HK CourtDB
HomeDirectoryMCP
Hong Kong CourtDB
Back to directory
Personal Injuries Action2015

TAI YUK CHEUNG v. HUNG SING CONSTRUCTION ENGINEERING CO. AND ANOTHER

Files (4)

[2018] HKCFI 739-EN-2018-04-12

TAI YUK CHEUNG v. HUNG SING CONSTRUCTION ENGINEERING CO. AND ANOTHER

HTML content

HCPI 298/2015

[2018] HKCFI 739

IN THE HIGH COURT OF THE

HONG KONG SPECIAL ADMINISTRATIVE REGION

COURT OF FIRST INSTANCE

PERSONAL INJURIES ACTION NO 298 OF 2015

_________________________

BETWEEN  
TAI YUK CHEUNGPlaintiff
And
HUNG SING CONSTRUCTION ENGINEERING CO.1st Defendant
YAU LEE – HSIN CHONG JOINT VENTURE2nd Defendant

_________________________

Before: Master Leong in Chambers

Date of Hearing: 6 March 2018

Date of Decision: 12 April 2018

________________

D E C I S I O N

________________

1.  This is a hearing to consider two wasted costs orders.

BACKGROUND

2.  Mr. Burke, the solicitor for the plaintiff, took out an application for specific discovery around August 2015 (the “First Discovery Application”).  In this court’s decision dated 1 June 2016 (the “First Decision”), most of the items sought under the application were dismissed and the parties were invited to fix a hearing for costs.

3.  I have indicated in the First Decision that, for the reasons specified in some details (which I need not repeat here), the hearing “would be an opportunity for Mr. Burke to address the court why a wasted costs order should not be considered”.

4.  Mr. Burke made an appeal against the First Decision and I have ordered that the costs hearing be adjourned pending the result of the appeal.

5.  Before the hearing of the appeal, Mr. Burke took out another application for specific discovery around May 2017 (the “Second Discovery Application”).  In a decision dated 30 November 2017 (the “Second Decision”), this court has dismissed the entire application.

6.  In the Second Decision, this court again set out reasons in some details and expressed concern in the way Mr. Burke has been handling the case.  I also note that Legal Aid Department has notified that the aided person’s Legal Aid Certificate did not cover the application.  I warned that a wasted costs order was being considered and again invite the parties to fix a hearing on costs.

7.  Subsequently, the appeal against the First Decision was heard before the Hon Mr. Justice Bharwaney and was dismissed with costs to the defendants summarily assessed at HK$80,000.  According to the Reasons for Decision, at that point, “Mr. Burke indicated that not only was he acting pro bono for the plaintiff but also that he wold personally discharge the costs order in favour of the 1st and 2nd defendants by paying the sum of HK$80,000 out of his own pocket.” Bharwaney J “did not make any order as to costs below as that matter still has to be determined.”

MATTERS IN DISPUTE

8.  As such, the current hearing was fixed to hear the issues for costs concerning both the First Discovery Application and the Second Discovery Application.

9.  Before the hearing, Mr. Burke has written to the court indicating that he has agreed with the plaintiff that he would personally “pay all adverse costs in respect of such applications – and will not charge him any common fund costs”. However, it would seem that he was only referring to the Second Discovery Application.

10.  During the hearing, Mr. Burke agreed that the hearing should deal with the costs of both the First and the Second Discovery Applications.

11.  After some submissions, Mr. Burke informed the court that he agreed to the court imposing wasted costs orders in both applications, except that he would only dispute as to the extent of the wasted costs order and the basis of the costs.

12.  According to PD14.5, imposing a wasted costs order would involve a 2‑stage procedure so that, amongst others, the party against which the order is considered would have ample opportunity to address the court.  As Mr. Burke now agreed to wasted orders being imposed, he has also agreed that such a procedure would not be required.

13.  As such, “the first stage hearing” is now redundant and this hearing is like “the second stage hearing” for the court to consider “how much of the wasted costs are the responsibility of the legal representative, specifying the extent of the costs recoverable in the award.” (see Hong Kong Civil Procedure 2018 PD14.5/7 on page 1937).

EXTENT OF THE WASTED COSTS ORDER

14.  As far as the extent of the wasted costs order was concerned, Mr. Burke submitted that there were 4 stages in the matter: the date of the initial request for the items, the date of the application to court with the plaintiff’s affidavit, the date of the affidavit in opposition, and the hearing date. He invited the court to look at each individual items requested for specific discovery and decide from which stage the wasted cost order should apply.  He raised criticisms on the defendants’ handling of the case including the lack of response to his initial requests.

15.  I would not take this approach as this would make this into a “full-on” taxation process.  The jurisdiction exercised under O.62 r.8 is a summary jurisdiction bearing in mind the principle of proportionality (see Hong Kong Civil Procedure 2018 under 62/8/8 on page 1240).

16.  Further, the legal principle of specific discovery should apply even at the earliest stage.  The plaintiff cannot justify seeking costs of writing letters requesting specific discovery of numerous items when it was later shown that all along there was no evidence to show his belief that such documents existed and, as such, the letters were all along “fishing exercises”.  This was especially when the whole specific discovery exercise was done in an unreasonable, unsatisfactory, oppressive, frivolous and costs-disproportionate manner that has been described in details in the First Decision, Second Decision as well as the Reasons for Decision of the appeal.

17.  Accordingly, I would adopt a summary approach.

18.  For the First Discovery Application, as I stated in paragraph 105 of the First Decision, out of the 40 items requested, only 3 were of possible relevance to the claim.  I would therefore find that Mr. Burke should personally be liable for 90% of the 1st and 2nd defendants’ costs of and occasioned by this application.  The remaining 10% should be remain as costs in the cause.

19.  As for the Second Discovery Application, I have stated in paragraph 51 of the Second Decision my concern that Mr. Burke did not take heed of any “fair warning” in the First Decision but had persisted.  The entire application was dismissed.  I would therefore find that Mr. Burke should personally bear the entire costs of and occasioned by the 1st and 2nd defendant’s in this application.

BASIS OF COSTS

20.  Mr. Burke suggested that the costs should be on a party and party basis.

21.  Under paragraph 62/8/9 on page 1240 of the Hong Kong Civil Procedure 2018: “The jurisdiction is not merely punitive but compensatory.  The order is for payment of costs thrown away or lost because of the conduct complained of.  It is frequently exercised in order to compensate the opposite party in action…The costs are usually ordered on indemnity basis.”

22.  However, Mr. Burke referred to PD14.5/7 on page 1937 of the Hong Kong Civil Procedure 2018: “33. Where a wasted costs order is made such costs would normally be payable by the legal representative on a party and party basis...”

23.  This may appear contradictory but one must read the paragraph above: “32. The costs of the wasted costs order application itself are also discretionary.”

24.  Further, what follows in paragraph 33 states: “…But account should be taken of any account on the part of the legal representative and the applicant in the course of the wasted costs proceedings which may indicate a different Order should be made.”

25.  Thus, it is clear that “the party and party costs payable normally” only refers to the costs of the wasted costs proceedings, not to the costs of the subject application of the wasted costs order where paragraph 62/8/9 still applies.

ORDER

26.  I would therefore make the following order:

a) There be a wasted costs order for Mr. Burke to personally bear 90% of the costs of and occasioned by 1st and 2nd defendants in the First Discovery Application on an indemnity basis, with the remaining costs be in the cause;

b) There be a wasted costs order for Mr. Burke to personally bear 100% of the costs of and occasioned by the 1st and 2nd defendants in the Second Discovery Application on an indemnity basis;

c) The costs of and occasioned by the wasted costs proceedings be personally payable by Mr. Burke to the 1st and 2nd defendants on a party and party basis;

d) There be no Legal Aid taxation for the plaintiff’s own costs; and

e) If there is no agreement as to costs, the 1st and 2nd defendants shall within 28 days of the order lodge and serve a summary bill of costs and Mr. Burke shall lodge and serve a list of objections 28 days thereafter.  The costs will be summarily assessed on paper.

(Harold Leong)
Master of the High Court

Mr. Patrick Burke of Burke & Company, for the plaintiff

Ms. Susanna Lam of William Lee & Associates, for the defendants

[2018] HKCFI 76-EN-2018-01-16

TAI YUK CHEUNG v. HUNG SING CONSTRUCTION ENGINEERING CO AND ANOTHER

HTML content

HCPI 298/2015

[2018] HKCFI 76

IN THE HIGH COURT OF THE

HONG KONG SPECIAL ADMINISTRATIVE REGION

COURT OF FIRST INSTANCE

PERSONAL INJURIES ACTION NO 298 OF 2015

__________________________

BETWEEN
 TAI YUK CHEUNGPlaintiff
and
 HUNG SING CONSTRUCTION1st Defendant
 ENGINEERING CO 
 YAU LEE – HSIN CHONG JOINT VENTURE 2nd Defendant

__________________________

Before: The Hon. Mr Justice Bharwaney in Court
Date of Hearing: 4 December 2017
Date of Decision: 4 December 2017
Date of Reasons for Decision: 16 January 2018

________________________

REASONS FOR DECISION

________________________

1.  This is an appeal from the decision of Master Leong dated 1 June 2016 dismissing the plaintiff’s application for specific discovery.

2.  The unusual feature of this case and the reason why the appeal was heard so late is that the plaintiff, who is legally aided, does not have a legal certificate for the appeal.  He is represented by Mr Patrick Burke on a private basis. Indeed, I must confess this is the first time I have seen, in a legally aided case, the assigned solicitor acting for the client on a private basis.

3.  The Director of Legal Aid (“the Director”) has refused to extend the legal certificate to cover the appeal proceedings.  An appeal was lodged before the Master against the legal aid refusal, and the Master dismissed the appeal.  I have not been provided with the Master’s reasons for dismissing the legal aid appeal but it is obvious to me that he did so because he agreed with the Director that there were no reasonable prospects of success on the appeal.

