HK CourtDB
HomeDirectoryMCP
Hong Kong CourtDB
Back to directory
Employee's Compensation Case2013

KWONG CHEUK SING v. SKY FIELD CONSTRUCTION LTD AND OTHERS

Files (2)

112093-EN-2017-10-12

KWONG CHEUK SING v. SKY FIELD CONSTRUCTION LTD AND OTHERS

HTML content

DCEC 2198/2013

IN THE DISTRICT COURT OF THE

HONG KONG SPECIAL ADMINISTRATIVE REGION

EMPLOYEES’ COMPENSATION CASE NO 2198 OF 2013

________________________

BETWEEN

 KWONG CHEUK SING (鄺灼成)Applicant
 and 
 SKY FIELD CONSTRUCTION LIMITED (天域建築有限公司)1st Respondent
 陳耀輝transliterated as CHAN YIU FAI2nd Respondent
 LI WAI CHIU trading as
CHEUNG ON ENGINEERING CO
(李偉超以長安工程公司之名稱營業)
3rd Respondent
 LAM KWOK PING trading as
CHEUNG ON ENGINEERING CO
(林國平以長安工程公司之名稱營業)
4th Respondent

________________________

Before: Deputy District Judge S.P. Yip in Court
Dates of Hearing: 9, 10 & 12 October 2017
Date of Judgment: 12 October 2017

________________________

J U D G M E N T

________________________

Background

1.  The applicant was a concrete repair worker.  He suffered from personal injury out of an accident at work on 20 November 2012 at the 1st Floor, City Industrial Complex, No. 116-122 Kwok Shui Road, Kwai Chung, Hong Kong (“the Site”) when he fell from a working platform of about 2 metres high (“the Accident”).  As a result of the Accident, he suffered:

   (1)  fracture over bilateral radius of both wrists;

   (2)  stiffness and swelling in both hands and wrists; and

   (3)  abrasion over forehead and upper lip.

2.  At the material times, the owner of the Site was Freudenberg and Vilene International Limited, appointed the 1st respondent (“R1”) as the principal contractor to undertake the renovation works at the Site.  R1 then subcontracted the entire works to an unincorporated business body known as Cheung On Engineering by a written subcontracting agreement dated 8 November 2012 signed between R1 and the 3rd respondent (“R3”) who claimed to be the responsible person of Cheung On.  The 2nd respondent (“R2”), who was working for R3 at the Site, later introduced the applicant to work at the Site without any written employment contract.

3.  After the commencement of the present proceedings, the applicant later applied to join the 4th respondent (“R4”) by the summons dated 22 April 2016, and it was approved by the order of Her Honour Judge Levy on 5 September 2016.  The applicant made such joinder application because R1 claimed that it intended to contract with R4 and denied any contractual relationship with R3.   

4.  After these proceedings were set down for trial, R1 filed a notice to act in person on 10 August 2017 and eventually failed to attend the trial.  R2 and R3 were all along acting in person.  Both were absent for the trial and all previous hearings.  R2 has filed an answer to the applicant’s original application, and R3 has filed nothing.

5.  On the first day of the trial, counsel for the applicant applied to discontinue the applicant’s claim against R4 as the primary case of the applicant is that only R3 and R1 should be liable to the applicant as employer and principal contractor respectively.  Leave to discontinue the claim against R4 was granted with the issue of R4’s costs reserved, and R4’s attendance of the trial was excused save and except for the adjourned argument of costs scheduled on the last day of the trial.

6.  The applicant himself came to court to give evidence at the trial by adopting his witness statements and supplemented by oral evidence updating his current situations. 

Liability

7.  There is no dispute that the applicant has suffered personal injury by the Accident arising out of and in the course of employment.  The issues for the trial are the following:

   (1)  Who was the employer of the applicant at the time of the Accident?  and

   (2)  The contractual relationship between the respondents and the employer of the applicant, if any.

8.  The applicant was asked to work at the Site by R2 on 17 November 2012.  R2 did not tell the applicant who was the employer.  Therefore, the applicant did not know who was his employer at the beginning of these proceedings.

9.  The Labour Department conducted an investigation over the Accident and compiled a report dated 14 December 2012.  The report identified R1 as the principal contractor of the Site and R3 being its subcontractor which in turn employed the applicant.  The Labour Department also prosecuted against R1 and R3 for breach of regulations 38C, 68(1)(a) and 68(2)(g) of Construction Sites (Safety) Regulations, (Cap 59I).  R3 was convicted on his own plea.  R1’s conviction was overturned on appeal on the basis that the working platform provided by R1 was not unsafe in the circumstances.

