not be ordered in circumstances in which the claim and counterclaim overlap in this way, I believe it is clear that this is a factor which significantly militates against making an order for security for costs against one party only.

20. Mr Liu submitted that the defendant should not be hobbled in its application by the fact that the plaintiff had not taken out a cross application seeking security in respect of the counterclaim, and that therefore security should nevertheless be ordered against the plaintiff.  In the circumstances it is perhaps sufficient for me to observe that adopting such an approach against the background of the present facts would not be consonant with the objectives of security; namely that whether or not to make such an order

“…is a discretionary question … and it is a discretion to be exercised in the interests of justice having regard to the peculiar features of the case before the court.” (per Bingham LJ in BJ Crabtree).

Conclusion

21. I do not accept that any discretion to order security for costs arises in this case.  It appears to me that the evidence does not provide a sufficient basis, or give rise to a reasonable belief that the plaintiff will be unable to pay the defendants costs if called upon to do so.  Were that conclusion to be incorrect, on the material before me I would be disinclined to make an order for security in any event.

22. Accordingly the defendant’s summons is dismissed.

Costs

23. At the conclusion of the hearing I indicated to the parties that I would make an order nisi on costs, which I now do.  The consequence of my conclusion above would seem to be that the plaintiff should have its costs of the summons.  Mr Liu sought however the costs of the application made by Mr Leung for the admission of the accounts evidence.  Since there was no advance notice of this application, it appears that these costs are restricted in amount, but the first half an hour of the hearing was taken up with this, and, to the extent that discrete costs can be identified I accept that these should be to the defendant.  Therefore there are to be orders accordingly, on an order nisi basis.

(Anthony Houghton, SC)
Recorder of the Court of First Instance
High Court

Mr Adrian Leung, instructed by Huen & Partners, for the Plaintiff

Mr Harry Liu, instructed by Wilkinson & Grist, for the Defendant

90055-EN-2013-11-07

SIMNEX INDUSTRIAL LTD v. THE CONTINUITY COMPANY LTD

HTML content

HCA 2038/2012

 

IN THE HIGH COURT OF THE

HONG KONG SPECIAL ADMINISTRATIVE REGION

COURT OF FIRST INSTANCE

CIVIL ACTION NO 2038 OF 2012

____________

BETWEEN

 SIMNEX INDUSTRIAL LIMITED    Plaintiff  
 AND
 THE CONTINUITY COMPANY LIMITEDDefendant

____________

Before: Deputy High Court Judge Seagroatt in Chambers
Date of Hearing: 30 October 2013
Date of Decision: 7 November 2013

__________________________________

DECISION

__________________________________

1.  In this action the Plaintiff claims the contractual price for certain goods delivered to the Defendant’s customers or, more specifically one of two specific customers.

2.  The parties have had a business relationship since 2007 although the number of actual contracts have been few.  However the Terms and Conditions applied are well known to both of them and there is no issue between them on this aspect although the Plaintiff raises some odd and illogical argument about one point with which I will deal shortly and briefly.

3.  The Defendant, a Hong Kong company, is wholly owned by a company registered in the Netherlands.  Its agent in Switzerland is wholly owned by the same company.  The Plaintiff, another   Hong Kong Company, supplies toys for export and, specifically in this case, glass marbles manufactured by a Taiwanese company.

4.  In October 2011 the Defendant sought a quotation for the supply of a quantity of “Ice Age 4” marbles.

5.  On 12 December 2011 the Defendant confirmed that differing quantities would be required for three identified customers.  Eventually only two customers, to whom the marbles would be supplied directly, were specified – Mercator in Slovenia and CZ Albert in the Czech Republic.  The Defendant sent by E-mail to the Plaintiff on the    18 December 2011 an order for 12,760,000 pieces for the customer Mercator and 18,500,000 pieces for the customer CZ Albert.  The Plaintiff then sent two Order Confirmations, one for each of the quantities to the two customers.

6.  On the 21 December 2011 the Plaintiff sent two draft    Purchase Orders (one for each delivery) and the Defendant returned them signed.

7.  One of the arguments advanced by the Plaintiff is that there were two separate contracts.  Although it is not necessary for me to decide whether there were two contracts or one contract with two delivery points, I have formed the view for the purposes of this hearing that there was one contract for a supply of one quantity of one product to be delivered to two separate destructions.  One matter (amongst several) which lends support to my view is the schedule for shipping and delivery set out in paragraph 31 of the Affirmation of the Defendant’s Regional Finance Director, Mr Lam Kin Ming, which is not disputed.

8.  Three instalments of the order were shipped on the   18 April 2012, one to Mercator (2 million items) and two to       CZ Albert (each of 1 million items).  These were obviously the first         4 million items off the production line, or at least, that is the reasonable conclusion.  Then there are two instalments shipped on 16 May 2012, one to Mercator of 2 million items, and the other to CZ Albert of 4 million items. 

9.  The next three instalments go to CZ Albert and the last three to Mercator.  Shipment to both customers is completed by 3July 2012. 