4.  Notwithstanding the contrary opinion of the Director and the Master, Mr Burke has advised his client that he has reasonable grounds of appeal.  No doubt it was based on that advice that client instructed Mr Burke to act for him on the appeal on a private basis.

5.  The rules permit this to be done.  I have done some research in this area, and I find that the legal aid regulations support Mr Burke’s stance that the legal proceedings could be partly legally aided and partly not.  There is also a provision in the Legal Aid Ordinance itself, which supports Mr Burke’s position that he can act on a private basis for the legally aided person.

Legal Aid Regulations, Cap. 91A

6.  Regulation 5(1) provides that “A certificate may be issued in respect of the whole or a part of – (a) proceedings in a court of first instance; ...” [My emphasis]. It is implicit from this provision that legal proceedings could be partly legally aided and partly not legally aided.

7.  Regulation 6A(e) provides that “The Director may amend a certificate where in his opinion ... it has become desirable for the certificate not to extend to certain of the proceedings in respect of which it was issued; ...” [My emphasis].  This provision allows the Director to limit the steps that could be taken by the assigned solicitor in the legally aided proceedings.

8.  The combined effect of these two provisions is that an assigned solicitor is permitted to act for the aided person on a private basis for certain part of proceedings which is not covered by the legal aid certificate.

9.  Examples of this practice can be seen in different contexts:

(a)   A respondent may be granted legal aid to defend a divorce proceedings “limited to custody and ancillary relief”.  However, the assigned solicitor is permitted to act for the aided person on a private basis to defend the main suit (for example, seeking to amend the grounds for divorce from unreasonable behaviour to separation) provided, of course, that the Director is informed and the Court and the petitioner are made aware that this part of the suit is not legally aided.

(b)   Legal aid may be granted to a defendant to defend a damages claim but not extended to cover a counterclaim. The assigned solicitor may act for the aided person on a private basis to pursue a counterclaim so long as the Director, the Court and the other parties are informed.

(c)   In criminal cases, legal aid may be granted to defend certain criminal charges but not extended to cover arguments on choice of language and venue of trial. The legal team may act the aided person on a private basis.

Legal Aid Ordinance, Cap. 91

10.  Section 22 provides that “… no person who, pursuant to any reference under this Ordinance,  makes any investigation or report or gives any opinion or certificate or who acts for an aided person, shall take or agree to take or seek from an aided person any fee, profit or reward (pecuniary or otherwise) in respect thereof” [My emphasis].  Section 22 is not applicable if the assigned solicitor has instructions to act for an aided person for matters or certain steps in the proceedings which are not covered by the legal aid certificate.

Guidance Notes to Solicitors Handling Civil Cases

11.  I refer to the following extract from “Chapter 7 - Guidance Notes to Solicitors Handling Civil Cases” of the Director’s “Manual for Legal Aid Practitioners” at pp.16-17:

“3. Legal Aid Certificate and Assignment

3.1 The assignment of cases to you is made on the condition that you do not have any perceived or actual conflict of interest and it is incumbent on you to return the papers to the Director if such condition could not be fulfilled.

3.2 The Legal Aid Certificate (“the Certificate”) provides the authority for the Director of Legal Aid (“the Director”) to pay counsel and solicitors for acting for an aided person. Solicitors should check the scope of the Certificate. If the Certificate is limited, payment will not be made for work done outside the scope of the certificate. Prior to undertaking any work outside the terms of the Certificate, you must apply to the Director for extension of the Certificate giving all necessary information justifying the extension by using Form X47 which can be downloaded from the website of the Legal Aid Department (www.lad.gov.hk). Solicitors should make timely application for extension of the scope of the Certificate and give the Director sufficient time to raise queries on the continued merits of the case.”

12.  Whilst §3.2, which deals with the extension of legal aid, may appear to be of some relevance, it is only applicable to the situation where an extension of the legal aid certificate is being requested by the assigned solicitor and does not cover the scenario where certain steps are to be undertaken on a private basis.  As stated above, the Director must be kept informed of any work undertaken on a private basis.  Upon being informed, the Director may exercise all his powers in connection with the provision of legal aid, including the power to discharge legal aid where necessary.

The Legal Aid Handbook

13.  The following passages from the U.K. Legal Aid Handbook pp.151-152 bear on the point under consideration:

“Certificates for a specific step

If a certificate is issued to cover only a specific step in an action, for example, to purge the assisted person’s contempt, and on completion of that specific step, no further steps in the action are expected, the assisted person’s solicitor should apply promptly, with his client’s agreement, for discharge of the certificate and serve the appropriate notices of discharge.

If further steps in the action are contemplated, the assisted person’s solicitor should apply promptly for an amendment of the certificate. If the amendment is refused, but discharge of the certificate has not been effected or is not yet appropriate, regulation 64 does not then prevent the solicitor from acting privately for his client in the steps for which an amendment was sought and refused.

Certificates not granted in full

If an application for legal aid is only partially granted, for example, an application for legal aid to cover a defence and counterclaim is made but a certificate is granted only to defend, then regulation 64 does not prevent the solicitor from acting privately for his client in that part of the action (the counterclaim) which is not covered by the legal aid certificate. This applies also where an application for legal aid is made to cover defending divorce decree proceedings and representation as to ancillary relief, but legal aid is granted only to cover ancillary relief. Regulation 64 does not prevent the solicitor from acting privately in defending the decree proceedings.

Before acting privately for a client in any steps in an action in which the client is legally aided, his solicitor should first either:

(a) ensure that an appropriate application for legal aid or for an amendment has been made and refused; or

(b) have his client’s consent either:

(i) not to apply for legal aid for an amendment to cover the step or steps; or

(ii) to act prior to the application being determined

and in either case should ensure that he:

(a) has his client’s instructions to act privately;

(b) explains what this means; and

(c) advises his client that the legal aid area office will have to be informed.

Whether a solicitor is instructed to act privately for a client in an action in which the client is legally aided, he should inform the appropriate area office in writing, as soon as possible, explaining the reason.  The very fact that an assisted person is also instructing his solicitor privately may be a matter which the area office should take into account when considering whether it is reasonable for the assisted person to continue to receive legal aid. See p. 586 for the solicitors’ professional conduct requirements concerning advice to clients on the availability of legal aid.”

14.  It is expressly acknowledged in the U.K. Legal Aid Handbook that an assigned solicitor is not prevented from “acting privately for his client in the steps for which an amendment was sought and refused.”

15.  The assigned solicitor’s obligations include the obligation to ensure that he has client's instructions to act on a private basis; the obligation to explain to the client what that means, including explaining to the client the costs implications and the lack of costs protection without legal aid; and the obligation to inform the Legal Aid Department.

16.  The court and all parties to the proceedings should also be informed expeditiously by the assigned solicitor that he is conducting a certain step of the proceedings on a private basis and that such step is not covered by the legal aid certificate. The other parties ought to be informed as soon as possible so that they are not under any false impression that any costs that they successfully recover from the aided person would be satisfied from the Legal Aid fund.  In this case, the solicitors for the defendants have been well aware that Mr Burke was acting on a private basis in this particular appeal.

Law Society’s Guide to Professional Conduct

17.  To complete the review, I refer to §10.06 in Chapter 10 on “Limited Instructions for Appearance in Court” of the “Law Society’s Guide to Professional Conduct” which also supports the proposition that an assigned solicitor can act on a private basis for the aided person:

“10.06 LIMITED INSTRUCTIONS FOR APPEARANCE IN COURT

A solicitor may accept instructions limited to a particular matter or issue in the proceedings, such as an application to adjourn the proceedings. Where a solicitor accepts limited instructions, he shall inform the court before which he has been instructed to appear of the limited nature of his instructions at the first available opportunity after his acceptance of such instructions, and preferably before the solicitor’s appearance.

Commentary

1. Before he accepts limited instructions, the solicitor should fully advise the client of the possible legal and cost consequences.

2. The client should be made aware and the solicitor should appreciate that once he is on the court record he cannot withdraw from representation without the leave of the court.

3. If counsel is also making a limited appearance on the instruction of the solicitor, the solicitor should ensure that counsel appreciates that the court’s consent will be required for withdrawal and it is desirable that he and counsel plan for the contingency of refusal by the court.”

Conflict of Interest

18.  Mr Burke’s locus to be here is not in issue.  What is in issue is whether or not he has put himself in conflict with his client’s interests.  It appears to me that he has put his own personal interest in conflict with his client’s interests.  The conflict arises because, at the conclusion of the hearing before him, Master Leong wanted to fix a hearing for Mr Burke to be afforded an opportunity to address him why a wasted costs order should not be made.  Later, Master Leong decided that the hearing to consider making a wasted costs order ought to be put on hold until these appeal proceedings were concluded.

19.  The fact that the rules permit this peculiar situation of the solicitor acting on a private basis in a legally aided case does not take away the fundamental obligation of the solicitor not put himself in a position of conflict with his own client. 

20.  When I learned that Mr Burke was acting in the appeal on a private basis, I had written to him to ask whether or not he was acting pro bono for the aided person. He replied in the negative and also stated that the plaintiff knew that any adverse costs orders could be enforced directly against him.

21.  When Mr Burke opened the appeal before me, I pressed him on the issue of conflict of interest as follows:

“… Mr Burke, … you are advising your client to pursue this appeal, notwithstanding the fact that [The Director of] Legal Aid considers [that] there are no reasonable grounds of appeal, notwithstanding the fact that the Master, in refusing the appeal from the legal aid refusal, must have been of the same view. … notwithstanding that, you have persisted in advising your client, not only that he has reasonable grounds of appeal, but that he should actually instruct you privately, not on a pro bono basis, instruct you privately to advance this appeal on his behalf, and well knowing that if you should lose the appeal, that he will be personally liable for the costs, including the defendant’s costs of the appeal, which may come out from any damages he may be subsequently awarded, or if he loses the action, might result in him becoming bankrupt.