10.  The applicant relies on section 62 of the Evidence Ordinance (Cap 8) that facts which form the basis of a criminal conviction shall be regarded as facts proven in a civil trial. 

11.  As R3 has pleaded guilty to the above criminal prosecution and admitted the brief facts drafted by the prosecution, including the admission of being the employer of the applicant, I accept such uncontested evidence and find that R3 was the employer of the applicant at the material time of the Accident.  I also accept that R2 was acting as the agent of R3 to recruit the applicant to work at the Site. 

12.  Therefore, I find that R3 is liable to the applicant as the employer of the applicant and R2 is not liable.  

Relationship Between R1 and R3

13.  First of all, there is no dispute that R1 was the principal contractor of the works at the Site.  The applicant relies on the following evidence to prove that R3 was R1’s subcontractor:

(1)  According to a subcontracting agreement dated 8 November 2012, R1 has engaged R3 as its subcontractor.  Although it is stated that Cheung On Engineering Company was the subcontractor, it was only a tradename.  The applicant submitted that the contracting party should be R3.

(2)  In the statement given by one Ms Lam, a staff of R1, to the Labour Department on 6 April 2013, Ms Lam confirmed that R1 had subcontracted the works at the Site to R3.

(3)  During the criminal prosecution by the Labour Department against R1, R1 had never raised any objection that R3 was not its subcontractor. 

14.  Although R1 has challenged the validity of the subcontracting agreement signed by R1 and R3, arguing that R4 was the registered proprietor of Cheung On but not R3, after considering all the evidence before me, I accept that R3 was the subcontractor of R1.  I agree with the applicant’s counsel that the contracting party of the contract would not be changed by the mere fact that R3 used the tradename of R4 to sign the contract, and the labelling of the contract is not conclusive in deciding who was the real contracting party.   

15.  Pursuant to section 24 of the Employees’ Compensation Ordinance (Cap 282)(“the ECO”), every subcontractor and principal contractor of the applicant’s employer would be liable for the applicant’s employees’ compensation.  As R1 was the principal contractor at the Site and, R1 is also liable for the applicant’s employees’ compensation claim according to section 24 of the ECO.

Quantum

16.  The applicant was born on 16 August 1957.  He was aged 55 at the time of the Accident. He appealed against the Form 9 dated 23 October 2014 which assessed the applicant to suffer 4% loss of earning capacity. 

17.  The applicant claimed that his earning immediately before the Accident was HK$900 per day, working 26 days a month.  He also earned the same amount per day in the preceding job.  The applicant takes HK$23,400 as his earning for the purpose of employees’ compensation.  At the trial, the applicant has updated the court his current earnings as a security guard of HK$13,275 per month.

Compensation for Permanent Partial Incapacity under Section 9

18.  The applicant submits that section 9(1A) of the ECO should be invoked in the present case and the Paper Mills formula as stated in Hong Kong Paper Mills Limited v Chan Hin Wu [1981] HKLR 556 and Lui Kwong Yan v Shui Hing Decoration Works & Another [1993] 1 HKLR 168 should apply for the purpose of calculating compensation under section 9 as the application of the first schedule of the ECO would produce unjust result.

19.  The applicant was examined by Dr Wong Sze-hoi for the applicant and Dr Tio Man-kwun Peter for R1 on 13 December 2016.  Dr Wong assessed the applicant suffering a loss of earning capacity of 8% to 10% whereas Dr Tio assessed the loss at 3.5%.  Dr Wong also opined that the applicant was unable to return to his pre-accident job as a ceiling-furnishing worker.  His residual wrist pain would cause him unable to perform moderate to heavy type of delivery work as required by his pre-accident job.  Dr Wong recommended the applicant to change to sedentary type of work.

20.  After the expiry of the applicant’s sick leave, he only managed to secure job as security guards, working for 26 days a month on a 12-hour shift. 

21.  The applicant submits that there are special circumstances in the applicant’s case that warrant the application of section 9(1A):

(1)  The applicant has been working as a ceiling-furnishing worker since 1996 and he has no other skills.

(2)  The applicant was only educated up to high school in mainland China.  In view of his low level of education, old age and his academic qualification not being recognised in Hong Kong, it would be difficult for the applicant to change to other types of work with earnings similar to a ceiling-furnishing worker.