10.  The goods had been subject to STR tests which they passed.  Later the customer CZ Albert began to make complaints about the quality of the goods it received.  These were received from in or about    27 June 2012.  The Defendant then arranged for the goods to be inspected by Bureau Veritas of the Czech Republic.  It carried this out on the first batch received.  The rate of defects discovered was well above the accepted rate in the GIS document.  They were regarded as not in accordance with the sample, and not reasonably fit for purpose.  There were similar results from the inspection of the fifth and sixth batch of   CZ Albert goods.

11.  Apparently even before the complaints from CZ Albert and the BV inspections, the Defendant had alerted the Plaintiff to its concern that the quality of the goods was below expectation and might be rejected by the customer, and pressed for an improvement in quality. 

12.  There is a series of E-mails dealing with this situation, most if not all dated the 20 July 2012, in which it is unequivocally clear that the Plaintiff was accepting that goods were substandard and that it would have to remedy the situation, one way or another.  Financial compensation was conceded.  Furthermore the Plaintiff shipped replacement goods – 32,000 items to CZ Albert and 80,000 to Mercator with an offer to supply a further 300,000 replacement items at its own expense.  It is not necessary for the purpose of this exercise, to consider and set out the various documents and records dealing with this.  They speak for themselves.

13.  At this stage I will revert to an aspect of the Plaintiff’s contention in relation to the Terms and Conditions which I mentioned earlier.  They provided for re-imbursement of monies paid in the event of breach on the part of the seller of the goods or, at the buyer’s option, replacement goods.  At some stage the Plaintiff sought to argue that the buyer had to accept replacement goods.  This is clearly wrong.

14.  In another attempt to suggest that there were two distinct contracts, it was argued that by reason of a number of aspects of the goods delivered to the two different customers of the Defendant, these were “separate and distinct transactions” for example:

1) Variations in the artwork.   

2) Approval of artwork on different dates.

3) Licence approval by 20th Century Fox on different dates.

4) Different shipping instructions (for the two destinations).

5) Different inspections for the two customers receiving the goods.

15.  I regret to say that this is an instance of the proverbial “scraping of the barrel” in the Plaintiff’s argument.

16.  The Defendant had promptly paid on the invoices in respect of the CZ Albert deliveries, and the earlier Mercator deliveries. The last two deliveries (and therefore invoices in respect of them) were made after the CZ Albert invoices had all being paid and some of the Mercator had been paid.  Therefore the Defendant had only these two unpaid invoices against which to attach their claimed compensation, in whatever form it was to take. There had clearly been an acceptance by the Plaintiff of the defects in the goods supplied to both of the Defendant’s customers.

17.  The defective goods had caused a claim to be brought by   CZ Albert for some form of compensation from the Defendant.  The Defendant paid them compensation by way of a discount on the price.  It also paid for the fees of the inspections.

18.  The Defendant therefore has in principle, a valid defence to the Plaintiff’s claim.  The E-mail records support the Defendant’s argument.  Its contents undermine the argument raised by the Plaintiff before me.

19.  I have had regard to the cases cited to me by both counsel.  I do not need to traverse them in detail.  The facts before me are different from those considered by the Hong Kong Court of Appeal in Karpex (HK) Ltd-v-Yasmine Printing (China) Ltd [2008] 1 HKLRD 199 CA.  There were clearly two contracts in that case and the second paragraph of the headnote highlights the distinctions readily to be drawn in the action before me.  The breach of warranty arose under the one contract (as I find it to be) in respect of the goods for both of the Defendant’s customers.  That is admitted by the Plaintiff in its E-mails.  The same terms applied to all supplies and shipments.  There was no relevant or significant difference in time.  The supplies and shipments proceeded in tandem.

20.  In my view the Defendant’s counterclaim clearly arises out of the single contract even though it may be limited to the consequences of the supply of defective goods to CZ Albert.  It is also properly pleaded as a set-off.  The other unliquidated heads of consequential loss claimed by the Defendant may give rise to difficulties of proof or quantification but both are reasonable, potential avenues of short-term or long term loss.

21.  Finally, without identifying the other cases referred to – and for immediate purposes I have borne in mind Geldof MetaalconstructieNV-v-Simon Carves Ltd [2011] 1 Lloyds Reports 517, and         Bim Kemi-v-Blackburn Chemicals Ltd [2001] 2 Lloyds Reports 93, amongst others, – even if one took the view that technically there were two contracts for supply, they are so closely connected and the counterclaim and set off so inextricably connected with the defence (and the claim itself) that it would be “manifestly unjust” or “inequitable” – these are really synonymous terms – to allow a Plaintiff, particularly one who concedes that he has supplied defective goods across the board i.e. to both end – recipients, to enforce payment regardless of the cross-claim.

22.  This summons is dismissed with costs to the Defendant to be taxed if not agreed.  There will be a certificate for Counsel.

23.  Restraint needs to be exercised in respect of the bundles of documents.  They were grossly excessive.

(Conrad Seagroatt)
Deputy High Court Judge

Mr Adrian Leung, instructed by Messrs Huen & Partners, for the Plaintiff

Mr Harry Liu, instructed by Messrs Wilkinson & Grist, for the Defendant