…

… Very simple, Mr Burke, why would you give him that advice, if not to avoid a wasted costs order? Is this not a direct conflict of interest case?

…

… you have your own personal interest here to avoid a personal wasted costs order, and despite [The Director of] Legal Aid and a Master saying, in effect, that there are no grounds of appeal, you advised the client to instruct you to pursue to appeal?

…

The fact that the rules allow … this peculiar situation of the solicitor acting on a private basis in a legally aided case does not take away the fundamental obligation of the solicitor not put himself in a position of conflict with his own client.”

22.  At this point, Mr Burke confirmed to me that he was willing to act on a pro bono basis in the appeal. I then asked Mr Burke to consider, notwithstanding that he was now willing to act pro bono, whether he was still in a position of conflict in that he was exposing his client to the risk of an adverse costs order from an unsuccessful appeal.  However, Mr Burke persisted in pursuing this appeal. 

The Appeal against the Master’s Order

23.  This is a personal injury action commenced by the plaintiff who was employed by the 1st defendant, a subcontractor of the 2nd defendant which was the principal contractor at a construction site at the old Kai Tak Airport.  The plaintiff was assigned to install kitchen units in the apartments that had been constructed at the site.

24.  There were some glass panes that were stored in the apartment in which the plaintiff was working. They were stored there pending their installation into the window frames of the apartments.  In the process of installing the base of a kitchen stove, the plaintiff’s left hand came into contact with the glass panes and he suffered a 3 cm cut to his left index finger, including a 70% cut of one of the two extensor tendons. 

25.  On these pleaded facts, the issue that arose was whether or not these glass panes were stored in an unsafe place creating a hazard to workers like the plaintiff installing kitchen units in the apartments at the Kai Tak site. 

26.  Against this background, Mr Burke has sought discovery of numerous documents which are set out in the Appendix. 

27.  By the time of the hearing before Master Leong, the request had been reduced to some 12 items that were set out in the Appendix. Although reduced, these were very substantial items, with a substantial number of documents requested against each item: -

(1)   Item 1 against the 2nd defendant (Contract with Developer);

(2)   Item 2.1 against the 2nd defendant (Accident / incident book or reports);

(3)   Item 2.3 against the 2nd defendant (Safety management system);

(4)   Item 2.4 against the 2nd defendant (Safety Officers);

(5)   Item 2.5 against the 2nd defendant (Risk assessments);

(6)   Item 4.1 against the 2nd defendant (Statutory report);

(7)   Item 4.4 against the 2nd defendant (Witness statements);

(8)   Item 5.1 against the 2nd defendant (Other accidents);

(9)   Item 6.1 against the 2nd defendant (Plan of the apartment);

(10)   Item 6.2 against the 2nd defendant (Documents showing dimensions of glass);

(11)   Item 7.1 against the 1st defendant (Contract of employment at the time of accident);

(12)   Item 7.5 against the 1st and 2nd defendants (Current wages of 3 comparable workers).

28.  There was no controversy about the principles to be applied in an application for specific discovery under Order 24, rules 7 and 8 of the Rules of the High Court, and Master Leong correctly set out those principles in §§61 to 64 of his decision. Cheung JA summarised those principles in Paul’s Model Art Gmbh & Co. KG v. UT Ltd. [2006] 1 HKC 238 at p.247 as follows:

“(1) There is no jurisdiction to make an order under RSC, O.24, r.7, for the production of documents unless

(a) there is sufficient evidence that the documents exist which the other party has not disclosed;

(b) the document or documents relate to matters in issue in the action;

(c) there is sufficient evidence that the document is in the possession, custody or power of the other party.

(2) When it is established that those three prerequisites for jurisdiction do exist, the court has a discretion whether or not to order disclosure.

(3) The order must identify with precision the document or documents or categories of document which are required to be disclosed, for otherwise the person making the list may find himself in serious trouble for swearing to a false affidavit, even though doing his best to give an honest disclosure. (See: Berkeley Administration v. McCelland [1990] FSR 381)”

29.  Superimposed on the requirement under Order 24, rule 8, which states that an order for specific discovery may be refused if, in the opinion of the court, the discovery sought was not necessary either for fairly disposing of the cause or matter, or for saving costs, is the additional requirement, since the advent of the Civil Justice Reform, of the need to look closely at costs implications and proportionality.

30.  Master Leong, guided by the above principles, decided that the documents listed under the 12 items considered by him were neither relevant nor necessary, and, accordingly, he refused to order specific discovery of the documents that had been sought.  The appeal against his decision has been brought in respect of the 8 of the said 12 items, which are set out in the following summary prepared by Mr Burke:

Appeal Item No.Item No. before Master LeongDocumentRelevance / ExistenceResponse of DefendantsRuling of Master Leong
1. 1.1 Contract between Housing Authority and D2
 
1. Must be a contract
2. Imposes safety management plan
1. D1 – not have
2. D2 – exists, but is irrelevant
Not relevant / necessary [para. 69]
2. 2.1 Safety / Accident Book 1. Common requirement on sites (page 3 HA plan)
2. Similar fact evidence
1. D1 – no
2. D2 – have, but irrelevant and not proportional
 
?
3. 2.3 Safety Management Plan 1. Statutory requirement
2. Housing Authority requirement
3. Sets out safety scheme (which in this case – includes Daily inspections before work starts)
 
1. D1 – No
2. D2 – Have, but irrelevant
Not relevant / necessary [para. 69]
4. 2.4 Qualifications of Safety Staff 1. D’s employ safety staff – not denied
2. Are properly trained / attending the site
1. D1 – no safety staff
2. D2 – Yes – but
·   Irrelevant
·   Not relevant
on issue of fault
 
Not relevant / necessary [para. 69]
5. 2.5 Risk Assessments
(“RA”)
1. Fundamental basis of current safety schemes – identify the risks and then exclude or adapt for them
2. D’s admit there are RA (through their defence)
 
1. D1 – now says is none
2. D2 – Yes, but
·   Irrelevant
·   Not proof of fault
 
Not relevant / necessary [para. 69]
6. 4.2 Accident Reports 1. HA have detailed system for reporting
2. D only give simple Investigation report and copy Form 2
3. Should be (page 3 Safe Working Cycle)
·   Report to Police
·   Report to Labour Department
·   Notify CM
·   Report to EMDTG
·   Submit DO Report
·   Report at Monthly Meeting
 
1. D1 – No
2. D2 – None
Already disclosed [para. 87]
7. 4.4 Statement of Witness Common practice 1. D1 – none
2. D2 – clearly does not exist
 
Not exist [para.70 – 75, 42]
8. 6.1 Plans of the Accident Flat 1. Must have – is being built
2. Dispute on dimensions
 
1. D1 – not have
2. D2 – not have
·   Irrelevant
 
Not necessary / relevant [para. 69]
 

31.  I have considered carefully the submissions of Mr Burke as well as the submissions of Mr Dennis Law who appeared for the defendants. I am not satisfied that Master Leong was wrong in his decision. I am required to consider this appeal by way a hearing de novo.  Doing so, I come to the same decision as Master Leong did.

32.  It is not proportionate to seek and obtain discovery of the construction contract between the Housing Authority and the 2nd defendant in respect of this very large construction project, in a case such as this involving a very simple accident where the only issue is whether or not the glass panes were negligently stored in those premises.  For the same reason, I am of the view that it is not proportionate nor necessary, either to fairly dispose of the case or to save costs, to order discovery of any of the other documents sought to be produced, including the following documents being sought that pertain to “Other Accidents”:

“2. Safety at the Construction Site

2.1 Other accidents

1. Safety / accident book

2. Recording incidents / dangerous occurrences/ near misses

…

2.3 All documents relating to the safety management system operated by the Defendant, including:

1. The company safety policy statement

2. Safety plans

3. Minutes of safety committees

4. All documents relating to safety audits or safety reviews

5. All documents relating to safety training to the employees of the Defendant

6. Form 2 & 3 for the period covering 6 months before and after the accident, prepared pursuant to the Factories & Industrial Undertaking (Safety Officers & Safety Supervisors) Regulations, Cap 59 – or similar documents

2.4 All documents relating to the employment of, and qualifications, of safety officers and safety supervisors at the site

2.5 Risk Assessments”

33.  Discovery was also sought of the following documents relating to the accident in question:

“4. The Accident

…

4.2 Accident investigation report prepared by or on behalf of the Defendants, including reports prepared pursuant to regulation 15(1) of the Factories & Industrial Undertakings (Safety Officers & Safety Supervisors) Regulations, Cap 59

…

4.4 Statements from witnesses”

34.  As Master Leong noted in his decision, the accident report prepared by the Safety Officer has already been disclosed.  It was common ground that the plaintiff was working alone at the time and that there were no witnesses to the accident.  There was no evidence to support the existence of any statement of any witness that was taken in relation to this accident.

35.  I have arrived at this decision in the context of the circumstances of the case where the Form 2 has been produced, and where the accident report in relation to this specific accident has been produced.  If I were the trial judge in this simple case, the only document that I could possibly be interested in having before me, from the entire list of the documents that have been sought, would be a risk assessment report on the placing and the storage of glass panes into these apartments pending their installation at a later date.  However, I am not satisfied that there is sufficient evidence to establish that a risk assessment report in relation to the work practice of storing glass panes in these apartments was in existence.  It is highly unlikely that a risk assessment report would have been produced for such a simple process.  It is obvious that there were risk assessment reports in respect of different aspects of the works, including many hazardous works, to be undertaken on this large construction project but these reports have no relevance to the accident which is the subject matter of this action.

36.  The accident report in respect of this accident has a layout plan of the apartment in question but this plan does not show any dimensions of the internal rooms and the kitchen.  Whilst the plans of the apartment where the accident occurred would have been of assistance to the court, it is clear from the affidavit filed on behalf of the defendants that they are not in possession of any such plans.  I am not satisfied that the plaintiff has made out a prima facie case that any such plans are in the possession of the 2nd defendant. 