(3)  The residual pain and weakness in his wrists make the applicant impossible to find a job as a ceiling-furnishing worker.

(4)  The job assessment performed by occupational therapy department of Princess Margaret Hospital found that the applicant’s performance was “non-matched” with the job demands of his pre-accident job as a ceiling-furnishing worker and advised the applicant to change to other less physically demanding jobs.  The applicant submits that the actual loss suffered is much higher than the loss of earning capacity as assessed by the experts.

22.  After considering the uncontested evidence before me, I accept the applicant’s submission and apply the Paper Mills formula to calculate the percentage of loss of earning capacity suffered by the applicant as follows:

   HK$(23,400 - 13,275) ÷ HK$23,400 × 100% =  43.27 %   

Accordingly, the applicant’s compensation under section 9 is:

   HK$23,400 × 72 × 43.27% » HK$729,000 (rounded up).

Compensation for Temporary Incapacity under Section 10

23.  The period of absence of the applicant was supported by sick leave certificates issued by registered medical practitioners.  Such sick leave certificates shall be deemed to be the period of total temporary incapacity.  In the absence of any evidence of fraud, I accept such period of absence as certified by the doctors.  The total days of absence are 572.  Therefore, the compensation under this section is

   HK$23,400 × 12 × 572/365 × 4/5 = HK$352,039.

Medical Expenses under Section 10A

24.  As the third schedule of the ECO stipulated that the daily medical expenses subject to a cap of HK$200, there is one item claimed by the applicant exceeds such limit.  The applicant agreed to deduct the excess amount and claimed the compensation under this section for the sum of HK$4,005.  I award the same to the applicant.

Conclusion & Order

25.  For the above reasons, I find that R1 and R3 are liable to the applicant for the total compensation of HK$1,085,044 as follows:

Section 9 compensation:
HK$ 729,000
Section 10 compensation:
HK$ 352,039
Section 10A compensation:
HK$ 4,005

  HK$1,085,044  

26.  I also award interest for the above compensation at half judgment rate from the date of Accident, ie 20 November 2012, to the date of this judgment and thereafter at full judgment rate until full payment.

Costs

27.  R1 and R3 shall pay the applicant’s costs of this application with certificate for counsel, to be taxed if not agreed, such costs to include all costs incurred by reason of joining R4 and further all costs the applicant may have to pay R4, save and except that there be no order as to costs as between the applicant and R2.

28.  Regarding the adjourned argument on R4’s costs, the applicant and R4 were eventually able to reach amicable resolution and I make the following costs order according to their agreement:

(i)  R1 shall pay R4’s costs of this action up to 20 October 2016 with certificate for counsel, to be taxed if not agreed;

(ii)  The applicant shall pay R4’s costs of this action from 21 October 2016 onwards, including the costs of the argument on costs of this action, with certificate for counsel, to be taxed if not agreed; and

(iii)  The applicant do have liberty to recover the costs set out in sub-paragraph (ii) above from R1;

29.  The applicant’s own costs shall be taxed in accordance with the Legal Aid Regulations.

30.  Finally, I thank Mr Yip for the applicant and Mr Lam for R4 for their assistance and cooperation.

(S.P. Yip)
Deputy District Judge

  

Mr Richard H L Yip, instructed by Or & Partners assigned by the Director of Legal Aid, for the applicant

The 1st , 2nd & 3rd respondents were not represented and did not appear

Mr Allen Lam, instructed by Tsang, Chan & Woo, for the 4th respondent

106536-EN-2016-10-31

KWONG CHEUK SING v. SKY FIELD CONSTRUCTION LTD AND OTHERS

HTML content

DCEC 2198/2013

IN THE DISTRICT COURT OF THE

HONG KONG SPECIAL ADMINISTRATIVE REGION

EMPLOYEES’ COMPENSATION CASE NO 2198 OF 2013

-------------------------

IN THE MATTER OF AN APPLICATION BETWEEN:

 KWONG CHEUK SINGApplicant

and

 SKY FIELD CONSTRUCTION LIMITED 1st Respondent
 陳耀輝 transliterated as CHAN YIU FAI 2nd Respondent
 LI WAI CHIU trading asCHEUNG ON ENGINEERING CO3rd Respondent
 LAM KWOK PING trading as CHEUNG ON ENGINEERING CO
( 林國平以長安工程公司之名稱營業)
4th Respondent
-------------------------
Before:  HH Judge Levy in Chambers
Date of Hearing:  5 September 2016
Date of Decision:  5 September 2016
Date of Handing Down Reasons for Decision:  31 October 2016