37.  It is not proportionate nor necessary, either to fairly dispose of the case or to save costs, to order specific discovery of the very wide scope of documents that were sought.  When considered in the context of the simple factual issues raised in this action, it is clear to me that the application for specific discovery of the very wide scope of documents that were sought was oppressive.

38.  For these reasons, I dismissed the appeal.

[Submissions on Costs]

39.  After hearing further submissions, I awarded costs of the appeal to the 1st and 2nd defendants summarily assessed, by consent, in the sum of $80,000.  At this point, Mr Burke indicated that not only was he acting pro bono for the plaintiff but also that he would personally discharge the costs order in favour of 1st and 2nd defendants by paying the sum of $80,000 to them out of his own pocket.

40.  I did not make any order as to the costs below as that matter still has to be determined.

41.  Before adjourning,  I expressed the hope that the parties would quickly settle this straight forward case either by mediation or by negotiation between the solicitors acting for the parties.

  

  

 (Mohan Bharwaney)
 Judge of the Court of First Instance
High Court

  

Mr Patrick Michael Burke, of Burke & Company, for the plaintiff

Mr Dennis S M Law, instructed by William Lee & Associates, for the 1st and 2nd defendants


APPENDIX

“1. The Construction Site

1.1 Contracts

1. Contract between D2 and HK Housing authority

1.2 Statutory notice

1. Notice of

(a) Commencement – with name of every subcontractor

(b) Further information

(c) Change

(d) Completion

of Construction work to Labour Department – form LD 202

2. Notification of establishment of workplace

2. Safety at the Construction Site

2.1 Other accidents

1. Safety / accident book

2. Recording incidents / dangerous occurrences / near misses

2.2 Employees Handbook

2.3 All documents relating to the safety management system operated by the Defendant, including:

1. The company safety policy statement

2. Safety plans

3. Minutes of safety committees

4. All documents relating to safety audits or safety reviews

5. All documents relating to safety training to the employees of the Defendant

6. Form 2 & 3 for the period covering 6 months before and after the accident, prepared pursuant to the Factories & Industrial Undertaking (Safety Officers & Safety Supervisors) Regulations, Cap 59 – or similar documents

2.4 All documents relating to the employment of, and qualifications, of safety officers and safety supervisors at the site

2.5 Risk Assessments

2.6 Method statement for work being done by the Plaintiff at the time of the accident

3. The work being done by the Plaintiff

3.1 Permit to work

3.2 Written instructions given to the Plaintiff / his team of workers

4. The Accident

4.1 Statutory report made under FIU Regulations – Section 17, or Employee’s Compensation Ordinance

4.2 Accident investigation report prepared by or on behalf of the Defendants, including reports prepared pursuant to regulation 15(1) of the Factories & Industrial Undertakings (Safety Officers & Safety Supervisors) Regulations, Cap 59

4.3 Photographs of the accident scene

4.4 Statements from witnesses

5. Previous / subsequent accidents

5.1 Same document as in 4 – for previous / subsequent similar accidents

6. The flat / Glass panes

6.1 Plan of the flat

6.2 Dimensions of glass panes

7. Employment

7.1 Contract of employment between the Plaintiff and the Defendant, or other documents etc. to identify the terms and conditions of employment – including different items / categories of wages and allowances

7.2 Personal records file of the Defendant for the Plaintiff including

1. Leave record

2. Training record

3. Performance appraisal

7.3 All documents relating to payments to the Plaintiff in the period of 12 months prior to the accident:

1. Time card record / daily signing record / computer scanner

2. Monthly pay slips

3. Record of wages paid

4. MPF/ ORSO record

5. Return to IRD

7.4 All documents relating to payments to the Plaintiff following the accident for:

1. Sick leave pay

2. Payment for re-imbursement for medical expenses

3. Payment for or re-imbursement for non-medical expenses

4. MPF records

5. Return to Inland Revenue

7.5 Records of wages paid to person(s) (up to 3 employee’s) currently employed by the Defendant in the same or similar position to that occupied by the Plaintiff, for the last 12 months – with documents to show

1. Their name

2. Their job title

7.6 Records of wages paid to person(s) (up to 3 employee’s) currently employed by the Defendant who have suffered similar injury and disability as the Plaintiff – with documents to show

1. Their name

2. Their job title

3. Their disability / previous accident”

 

112544-EN-2017-11-30

TAI YUK CHEUNG v. HUNG SING CONSTRUCTION ENGINEERING CO. AND ANOTHER

HTML content

HCPI 298/2015

IN THE HIGH COURT OF THE

HONG KONG SPECIAL ADMINISTRATIVE REGION

COURT OF FIRST INSTANCE

PERSONAL INJURIES ACTION NO 298 OF 2015

_________________________

BETWEEN
 TAI YUK CHEUNGPlaintiff
 and
 HUNG SING CONSTRUCTION ENGINEERING CO.1st Defendant
 YAU LEE – HSIN CHONG JOINT VENTURE2nd Defendant

_________________________

Before: Master Leong in Chambers

Date of Hearing: 1 November 2017

Date of Decision: 30 November 2017

___________________

D E C I S I O N

___________________


1.  This is the plaintiff’s second application for specific discovery. I have already dismissed the plaintiff’s first application in a Decision dated 1 June 2016 (the “Previous Decision”). The background of the case has been set out in some details in the Previous Decision so I need not repeat here.

2.  Incidentally, the plaintiff made the application under “Order 24 Rule 7A of the Rules of the High Court, Cap. 4” which is wrong: it should be under Order 24 Rule 7.

3.  In this application, the plaintiff is seeking discovery of 3 “classes” of documents.

Documents on “instruction or training”

4.  The plaintiff firstly sought:

“(1) All documents to support the contention by the 1st and 2nd defendants that the plaintiff had been instructed or trained – to arrange himself the removal of the glass window panes himself – as detailed in witness statement of:

(a) Mr. Chu (for D1) – under paragraph 8

(b) Mr. To (for D2) – paragraph 5”

5.  Paragraph 8 of the witness statement of Chu Kau dated 5 January 2016 stated, as translated into English:

“At the time of the alleged accident, there were workers from other subcontractors…Under general circumstances, if anything placed in the construction site impeded the progress of work, a worker should inform the related contractor or principal contractor so that they would arrange people to remove it. If the thing can be easily removed, the worker may consider removing it by himself or seeking assistance from other workers to remove it for the work to progress. In fact, the situation is commonplace in construction sites. General experienced construction site workers must be clear about and understand the situation.”

6.  Paragraph 5of the witness statement of To Cheuk Hon dated 5 January 2016 stated, as translated into English:

“As far as I know, the glass pieces placed in the kitchen were for the installation of the aluminium windows in the unit…If any materials placed in the construction site blocked any work from progressing, under normal circumstances, a worker should inform the foreman of the block so that he would ask the related subcontractor or the principal contractor to arrange workers to handle it. He should not move other people’s materials by himself so that injury or damage to the materials could be prevented. However, some workers did not bother to do that, but moved the materials by themselves or moved…with help from other workers… At any rate, if any material…really blocked the progress of work, the site worker must make arrangements for it to be removed, but should not ignore the material.”

7.  In short, what both statements stated was no more than: when building materials impede work, the worker is expected to apply his common sense to ask someone responsible to move them etc.

8.  The plaintiff’s application cannot be more misconceived: nowhere in these paragraphs can one find any “contention by the 1st and 2nd defendants that the plaintiff had been instructed or trained – to arrange himself the removal of the glass window panes himself”, let alone any evidence that there are documents for such “instructions or trainings”.

9.  Suffice to say, in the Third Affidavit of Patrick Michael Burke (the plaintiff’s solicitor) filed on 12 May 2017, he raised no evidence to support any belief that there was such “instructions and trainings” and further that documents on such existed.

10.  One would have thought that if the plaintiff had received “instructions and trainings” and had come across any documents on the matter, he himself, and not Mr. Burke, should have made the affidavit.  In fact, Mr. Burke stated in his Third Affidavit (in paragraph 20) that “The plaintiff does not agree that there was such a system” of training.

11.  I am baffled as to the logic of Mr. Burke in seeking specific discovery of documents of training when the plaintiff stated that there was no system of training and the defendants never said that there was.

12.  In the Previous Decision, I have raised concern about the handling of this case by Mr. Burke and this is another example.  One concern is whether Mr. Burke has failed to read the witness statements properly, or whether he has failed to understand the basic concept of specific discovery that he needed to produce evidence to support the belief that “the party from whom discovery is sought under this rule has, or at some time had, in his possession, custody or power the documents…described in the application…” (Order 24, r.7(3) Hong Kong Civil Procedure 2018 edition P.631).

13.  Either scenario would be troubling given the experience of Mr. Burke, but if Mr. Burke has not misread the witness statements nor misconceived the legal concept of specific discovery, the alternative explanation might be that this was a deliberate attempt to waste time and costs, and to “bully” the other party into an oppressive time and costs wasting exercise at the same time.

14.  I understand that the solicitors for the 1st and 2nd defendants have, before the hearing, written to Mr. Burke confirming that there was no such document. Mr. Burke confirmed that he was no longer pursuing such, and the only matter concerned would be costs.

15.  Mr. Burke somehow sought to justify this application because “the defendants had neglected to respond to the written request for such documents” and sought costs.

16.  It was, of course, Mr. Burke who “neglected” to properly read (or, worst, intentionally misread) the witness statements in the first place. It should be to clear any reasonably competent lawyer that pursuing specific discovery of such documents was futile right from the beginning.  I see no reason why the defendants should be “bullied” into a time wasting exercise arguing the obvious.

Documents to record “inspection system”

17.  The plaintiff also sought:

“(2) All documents to record the 1st and/or 2nd defendants’ system for inspections of work places to ensure they are safe, as referred to by Mr. To (D2 Safety Officer) in paragraph 12 and 14 of his witness statement (which is believed to be the Inspection system set out under the Safe Working Cycle).”

18.  Paragraph 12of the witness statement of To Cheuk Hon dated 5 January 2016 stated, as translated into English:

“Every day before the commencement of work in the construction site, there was a morning safety meeting for the purpose of reminding workers of the need to pay attention to safety issues. The Safety Department also held safety meetings, from time to time, with the subcontractors for the purpose of reminding them of the need to pay attention to safety issues in the construction site.”

19.  Paragraph 14 stated, as translated into English:

“In my daily routine inspection in the construction site, if I found workers carrying out routine moving work, I would remind them of putting on labour gloves in order to prevent accident as much as possible. However, the workers could decide by themselves whether to put them on or not.”

20.  First of all, the drafting of the application was ambiguous: Mr. To was talking about 2 different procedures in paragraph 12: a daily morning safety meeting and a safety meeting between the Safety Department and the subcontractors from time to time, and a further procedure in paragraph 14: a daily routine site inspection.  Only the last procedure concerned with site inspection.  Is the plaintiff asking for documents recording all 3 procedures or just on “inspections of work places”?

21.  Secondly, I would also question the relevance: the plaintiff failed to specify a time period for such documents.  There are daily safety meetings and inspections so I cannot see how they can all be relevant to the case.

22.  Mr. Burke suggested that he would ask for documents covering 3 months prior to the accident and 3 months after.  He said he needed these documents to show that the defendants had fallen below the standard in safety.  I think this is the very definition of a “fishing exercise”.

23.  The only relevant purpose in seeking these “records” is to address this issue: were the defendants aware that there was any (alleged) unsafe storage of the glass panes at the relevant time?

24.  During the hearing, Ms. Yuen, the solicitor for 1st and 2nd defendants, submitted that she would not oppose to this application if it was properly redrafted by the court.

25.  However, besides the requirements of clarity and relevance, the court still needs to be satisfied that there is evidence to support the belief that such documents existed and in possession of the defendants etc..  Otherwise, the court should not entertain a time and costs wasting exercise.

26.  In his Third Affidavit, Mr. Burke stated, in paragraph 10, that:

“Being a Housing Authority project, I know…that there will be strict contractual terms for safety – and it appears to be standard practice for their contractors to have used the Housing Authority Safety plan.  I have discovered that this is now called the “Safety Working Cycle”…”

27.  During the hearing, Mr. Burke referred extensively to this “Safe Working Cycle Handbook” (the “Handbook”) including the chapters titled “Hazard Identification Activity”, “Safety Inspection” and “Final Check After Work”.  He also referred to the appendix of the Handbook which contains various forms and checklists.

28.  In short, Mr. Burke argued that this Handbook specified that various meetings or inspections should take place each day etc. and various forms, records and checklists etc. should be completed.  In Mr. Burke’s Third Affidavit, under paragraph 23 (2), after referring to various pages in the Handbook, he stated(my underlining):

“These showed…there must be written records with the minimum being the completion of the Check Lists.”

29.  This was therefore the basis of the evidence for Mr. Burke’s belief that such documents existed and were in the possession of the defendants.

30.  Of course, I have gone through this Handbook in the plaintiff’s last application and under paragraph 54 of the Previous Decision, I already stated:

“I failed to see how these materials support Mr. Burke’s argument that such documents existed…”

31.  I have not explained further then (since Mr. Burke, at the hearing of the last application, did not refer to the Handbook at all) but now, with this being Mr. Burke’s “second bite at the cherry”, I will elaborate.

32.  Mr. Burke maintained that the “Safe Working Cycle” in the Handbook“appears to be standard practice” and that the requirements stated there “would be what is required under Part 1 of Schedule 4 of the FIU (Safety Management) Regulation, Cap. 59 AF” and thus “there must be written records with the minimum being….the Check Lists” (paragraphs 10, 23 (1) and (2) of Mr. Burke’s Third Affidavit).

33.  However, if Mr. Burke had bothered to read the “Preface” of the Handbook, he would have read this (my underlining):

“…The construction industry….is required by the law to establish a safety management system….

…The safe working cycle is one of the tools that management can use to enable the organization to regulate its daily working process, provide a model for management to follow, and implement certain elements of the safety management system…

…The concept of safe working cycle…is a type of management tool that can be used to solve difficulties in different aspect of the management systems…

…the Occupational Safety and Health Council has specially prepared a series of material on the safe working cycle for the construction industry.  The Council hopes that the material will be able to help the organisations to implement the safety management system…”

34.  And further, under “An Introduction to the Safe Working Cycle Handbook”, it is stated (my underlining):

“This handbook aims to introduce the main concepts of the safe working cycle, and explain simply the procedures…Organisations can make suitable adjustments according to their own situations such as individual needs, organization size, activities, type of worker, nature of hazards and the degree of risks involved. The organization managerial staff can use this handbook as a reference and subsequently develop a safe working cycle suitable to their specific working environment.”

35.  Thus, it should be clear to anyone reading the Handbook that the “Safe Working Cycle” is meant to be “a concept”, “a model”, “a reference” and only “one of the tools” for individual organisations to tailor and adjust according to individual needs to establish their own safety management systems.  The Handbook is not meant to provide a “standard practice” or a set of “regulations” to be strictly abided to.

36.  Therefore, the fact that various forms and checklists are mentioned in the Handbook is not evidence that such documents should exist in the current case.  (And even if they exist, there is still the question of whether any of those forms and checklists are relevant to the claim.)

37.  There was nothing in Mr. To’s evidence that the defendants have produced any such forms and checklists.  It might be that the defendants implement the daily site inspection and various safety meetings but did not implement writing Safety Inspection Checklists etc.  There was no suggestion in the Handbook that such “adjustments” would be inappropriate.

38.  In the Previous Decision (under paragraph 97), I have questioned whether Mr. Burke had actually read the materials he exhibited in his Affidavit, including this 66-pages-long Handbook.

39.  The Previous Decision was dated 1 June 2016. Mr. Burke took out the current application almost one year later on 12 May 2017. It would appear that he still has not read the Handbook properly.

40.  As stated above, the only purpose for seeking such “records” was to establish whether the defendants were aware that there was any (alleged) unsafe storage of the glass panes at the relevant time.

41.  Given what Mr. To had stated in his witness statement, I would think that a much simpler and cheaper way forward is to raise interrogatories along the lines of whether, during any of the safety meetings or routine inspections at the relevant time of the accident, any safety concerns were raised or detected regarding storage of glass panes and whether any safety measures were implemented as a result.  This issue would then be adequately addressed.  There was no need to waste time and costs to peruse and produce voluminous materials, and to seek repeated specific discoveries.

42.  Of course, I would question whether this was an important issue in the first place.  As stated in paragraph 7 of the Previous Decision:

“One would imagine that the crux of the claim must centre around whether the glass panes were stored as alleged, whether this would create an unsafe working environment which caused the accident, and what reasonable precautions, if any, was taken by any liable parties under the circumstances.”

43.  Thus, once the plaintiff could establish that there was an unsafe working environment, the question of whether the defendants were aware of this or not might arguably be an academic question: the defendants either failed to detect an unsafe situation or they have detected such but still failed to prevent the current accident. In either scenario, the defendants would likely be found negligent.

44.  With the CJR, Mr. Burke must be aware that there should be a sense of time / costs proportionality in addressing such a “non-core” issue.  This should be something to bear in mind even if he was simply raising interrogatories.  Pursuing a second round of application of specific discovery basing on materials which he (again) failed to read through properly was a travesty of the spirit of the CJR.

Documents to record relevant matters in safety meetings

45.  Thirdly, the plaintiff also sought:

“(3) All documents to record “relevant matters” [to this action] discussed at;

(a) Morning safety meeting with workers

(b) Safety meetings of Contractors and sub-contractors and workers

As referred to in paragraph 12 of the statement of Mr. To, including the matters set out in items (1) and (2) of this schedule.”

46.  I have already produced paragraph 12 of Mr. To’s witness statement in paragraph 18 above.

47.  Suffice to say, my observations in paragraphs 25 to 44 above would apply to this request as well.  In short, there is no evidence that such documents existed: the Handbook does not provide a “standard practice” and Mr. To did not give evidence that such documents existed.  

48.  As pointed out by Ms. Yuen, I have already addressed this particular point in paragraphs 99 and 100 of the Previous Decision:

“I can think of scenarios when certain aspects of this application may be appropriate. For example, if the plaintiff’s case was that certain specific safety procedures concerning storage of certain materials (e.g. glass panels) on construction sites were breached (and that this had caused the accident) and that this was denied by the defendants. And if Mr. Burke had then produced an affirmation (perhaps from the plaintiff) giving evidence that, say, on a particular day, he had attended a safety meeting concerning such specific safety procedures, or that he had seen a risk assessment document listing such specific safety procedures…

…In such scenarios, it would be perfectly proper to seek specific discovery for the safety meeting minutes of that particular meeting, or the risk assessment document concerning that set of safety procedures.”

49.  There is no evidence before me that this is the scenario here. This is again Mr. Burke’s “second bite at the cherry”.

Order

50.  I would accordingly dismiss the plaintiff’s application.

51.  In the Pervious Decision, I have already expressed my concern with how Mr. Burke was handling the plaintiff’s case.  That should have served as a “fair warning”.  However, by taking out this second application on essentially the same matter, it is clear that Mr. Burke did not take heed at all. (Incidentally, Mr. Burke has again exhibited voluminous materials in his affidavit (“UK Pre-Action Protocol” and an entire Chapter from a textbook on construction site safety) which are largely irrelevant.)

52.  A further concern is that Legal Aid Department has notified the court that the aided person’s Legal Aid Certificate does not cover the current application.

53.  I therefore do not know under what capacity Mr. Burke is acting in this application.  I also do not know if the defendants have been made aware of this position before the application.  Further, even if the plaintiff is now personally instructing Mr. Burke for this application, I see no reason why the plaintiff should fund the costs.  I would think that the plaintiff should be able to rely on the professionalism of his lawyer, as a minimal, to properly read all the documents before embarking on a costly application.