------------------------------------

REASONS FOR DECISION

------------------------------------

A. INTRODUCTION

1. These proceedings were instituted on 9 December 2013 pursuant to the Employees’ Compensation Ordinance (Cap.282) (All references to statutory provisions in this decision, unless expressly stated, are references to this Ordinance) in respect of the personal injuries the applicant, a concrete repair worker, sustained in an accident (“Accident”) that took place on 20 November 2012 allegedly in the course of employment with Sky Field Construction Limited (“Sky Field”).

2. By two subsequent amendments made on 22 May 2014 and 12 May 2015, the applicant respectively added two additional respondents to these proceedings, namely Chan Yiu Fai, and Li Wai Chiu (“Li”) trading as Cheung On Engineering Co (“Cheung On”) as the 2nd and the 3rd respondents.  The applicant alleged that Sky Field was the principal contractor and that the 2nd and the 3rd respondents were the sub-contractors.

3. By a summons dated 22 April 2016, the applicant applied to join Lam Kwok Ping (“Lam”) trading as Cheung On (who is referred to as the “Intended 4th respondent”) as the 4th respondent.  This joinder application was made 17 months after the expiry of the 24 months’ time limit stipulated by s. 14 for the bringing of proceedings for the recovery of compensation by an employee against an employer.

4. Lam objected to the application.  As Sky Field did not object to it and the 2nd respondent was neutral as to the application, this court excused them from attending the substantive hearing of the application.

5. At the substantive hearing on 5 September 2016, the applicant and Lam were respectively represented by Counsel Mr Yip and Mr Poon. Sky Field and the 2nd respondent, having been excused from attendance, did not attend the hearing.  The 3rd respondent was served with the summons and the notice of the hearing, and was absent.

6. After hearing arguments from counsel, I acceded to the applicant’s application by joining the Intended 4th respondent as the 4th respondent to these proceedings.  These are my reasons for the decision.

B. Background Information

7. The followings is taken from the background information set out in an accident report (“Accident Report”) dated 22 April 2015 compiled by the Labour Department.

(1) The place of the Accident was at unit C, 1/F., 116-122 Kwok Shui Road (“Site”).

(2) Sky Field was appointed as the principal contractor by the owner, “Freudenberg & Valene International Ltd” (“科德堡有限公司”) (“Owner”) to undertake the renovation works (“Works”) at the Site.

(3) By a sub-contracting agreement signed between Sky Field and Li, Sky Field sub-contracted the entire Works to Li who claimed to be the responsible person of Cheung On.

(4) Li assigned the Works to the 2nd respondent who later introduced the applicant to work at the Site without any written employment contract.

8. It is not in dispute that the applicant obtained from the Labour Department on 28 January 2015  the Accident Report along with a number of other documents, which included a record of interview of Li (“Li’s Statement”) taken by an officer of the Labour Department on 2 May 2013.   The sub-contracting agreement referred to in para 7(4) above was dated 8 November 2012 (“Subcontract”), and which Sky Field provided to the applicant’s solicitors on 10 February 2015.

C. APPLICANT’S EXCUSE FOR THE DELAY

9. Since this joinder application was made out of time, the applicant would need to show to the satisfaction of the court the existence of a reasonable excuse for having failed to make the claim against the Intended 4th respondent within time: s 14(4).

10. The applicant’s excuse, according to the two affirmations the applicant had filed - one filed on 22 April 2016 in support of the present application, and another on 14 April 2015 in support of his previous application to join the 3rd respondent – was: first, the applicant did not have the information as to the identities of all the relevant parties until he had obtained the relevant documents on 28 January 2015 from the Labour Department. Secondly, Sky Field had shifted its pleaded case and only put forth a positive case after the time limit had expired. Thirdly, Li’s statement contained allegations that did not seem to be consistent with the relevant documents. The applicant therefore stated that he could only make an informed decision to make the joinder application after he had been served by Sky Field on 7 January 2016 with the witness statement of Law Po Ting (transliteration) (羅寶珽) (“Law’s statement”), in which Law affirmatively denied that Sky Field had subcontracted the Works to Li or the 2nd respondent.