54.  Like the first application, I am considering whether it is appropriate to give a wasted costs order.  I am inviting the parties to fix a hearing for 30 minutes on the issue of costs, and it would be an opportunity for Mr. Burke to address me on why a wasted cost order should not be considered, as well as the issue of his capacity of representation in this application.

 (Harold Leong)
 Master of the High Court

Mr. Patrick Burke of Burke & Company, for the plaintiff

Ms. Nora Yuen of William Lee and Associates, for the defendants

104303-EN-2016-06-01

TAI YUK CHEUNG v. HUNG SING CONSTRUCTION ENGINEERING CO AND ANOTHER

HTML content

HCPI 298/2015

IN THE HIGH COURT OF THE

HONG KONG SPECIAL ADMINISTRATIVE REGION

COURT OF FIRST INSTANCE

PERSONAL INJURIES ACTION NO 298 OF 2015

_________________________

BETWEEN

 TAI YUK CHEUNGPlaintiff
 and
 HUNG SING CONSTRUCTION ENGINEERING CO1st Defendant
 YAU LEE – HSIN CHONG JOINT VENTURE2nd Defendant

_________________________

Before: Master Leong in Chambers
Date of Hearing: 8 March 2016
Date of Decision: 1 June 2016

_______________

D E C I S I O N

_______________

1. This is the plaintiff’s application for specific discovery.

Background

2. For what I will come to later in this decision, I will need to go into some details about this claim.

3. This is a personal injury claim.

4. The plaintiff was employed by the 1st defendant, a sub contractor (with the 2nd defendant being the principal contractor) as a labourer on a construction site.

5. The plaintiff was assigned by the 1st defendant to install kitchen units.  The plaintiff claimed that there was some glass panes being stored in the working premises and in the process of installing the base for the kitchen stove, the plaintiff’s left hand came into contact with the glass panes and was cut.

6. The injury was a 3cm laceration with a partial (70%) cut of one of the 2 extensor tendons (extensor indicis, the other, the extensor digitorum communis, was intact) of left index finger.

7. This would appear to be a rather straightforward personal injury claim, what I would call a “bread-and-butter” claim of a relatively minor and simple accident at a construction site.  One would imagine that the crux of the claim must centre around whether the glass panes were stored as alleged, whether this would create an unsafe working environment which caused the accident, and what reasonable precautions, if any, was taken by any liable parties under the circumstances.

8. Against this background, the plaintiff’s solicitors, Messrs Burke & Co, filed a 15-page long Statement of Claim.

9. Much of the pleadings in the Statement of Claim were information which was of little or no relevance to the crux of the claim, for example, under paragraph 1, it was pleaded that, amongst others, that the plaintiff was born in Guangdong, his native language is Hakka, is 1.73 m tall and weighed 135 pounds at the time of the accident.

10. Further, under paragraph 2(4), it was pleaded that:

“The contract between the Hong Kong Housing Society and the 2nd defendant would include provisions regarding safety at the site including matters such as :

(a) To submit a sub contract management plan with quarterly updates

(b) To counter sign daily site diary

(c) Prepare a safety plan covering key elements including

i) Safety policy

ii) Safety organizations

iii) Safety & Health training

iv) Safety rules and regulations

v) Safety committees

vi) Safety & health inspections

vii) Job hazard analysis – with method statements

viii) Personal protective equipment

ix) Accident / incident investigations

x) Emergency preparedness

xi) Safety promotion

xii) Health assurance programme

xiii) Evaluation, selection and control of sub contractors

xiv) Process health programme – including safety rules, regulations safe working procedures and in particular method statements and permit to work systems incorporating the findings of risk assessments conducted for identified high risk processes including manual handling

(d) To employ safety officers, supervisors and representatives including safety inspections and safety audits

(e) To provide training to worker at the site”

11. Under paragraph 2(11), the plaintiff alleged that he was not provided with nor required to wear safety gloves when working at the site.

12. And under paragraph 2(13), it was pleaded that the site (known as Tak Long Estate):

“This included:

(a) 9 blocks of residential buildings

(b) Each residential block was 40 to 41 floors in height

(c) Each residential floor had 23 to 26 flats on it

(d) The size of flat would vary”

13. Under paragraph 2(14), it was pleaded:

“In each flat there were:

(a) A kitchen

(b) Bathroom toilet

(c) Living area; and

(d) Windows”

14. Under paragraphs 2(26) to (32), there were detailed pleadings of the sizes and number of the glass panes, where and how they were placed, and how that there were no protective covers or barriers.

15. At various subparagraphs of paragraph 2, it was pleaded that the defendants did not perform any “risk assessments”, give any “specific guidelines nor written instructions”, I perform any “job hazard analysis” etc.

16. Under paragraph 4 “Particulars of negligence” and “Particulars of breach of statutory duty”, there were also allegations of failure to do “risk assessment”.

17. The defendants did not admit to paragraph 2 of the Statement of Claim save that the defendants “were engaged in construction work at the material times, had duties as to safety as imposed by the law and the plaintiff worked as a labourer at the site at the material times”.

18. The defendants specifically denied paragraph 2(11) of the Statement of Claim and averred that the plaintiff was “provided and supplied with safety gloves were required to wear the same while working at the site and had been trained and instructed to use the same when working”.

19. The defendants also pleaded, amongst others, that the plaintiff could have arranged to move the glass panes elsewhere, and that it was unnecessary to come into contact with the edges of the glass panes in the plaintiff’s work etc.

20. Therefore, it must be clear for the parties what the relevant matters in dispute are in this claim.

The Plaintiff’s application for specific discovery

21. Against this background, the solicitors acting for the plaintiff, Mr Patrick Burke wrote to the Court on 19 August 2015, prior to the Check List Review hearing, enclosing a “table of documents sought from the defendants”.

22. The “table” runs to some 8 pages. I am copying this table below using the plaintiff’s own numbering system: -

“1. The Construction Site

1.1 Contracts

1. Contract between D2 and HK Housing authority

1.2 Statutory notice

1. Notice of

(a) Commencement – with name of every sub contractor

(b) Further information

(c) Change

(d) Completion

of Construction work to Labour Department – form LD 202

2. Notification of establishment of workplace

2. Safety at the Construction Site

2.1 Other accidents

1. Safety / accident book

2. Recording incidents / dangerous occurrences / near misses

2.2 Employees Handbook

2.3 All documents relating to the safety management system operated by the Defendant, including:

1. The company safety policy statement

2. Safety plans

3. Minutes of safety committees

4. All documents relating to safety audits or safety reviews

5. All documents relating to safety training to the employee’s of the Defendant

6. Form 2 & 3 for the period covering 6 months before and after the accident, prepared pursuant to the Factories & Industrial Undertaking (Safety Officers & Safety Supervisors) Regulations, Cap 59 – or similar documents

2.4 All documents relating to the employment of, and qualifications, of safety officers and safety supervisors at the site

2.5 Risk Assessments

2.6 Method statement for work being done by the Plaintiff at the time of the accident

3. The work being done by the Plaintiff

3.1 Permit to work

3.2 Written instructions given to the Plaintiff / his team of workers

4. The Accident

4.1 Statutory report made under FIU Regulations – Section 17, or Employee’s Compensation Ordinance

4.2 Accident investigation report prepared by or on behalf of the Defendants, including reports prepared pursuant to regulation 15(1) of the Factories & Industrial Undertakings (Safety Officers & Safety Supervisors) Regulations, Cap 59

4.3 Photographs of the accident scene

4.4 Statements from witnesses

5. Previous / subsequent accidents

5.1 Same document as in 4 – for previous / subsequent similar accidents

6. The flat / Glass panes

6.1 Plan of the flat

6.2 Dimensions of glass panes

7. Employment

7.1 Contract of employment between the Plaintiff and the Defendant, or other documents etc. to identify the terms and conditions of employment – including different items / categories of wages and allowances

7.2 Personal records file of the Defendant for the Plaintiff including

1. Leave record

2. Training record

3. Performance appraisal

7.3 All documents relating to payments to the Plaintiff in the period of 12 months prior to the accident:

1. Time card record / daily signing record / computer scanner

2. Monthly pay slips

3. Record of wages paid

4. MPF/ ORSO record

5. Return to IRD

7.4 All documents relating to payments to the Plaintiff following the accident for:

1. Sick leave pay

2. Payment for re-imbursement for medical expenses

3. Payment for or re-imbursement for non-medical expenses

4. MPF records

5. Return to Inland Revenue

7.5 Records of wages paid to person (s) (up to 3 employee’s) currently employed by the Defendant in the same or similar position to that occupied by the Plaintiff, for the last 12 months – with documents to show

1. Their name

2. Their job title

7.6 Records of wages paid to person(s) (up to 3 employee’s) currently employed by the Defendant who have suffered similar injury and disability as the Plaintiff – with documents to show

1. Their name

2. Their job title

3.  Their disability / pervious accident”

The plaintiff’s affidavit in support of the application

23. Mr Burke subsequently filed and served an Affirmation in support of this application (First Affidavit of Patrick Michael Burke dated 16 September 2015).  Mr Burke submitted that “in support of the application, I intend to rely on all relevant documents in the draft bundle of (1) pleadings (2) witness statements….  To save costs, these are not exhibited – and there is now shown to me marked “PMB-1” a copy of the up-dated index of the same…”

24. “PMB -1” is a 14-page long “Indexes of draft Trial Bundle”.  As a passing comment, I am concerned that Mr Burke saw it fit to prepare an “Indexes of draft Trial Bundle” and apparently kept it “updated” at this early stage of the proceedings.

25. As usual practice, the court does not give directions for the preparation of Trial Bundle index until the case is ready to set down for trial (and ideally after failed mediation) in order to save costs and time. The spirit of the CJR is such that the court disapproves any unreasonable attempt to load up the costs “upfront”.