11. Mr Yip submitted that before the 3rd respondent was made a party to the proceedings, Sky Field had only maintained a bare denial without pleading a positive case. It was not until Sky Field served its re-re-amended answer filed on 14 August 2015 that it, for the first time, alleged that  the Subcontract was signed by Li as Cheung On’s responsible person only, but that the Works had been subcontracted to Cheung On, which bore a business registration number of 51430244 (“B.R.No.”) and that its sole-proprietor was Lam.   

12. Mr Yip submitted that Sky Field’s pleaded case was far from clear as it was unclear whether it was averred that Li or the Intended 4th respondent was Sky Field’s subcontractor. The applicant was therefore placed in a difficult situation. The difficulty was further compounded by the assertions in Li’s statement which contained allegations by Li that he was the de facto person responsible for the entire Works, including the provision of the quotation to the Owner as well as the entry of the Subcontract by using Cheung On’s name. In the circumstances, it was submitted that the applicant had a good reason to wait until Sky Field had served Law’s statement before the applicant could properly issue the joinder application.  

D.  ORIGINAL CONSENT TO BE JOINED

13. Mr Yip further submitted that no prejudice would be caused to the Intended 4th respondent by joining him as this stage. Referring to the consent summons the solicitors for the Intended 4th  respondent enclosed with their letter dated 31 May 2016 in which the Intended 4th respondent had agreed to be joined to these proceedings, Mr Yip said that the Intended 4th respondent had never complained of any prejudice despite the expiry of the time-limit.  It was stated that were the 2nd and 3rd respondents legally represented instead of having acted in person, the consent summons could have been signed and made an order in terms.  Absent an explanation from the Intended 4th respondent for its change of position, the court, it was submitted, should conclude that there was no prejudice.

E. GROUNDS OF OPPOSITION

E.1 No reasonable excuse

14. Lam opposed the joinder application by relying on his opposing affirmation as well as the affirmation of Chan Kin Wo (“Chan’s affirmation”), who was the solicitor for the Intended 4th respondent.

15. Mr Poon, on behalf of the Intended 4th respondent, identified three periods during which it was contended that the applicant should have had sufficient information to enable him to join the Intended 4th respondent. It was argued that the applicant had failed to put forward any satisfactory explanation for these three periods of delay.

E.1.1 From 20 November 2012 to 28 January 2015

16. First, Mr Poon urged this court to reject the applicant’s explanation for the delay on the ground of the late availability of the documents (on 28 January 2015) from the Labour Department. It was contended that even without the Accident Report and the other documents from the Labour Department, the applicant, had he acted promptly, should have been able to ascertain the identity of the principal contractor by making a request to the 2nd respondent who, as a sub-contractor, is statutorily obliged under s24 (3), to supply to the applicant the name and address of the principal contractor. Had such request been made, the applicant would have likely, it was contended, ascertained from the 2nd respondent the identity of the Intended 4th respondent before 28 January 2015.

E.1.2 From 28 January 2015 to 7 January 2016

17. It was suggested by Mr Poon that by 28 January 2015, the applicant already had the B.R. No. of the Intended 4th respondent from the documents that he had obtained from the Labour Department. By using the B.R. No., the applicant could have conducted a business registration search and discovered that it was Lam, not Li, who was Cheung On’s sole-proprietor.  Thus, Mr Poon argued that the applicant’s excuse that he had to wait until Law’s statement before taking out the joinder application was not valid.  

E.1.3 From 7 January 2016 to 22 April 2016

18. Lastly, Mr Poon contended that the applicant was not able to put forward any valid reason for a further 3 months’ delay between Law’s statement on 7 January 2016 and the issuance of this joinder application.

E.2 No s.24(6) notice

19. According to s 24(6), before making any claim or application against a principal contractor, an employee is required to serve a written notice on the former (not later than 2 years from the date of the accident in accordance with the time-limit stipulated in s.14).  Mr Poon argued that since no such notice as required by s.24 (6) had been served; the applicant should have given an explanation for this failure. However, the applicant had not done so and the court should take that into account when determining whether the applicant should be allowed to join the Intended 4th respondent out of time.

E.3 The case against the Intended 4th respondent was flimsy

20. It was Poon’s contention that the court should not grant indulgence to add the Intended 4th respondent when the applicant’s case against the latter was flimsy.

21. The merits argument is essentially based on the respective pleaded cases of Sky Field and the Intended 4th respondent in the related Personal Injuries proceedings the applicant instituted in the High Court, HCPI 1122/2015 (“PI claim”) against the parties in these proceedings as well as the Intended 4th respondent.