26. I would therefore put it on record that should there be future dispute in costs, the Plaintiff would have to justify the need for such work.

27. Mr Burke then produced “PMB-2” which was “Extracts from HK OSH Guide” which ran to 48 pages.  There was no more submission in Mr Burke’s Affidavit as to which part of this “guide” he was referring to as support for his application.

28. Mr Burke further produced “PMB-3” which was a “Table of material facts” which was a list of (claimed) “material facts” pleaded in the Statement of Claim with the “response” to these by the Defendants in the Defence.  There was a column titled “Comment” with abbreviations (without explanations) and brief notes like “NTA”, “OK”, “FBP – which law”, “Discovery”, “Did D investigate accident”, “OK – no positive case”….

29. Mr Burke then listed the “accident background” which was more like a summary of the Statement of Claim.  Then he listed the “discovery background” which was more like a brief summary of the Defence (along with some unnecessary personal observation: “In this case, as so often, the Insurers and their lawyers have not addressed the issues and do simple “Non Admission” defences.”) and an allegation that the Defendant’s List of Documents “does not deal with most the documents sought etc.”.

30. The only submission Mr Burke made on specific discovery in the whole affidavit was on page 5, and his submission only ran to one paragraph (paragraph 10) stating that “proper description”, “existence”, “relevance” and “why it is reasonable for the same to be disclosed” were “set out on the Table” (presumably he meant “PMB-3”).

31. Mr Burke then made some submission on the defendants’ response at the call-over hearing and then there was a repeat of the plaintiff’s position that various matters were pleaded in the Statement of Claim but was not admitted in the Defence.  These matters were again listed out.

The 1st defendant’s affirmation in opposition to the application

32. The 1st defendant filed and served an Affirmation in Opposition (Affirmation of Chu Kau dated and filed on 27 November 2015).

33. Mr Chu made some general comments on the extensiveness and lack of reference (both with regard to the facts of the case and failure to identify to which defendant the request was being made against) in the plaintiff’s request.

34. Mr Chu then confirmed that the 1st defendant did not have items 1- 6, 7.2 and 7.6: of which items 1, 2, 4 and 5, if they exist, should be with the 2nd defendant (there was no dispute that the 1st defendant was the principle contractor and the 2nd defendant was the sub-contractor), and items 3 and 7.2 did not exist.

35. Mr Chu then stated that items 7.1, 7.2(2), 7.3 and 7.4 have already been disclosed as items 1, 6, 7, 10, 12, 14, 15, 17 and 19 of the Defendants’ List of Documents.  This was filed on 29 July 2015, or 3 weeks before the plaintiff’s letter to the court seeking specific discovery.

36. As for 7.5, Mr Chu stated that “the 1st defendant will disclose the record of one employee who is still engaged in such similar job…by way of supplemental list of documents.”

The 2nd defendant’s affirmation in opposition to the application

37. The 2nd defendant also filed and served an affirmation in opposition (Affirmation of Lam Chan Sing dated 25 November 2015 and field on 27 November 2015).

38. Like Mr Chu, Mr Lam made similar general comments on the conduct of the specific discovery application.

39. Mr Lam confirmed that the 2nd defendant does not have items 2.1, 2.2, 2.4, 2.6, 3.1, 3.2, 5, 7.1, 7.2 and 7.6.

40. Mr Lam further argued that the plaintiff failed to establish any prima facie case that the 2nd defendant holds some of the documents (2.2, 2.6, 3.2, 4.4, 7.1, 7.2): eg no case was made as to why a principal contractor should hold personal records file for a casual construction site worker, or why there was “method statement” in existence for the rather simple work done by the plaintiff.

41. Mr Lam also argued that some items were irrelevant (2.1, 2.4, 5, 7.6): “as it is quite clear that accident of the nature….and the responsibilities of the parties…depends on the facts and circumstances of the present case and has nothing to do with other instances and accidents…The principle of proportionality clearly tips…the balance against the making of any order for discovery in this respect.”

42. Mr Lam confirmed that the 2nd defendant had not interviewed any witness after the accident so 4.4 did not exist.

43. As to items 1, 2.3, 2.4, 2.5, Mr Lam agreed that they were possessed by the 2nd defendant but were irrelevant.  There were contract between the Housing Authority and the 2nd defendant and a whole class of documents called “statutory notices”, general safety system, employment and qualification of the safety officers.

44. Mr Lam argued: “that there were safety officers, safety management systems generally and risk assessment and other method statements generally are not proof that the defendants were not at fault.  Likewise, the absence of such….does not decide one way or another whether the defendants were negligent or at fault in relation to the present accident.  It will not be conductive to resolution of any matter or issue involved.  It only adds to costs…unreasonably….the construction site was a large one and there must be hundreds and thousands of such documents but which are totally irrelevant.”

45. Mr Lam then made the same submission as Mr Chu as stated in paragraph 35 above.

46. Mr Lam agreed to disclose items 4.2 and 4.3 (photographs of the accident scene and an accident investigation report) by way of a supplemental list of documents.

Subsequent event

47. The 1st and 2nd defendants filed and served a Supplemental List of Documents on 3 December 2015 disclosing the 3 items that the 1st and 2nd defendants agreed to disclose in the respective affirmations of Mr Chu and Mr Lam as I stated above.

48. Mr Burke then wrote to the Court on 9 December 2015 enclosing a “Schedule of documents believed to be in the possession, custody or power of the defendant” which ran to 22 pages and the letter itself was 5 pages long and a large part of it were in form of submission attempting to rebut points raised in the defendants’ affirmations.  In my view, it is entirely unnecessary and inappropriate to make such submission at this stage.  The plaintiff might still file and serve an affidavit in reply and such submissions should be made, if needed, at the time of the hearing and not in a letter to the Court.

49. Then, on the very next day (10 December 2015), Mr Burke wrote again enclosing another “Schedule of documents believed to be in the possession, custody or power of the defendant” which had now been reduced, in the space of one day, to 7 pages listing the items “outstanding” (which now identified against which defendant the discovery was sought).  Mr Burke maintained his request for 12 items: -

(a) Item 1 against D2 (contract with Developer)

(b) Item 2.1 against D2 (Accident / incident book or reports)

(c) Item 2.3 against D2 (Safety management system)

(d) Item 2.4 against D2 (Safety Officers)

(e) Item 2.5 against D2 (Risk assessments)

(f) Item 4.1 against D2 (Statutory report)

(g) Item 4.4 against D2 (witness statements)

(h) Item 5.1 against D2 (Other accidents)

(i) Item 6.1 against D2 (Plan of the flat)

(j) Item 6.2 against D2 (documents show dimensions of glass)

(k) Item 7.1 against D1 (Contract of employment at the time of accident)

(l) Item 7.5 against D1 and D2 (current wages of 3 comparable workers)

The plaintiff’s 2nd affirmation

50. Mr Burke filed and served a second affirmation on 25 February 2016.

51. Mr Burke disputed the existence of documents sought “on the issue of safety”.  He exhibited, as “PMB – 4”, 114 pages of materials identified as “print outs from Hong Kong Housing Authority Safety Website” and argued “whilst the Defendants deny such documents exist – this is a Housing Authority project and on the Housing Authority own safety website, they give full deals (typo: details?) of such a system.”

52. However, Mr Burke failed to clarify which documents in his list of specific discovery are “documents on the issue of safety” and where amongst the 114 pages of print-outs are the evidence that such documents (relevant to the current case) actually exist.

53. Notwithstanding the unhelpfulness of Mr Burke, I have perused the print-outs.  These are general safety principles and statistics published by Hong Kong Housing Authority in its website and, as far as I can see, the entire content of the “Safe Working Cycle Handbook” published by Occupational Safety and Health Council.  One page, for example, demonstrates stretching exercises to be performed before starting work.

54. I fail to see how these materials support Mr Burke’s argument that “such documents exist” (even if he thought that he was entitled to do so after the defendants’ affirmations).

The hearing

55. During the hearing on 8 March 2016, Mr Burke agreed that he was only seeking specific discovery for the 12 items as listed in paragraph 49 above.

56. In essence, Mr Burke justified his application by the following:

(a) the Judgment of Bokhary, J (as he then was) in Chan Tam Sze v Hip Hing Construction Co Ltd [HCA 1931 of 1988] and 2 Others.

(b) That he has pleaded the matters in the Statement of Claim but the defendant has not admitted to them.

Chan Tam Sze v Hip Hing Construction Co Ltd

57. Mr Burke argued that documents he requested were within the “scope of discovery” as listed under paragraph 14 of that judgment.

58. I am of the view that Bokhary, J in that case was dealing a non-party discovery against the Commissioner for Labour where 2 of the 3 accidents concerned were not investigated.

59. More importantly, this decision concerns with the “scope” of documents that the party may seek “if discovery is correct in principle” (see paragraph 16 of the Judgment).

60. In other words, the seeker would still need to satisfy the principle of specific discovery, that is, Order 24 r 7 and r 8 of the Rules of the High Court.

The principle of specific discovery

61. Order 24 r 7 states: -

(1) Subject to rule 8, the Court may…on the application of any party to a cause or matter, make an order requiring any other party to make an affidavit stating whether any document specified…is, or has at any time been, in his possession, custody or power, and if not…when he parted with it and what has become of it.”

(2)  …

(3) An application…must be supported by an affidavit stating the belief of the deponent that the party from whom discovery is sought…has, or some time had, in his possession, custody or power the document…specified…and that it relates to one or more of the matters in question in the cause or matter.

62. Order 24 r 8 states: -

(1)  On the hearing of an application for an order under rule…7 the Court, if satisfied that discovery is not necessary…may dismiss…the application and shall in any case refuse to make such an order if an so far as it is of the opinion that discovery is not necessary either for disposing fairly of the cause or matter or for saving costs.