22. Since, Mr Poon suggested, it was going to be Sky Field’s pleaded case in the PI Claim that the Subcontract was null and void, the case against the Intended 4th respondent was weak.  The proposed pleaded case Mr Poon relied on was para 2(b) (iv) of Sky Field’s draft re-amended defence in which Sky Field alleged that the Subcontract had been concluded by the 3rd defendant (the 3rd respondent here) without the authority of the 4th defendant (the Intended 4th respondent).

E.4 Prejudice

23. Lastly, Mr Poon contended that since there was no evidence that the Intended 4th respondent knew of the Accident, the late joining of the Intended 4th respondent outside the two years’ time limit would mean that Lam had been deprived of an opportunity to preserve evidence.

F. Applicable legal principles on “reasonable excuse”

24. Both counsel have cited several court decisions[1] in their skeleton submissions on how the courts have in past cases determined the question of “reasonable excuse”.  It is however my view that a previous decision of a court, short of providing instructive guidelines as to the grant or refusal of an extension of time, would serve little useful purpose because the categories of what constitute “reasonable excuse” are not closed and this sort of application is mostly fact-sensitive.

25. One case that has provided useful guidance is the Court of Appeal decision of Tsang Loi Fat v Sun Fook Kong (formerly known as Sung Foo Kee Ltd (transliteration)[2] , which I had referred to counsel at the hearing. In that case, the Court has provided instructive guidance by listing a number of relevant factors a court may take into account when determining whether an explanation nay constitute “reasonable excuse”.

26. Based on the authorities counsel have referred to and the case of Tsang Loi Fat, the parties are in broad agreement that the test should be one of justice and merits, and the applicant bears the onus of showing that there was reasonable excuse for the whole period of delay. In considering the reason for the delay, the court should take into account various factors that may include whether the applicant’s failure to make a claim before the expiry of the prescribed period was induced by the conduct of or words said by, among others, a third party. In addition, the court should also have regard to any prejudice that might be occasioned to a respondent to the application[3].

G. Discussion

G.1 Whether the applicant has shown reasonable excuse for the delay

27. In relation to the first period of delay Mr Poon complained of, I do not think the facts support Mr Poon’s argument that a s.24 (3) notice could have yielded the necessary information to enable the applicant to ascertain the identify all the relevant sub-contractors including that of the Intended 4th respondent.

28. First of all, the applicant, before the commencement of these proceedings, had already been informed by the Labour Department that Sky Field was the alleged principal contractor. Hence, the difficulty the applicant faced was not the lack of information regarding the principal contractor but rather its sub-contractor(s). Section 24 (3) notice is about the giving of a notice to a sub-contractor for the disclosure of the identity of the principal contractor. Hence, I do not think this provision is relevant.

29. In any case, I believe that it is unlikely that the 2nd respondent would have been in a position to provide any information beyond what he had stated in his answer filed on 17 August 2015, in which only two parties had been alluded to, namely Li and a person named called Fung Kin Ping (transliteration) (馮建平). There was no reference at all to the Intended 4th respondent. In the circumstances, the giving of a s.24 (3) notice to the 2nd respondent would have obviously been a futile exercise.

30. Insofar as the 2nd and the 3rd periods of delay Mr Poon have complained of, they substantially relate to the applicant’s alleged failure in having taken prompt action after the B.R. No. was available to him by 28 January 2015.

31. It is indeed the case that by 28 January 2015, the applicant had already had the B.R. No as it was stated in the Subcontract, which copy had in fact been attached to Li’s statement (which was available to the applicant’s solicitor on 28 January 2015) as “Attachment 2”. However, it seems to be the applicant’s explanation that he had only had the B.R. No when the applicant’s solicitors were provided with a copy of the Subcontract by Sky Field on 10 February 2015. In either case, whether the B.R. No. was available to the applicant on 28 January or 10 February 2015 is not material, for the applicant’s reason for delay did not hinge upon the availability of the Subcontract.  As a matter of fact, according to a business registration search extract on 2 March 2015 Mr Yip submitted to court, the applicant had indeed conducted a search on the B.R.No. that confirmed Lam to be the only owner of Cheung On.

32. The applicant’s explanation was that although the Intended 4th respondent had been alluded to by the B.R. No, the applicant, due to all the apparent inconsistent allegations that were contained in Li’s statement and  Sky Field’s re-re-amended answer containing the positive assertions for the first time, could only make an informed decision to make the joinder application after Law’s statement.   

33. After having considered all the pleadings, including those of the PI Claim exhibited to Chan’s affirmation, I think the applicant’s complaint about the way Sky Field had pleaded its case has merit.  Before the 3rd respondent was added as a party to these proceedings, Sky Field did not put forth any positive case but only made a bare denial when it certainly could have pleaded the assertions presently contained in the latest answer.  On Sky Field’s present pleaded case in these proceedings, it seems that it was alleged that it had entered into the Subcontract with Li acting as Cheung On’s responsible person. This plea would however appear to be quite inconsistent with its proposed amended defence in the PI claim by alleging for the first time that the Subcontract as null and void.

34. In light of the seemingly confusing stance Sky Field, as the alleged principal contractor, has been adopting, I consider that it is reasonable for the applicant to have adopted a more cautious approach in evaluating all the evidence before he could make a decision to add a new party, for such an application would have costs implication (as Mr Yip has pointed out).

35. In Li’s statement, Li had made allegations that could have given an impression that he was, apart from the alleged responsible person of Cheung On (which was owned by Lam) [4], responsible for the entire Works including the acceptance of the Works from the Owner. In Li’s statement, it was alleged that owing to the alleged reason that Cheung On was not a registered contractor with the Buildings Department, he had used Sky Field to obtain the Works from the Owner[5].

36. These assertions, in my view, could not be lightly glossed over as they did not seem to be bare allegations. The two attachments to Li’s statement - the Subcontract and a document headed “Quotation” dated 6 November 2012 (“Quotation”) – seemed to suggest that Li, instead of Sky Field, was responsible for the entire Works.  In the Subcontract which was attached as attachment 2, it showed that Li had signed on behalf of Cheung On as the responsible person. The Quotation (which was attachment 1) was an agreement between Sky Field and the Owner regarding the price for the Work. What, however, seemingly a strange feature that I have noticed, is that the authorized person who had signed on behalf of Sky Field was named Paul Li. There is no evidence that Paul Li was Li. It is however a coincidence that the surname was the same as Li. It is probably that Paul Li might have in fact been Li, who had indeed been instrumental in obtaining the Works instead of Sky Field as Li has seemed to have alleged in Li’s statement.

37. The allegations contained in Li’s statement when read in conjunction with Sky Field’s also seemingly confusing stance, in my judgment, deserved serious consideration especially bearing in mind that Li’s assertions did not seem to be bare allegations. These allegations seem to suggest that the  relationships between Sky Field and Li on one the hand, and Li and the Intended 4th respondent on the other were not those reflected in the relevant documents such as the Subcontract. The convictions of Sky Field and Li[6] for their respective alleged roles of the principal contractor and employer consequent on the prosecutions brought by the Labour Department would have justified the applicant’s belief that the identities of the principal contractor and sub-contractor had been established before joining the Intended 4th respondent, irrespective of the information disclosed in the business registration search of the Intended 4th respondent.

38. In the circumstances, I consider that the applicant was justified in issuing the joinder application after he was served with Law’s statement that Sky Field had adduced as evidence to support its pleaded assertions.  In view of Sky Field’s stance and the allegations contained in Li’s statement, as well as the documents such as the Subcontract and the Quotation, I consider that it was not unreasonable, as a prudent litigant, to have another 3 months after Law’s statement to bring the joinder application. The applicant, in my judgment had provided a reasonable excuse for the delay.

G.2 Is the claim against the Intended 4th respondent meritorious?

39. It has been suggested that the applicant’s case against the Intended 4th respondent was only marginal and I should not grant indulgence for the late bringing of the claim.

40. According to the analysis above, I do not consider that the case against the Intended 4th respondent was weak as Mr Poon has contended.  In light of documents that were placed before me, I consider that the Intended 4th respondent was the correct party to be added so that all the matters in dispute in relation to the identities of the principal contractor and sub-contractor(s) can be properly determined at trial.

41. I do not consider that the pleadings filed in the PI claim are relevant to these proceedings. In any event, not only are the pleadings  not able to show that the case against the Intended 4th respondent was weak, they seem to fortify the applicant’s assertions that it was necessary to join the Intended 4th respondent.  

42. In any event, the pleaded case of the Intended 4th respondent in the PI claim, as Mr Yip submitted, looks suspicious.  According to the amended defence (at paras 3 and 4) of the Intended 4th respondent filed in the PI claim,  the 3rd respondent and the 4th respondent had both been using “Cheung On” as their trade names. The relationship between Li and Lam seemed to be also extremely close and intricate in that the 3rd respondent had occupied the same warehouse which the Intended 4th respondent had used to place his business registration certificate.

43. The pleaded case of the Intended 4th respondent when considered against the latest averments of Sky Field as well as the assertions Li made in his statement to the Labour Department all seem to suggest that it would not have been possible to have taken any of the assertions made either by Sky Field (in these proceedings as well as in the PI claim), Li (in Li’s statement) or the Intended 4th respondent (in its amended defence in the PI claim) at their face value.

44. In the circumstances, I respectfully disagree with Mr Poon that the case against the Intended 4th respondent is weak.

G.3 Any prejudice to the Intended 4th respondent?

45. It has been suggested that prejudice would be caused to the Intended 4th respondent as he did not have any knowledge of the Accident or the Subcontract. The Intended 4th respondent, in my judgment, has not demonstrated any prejudice that he might suffer were the Intended 4th respondent joined to the proceedings.

46. First, as Mr Yip has submitted, no explanation had been given for the Intended 4th respondent’s resiling from the consent that the Intended 4th respondent had given shortly before he filed his affirmation on 10 August 2016 in opposition to the joinder application. Secondly, Lam could not state what prejudice would be caused to him were the Intended 4th respondent joined to the proceedings.  Finally, Mr Poon was not able to, apart from a vague suggestion that “the evidence, in particular as to the role of Intended 4th Respondent, cannot be preserved as well”[7], to specify any prejudice.  

47. Last but not least, I also do not consider that the applicant’s failure to give a s24 (6) notice to the Intended 4th respondent has prejudiced Lam.  Section 24 confers on an employee an additional remedy against a principal contractor in additional to his direct employer, a sub-contractor.  The s24 (6) notice seems to be applicable to the giving of notice to a principal contractor.  In the present case, the Intended 4th respondent does not seem to have been added as the principal contractor but as a sub-contractor. It is therefore questionable whether the s24 (6) notice is applicable.  In any event, even if this requirement were applicable to the Intended 4th respondent, Mr Poon has not suggested that the failure to comply with s24 (6) will impose a complete bar to the applicant’s claim against the Intended 4th respondent.

H. CONCLUSION

48. For the foregoing reasons, I allowed the applicant’s application to join the Intended 4th respondent as the 4th respondent in these proceedings. 

(Katina Levy)
District Judge

  

Mr Richard Yip instructed by Or & Partners, assigned by the Director of Legal Aid, for the applicant

The attendance of Stephen Lo & PY Tse for the 1st respondent was excused

The attendance of the unrepresented 2nd respondent was excused

The 3rd respondent was not represented and did not appear

Mr Edward Poon instructed by Tsang, Chan & Woo for the 4th respondent



[1]Mohammad Zameer v Hopkins Construction Ltd, unreported, DCEC 2206/2012, 4 February 2015 was cited by Mr Yip. Mr Poon referred to Chan Man-lap v Secretary for Justice, unreported, DCEC 261/1998, 22 October 2001 and Liu Le Wen v Chan Sing & Anor, unreported,CACV 185/ 2007, 23 January 2008.

[2] [2011] 4 HKLRD 344.

[3]Liu Le Wen at para 10; Tsang Loi Fat [2011] 4 HKLRD 344 at 349 para 11.

[4]  “本人是長安的負責人。本人知道長安的東主是林國平,而他是本人的朋友,因此本人在外面接洽工程時便借用他的公司名義去接洽工程,而林先生並不參與該些業務工作,一切是由本人負責,只是借用了他的公司名。” (Hearing Bundle p.309).

[5] “在本人接到工程後借用天域的名義跟客戶簽訂合約,再由天域分判給“長安”去做。這樣做的原因是由於長安本身並沒有屋宇署的承建註冊,因此須要借用天域的名義。” (Hearing Bundle p.308).

[6] Sky Field and Li were respectively prosecuted in  labour summonses under cases nos. TWS 6802/2013 and TWS 6803/2013, for the contravention of Regulations 38C, 68(1)(a) and 68(2)(g), Construction Sites (Safety) Regulations made under the Factories and Industrial Undertakings Ordinance, Cap.59.  Both were convicted but Sky Field’s conviction was overturned on appeal.

[7] Mr Poon’s written submission, para 31.