63. The principle is clear.

(a)  The party seeking specific discovery should:

(i)   provide sufficient description to identify the specific documents or class of documents sought against which particular party;

(ii)  demonstrate his belief by way of an affidavit that such documents exist and that the other party has or at some time had, in possession, custody or power of such documents, and that the documents are related to the “matters in question in the cause or matter”.

(b)  Even if a) is satisfied, the Court may grant such an order only if it is of the opinion that it is necessary either for disposing fairly of the cause or matter or for saving costs.

64. Further, in view of the CJR (which came well after the case of Chan Tam Sze), the Court must look at time, cost and proportionality in applying the “necessity” test.

The pleadings in the Statement of Claim

65. With such principles in mind, it is wrong to suggest that the Court should grant the order for specific discovery just because the plaintiff pleads a matter which the defendant does not admit to (or denies).

66. The Court must look at how relevant this matter is and whether discovery of documents related to this matter is necessary.  Otherwise, the procedure would be open to abuse by one party making laborious and irrelevant pleadings and wasting time and costs in seeking specific discovery in relation to such matter.

67. As I stated in paragraph 7 above, this is a simple claim and the crux of the claim (or what constitutes “cause or matter in question”), must centre around whether there was an unsafe working environment which caused the cut in the plaintiff’s finger (as alleged), and what reasonable precautions, if any, was taken by the defendants under the circumstances.

68. This would be a finding of fact by the Court.  I fail to see how this will turn on much of the pleadings in the Statement of Claim eg the plaintiff’s weight and height, place of birth, what language the plaintiff speaks, how many blocks of flats and how many floors in each block etc were in the project, what were the plans of the flat, the exact dimensions of the glass panels, whether this was a Housing Authority project, whether there was a “safety plan”, there were “safety officers” (and their qualifications) etc.

69. As such, specific discovery on documents regarding many of such matters pleaded (ie item 1 (contract of the 2nd defendant), item 2.3 (safety management system), item 2.4 (matters regarding safety officers), item 2.5 (risk assessments), item 5.1 (documents on “other accidents”), item 6.1 (plan of the flat), item 6.2 (documents on dimension of glass panels) are neither relevant nor necessary with regard to the principles stated above.

Item 4.4: the “witness statements”

70. As for item 4.4 (witness statements), Mr Burke simply stated “common practice as part of safety investigation” in the table he exhibited in his first affidavit.  No effort was made to inform the court as to why he believed there were witnesses in such an investigation, who they were, and that written statements were taken as “common practice” etc.

71. In short, there was utter failure on part of Mr Burke to demonstrate his belief that such documents existed in the first place.

72. This is more surprising given that the plaintiff already pleaded that “The accident happened when the plaintiff was working alone…” (see paragraph 2(19) of the Statement of Claim) and, of course, there is nowhere in Mr Burke’s affidavits that suggested there was any witness.  So one wonders what the point is of this exercise.

73. When I asked Mr Burke during the hearing to identify the witnesses whose statements he was requesting for, he replied that he did not know.

74. So this was a “fishing exercise” right from the beginning.

75. But this was worst: a “fishing exercise” is when one party wishes to “fish” for something useful for his case.  Given the plaintiff’s case that the accident happened when he was alone, Mr Burke should be aware that this “fishing exercise” would be futile right from the beginning, and would only incur unnecessary time and costs.

Affidavits should be taken as conclusive

76. Given what Mr Burke should have known, it is even more incredible that, despite the affirmations by the defendants denying the existence of any witness statements, Mr Burke still maintained the request at the hearing.

77. Mr Burke also maintained his request for other documents when the affirmations of the defendants already denied the existence or questioned the irrelevancy of such documents.

78. It was well-established law that the statements in the affidavits should be taken as conclusive on the question of whether the party has or has had any documents other than those disclosed, or as to their relevancy (see White Book 2016 24/7/1).

79. As such, it was entirely inappropriate for the plaintiff to maintain his application when the defendants’ affidavits clearly stated that they did not hold such documents, that they do not existed, or that they were irrelevant.

80. Further, it is also trite that the party seeking discovery could not, with a view to obtaining further and better affidavit of documents, adduce evidence to show that the affidavit already filed was insufficient or untrue (see 24/7/1 White Book 2016).

81. Mr Burke was clearly attempting to do so in his 2nd Affidavit and even then, he made little attempt to assist the court and simply burdened the Court with a huge amount of materials, effectively asking the Court to search for what might support his case.  As stated above, the Court found none.

Item 4.1: Statutory Report

82. This is what Mr Burke described as “Statutory report made under FIU Regulations – Section 17, or Employee’s Compensation Ordinance.”

83. I note that this item was not specifically addressed in either of the defendants’ affirmations.

84. However, I note that Mr Lam did deal with the discovery of the Accident Investigation Report (item 4.2) in his affirmation and such a report was disclosed in the Supplemental List of Documents of the 1st and 2nd defendants.

85. During the hearing, I understand from Mr Lee, solicitor for the defendants, that there was no further investigation report and this report would be the same as the “Statutory Report” as requested under item 4.1.

86. Although it might be ideal for this to be dealt with by way of a further affirmation by the 2nd defendant, I would accept Mr Lee’s submission and not to dwell on this which would only cause further waste of time and costs.

The remaining items

87. I am of the view that the remaining items (copy employment contract of the only comparable worker, photograph of the accident site, accident investigation report) have been disclosed and dealt with in the Supplemental List of Documents of the 1st and 2nd defendants.

Concern in the handling of the plaintiff’s case

88. I have serious concerns about the handling of the plaintiff’s case.

89. I have already commented on the practice of preparing an “Indexes of draft Trial Bundle” at such an early stage.

90. The laborious and irrelevant pleadings in the Statement of Claim may be a result of the failure on part of Mr Burke to analyse the claim properly.  It may also be a result of a lack of a sense of time/cost proportionality.

91. Similarly, the handling of the current application may be a result of Mr Burke not understanding of both the principle and application of specific discovery: he failed to specify the documents requested adequately, failed to adequately show that such documents existed in the possession etc of the defendants, failed to specify which defendants the requests were directed against, failed to show the “relevancy” and “necessity” of such requests, and he maintained the application despite the affirmations from the defendants.

92. If this is true, there is cause of much concern given the experience of Mr Burke.

93. On the other hand, one may question, given the experience of Mr Burke, whether this was all along a sinister attempt to “milk” a “bread-and-butter” claim by padding up the pleadings to provide a fruitful ground for irrelevant specific discovery applications in order to generate costs.

94. Of course, there may be other explanations, but I have not thought of any as yet.

95. I have previously criticised Mr Burke’s practice in the use of “schedules” with his own abbreviations (with no or inadequate explanations) in a similar application in another case (my decision dated 6 June 2014 in HCPI 264/2012).  I note that Mr Burke handled the specific discovery application in that case much in the same way as the current one (sharing many of the “failures” as listed in paragraph 91 above) and I have already raised concern in that decision.  It is unfortunate that Mr Burke failed to take notice of that and still maintained his ways.

96. I am also concerned that Mr Burke has simply exhibited huge amount of materials which are largely if not entirely irrelevant. Not once has Mr Burke referred to any specific passage in the material either in his affidavits or during the hearing in support of the existence of any documents relevant to this claim.

97. This raises the question of whether Mr Burke has actually read the materials he exhibited carefully or at all.  In passing, I note that page 24 of “PMB-4” is a blank page.

98. In any case, it does not show that much thought has gone into it and gives the impression of an attempt to generate as much material (and costs) for as little effort as possible.  Much of the Court’s time is wasted dealing with such materials as well as the extensive lists in the various “schedules”.

99. I can think of scenarios when certain aspects of this application may be appropriate.  For example, if the plaintiff’s case was that certain specific safety procedures concerning storage of certain materials (eg glass panels) on construction sites were breached (and that this had caused the accident) and that this was denied by the defendants.  And if Mr Burke had then produced an affirmation (perhaps from the plaintiff) giving evidence that, say, on a particular day, he had attended a safety meeting concerning such specific safety procedures, or that he had seen a risk assessment document listing such specific safety procedures.

100. In such scenarios, it would be perfectly proper to seek specific discovery for the safety meeting minutes of that particular meeting, or the risk assessment document concerning that set of safety procedures.

101. The plaintiff’s case is so far from the above scenario that I wonder how, as an experienced personal injury litigator, Mr Burke might ever believe that his application would achieve anything other than incurring unnecessary costs and time.

102. The CJR aims to prevent precisely these types of “satellite litigation” proceedings and this application is making a complete mockery of it.

103. I would follow the recent judgment in CACV 192 of 2014 to direct that a copy of this decision be provided to the Director of Legal Aid for him to consider, in light of the experience relating to this case, whether there is any need for closer monitoring on how costs are being spent in legal aid cases in order to protect the legal aid fund.

Order

103.  As the plaintiff’s application of specific discovery has already been adequately addressed by the defendants’ respective affirmations and the Supplemental List of Documents of the 1st and 2nd defendants, there is no need for any order under Order 24 r 7 of the Rules of the High Court.

104. The only remaining issue is costs.

105. The application is almost entirely frivolous, out of some 40 poorly specified documents or classes of documents originally requested by the plaintiff, only the 3 abovementioned documents disclosed may be of some possible relevance to the claim. The time and cost incurred was wholly disproportionate.

106. As such, the 1st and 2nd defendants should be awarded a large proportion of the costs of and occasioned by this application.  However, I see no reason why public money from Legal Aid should be used under the circumstances, either to pay for this proportion of the defendants’ costs or to pay the plaintiff’s lawyers via Legal Aid taxation. I am, therefore, considering whether it is appropriate to give a wasted costs order.

107. I am inviting the parties to fix a hearing for 30 minutes before me to address the issue of costs, and this would be an opportunity for Mr Burke to address me on why a wasted costs order should not be considered.

(Harold Leong)
Master of the High Court

Mr Burke, of Burke & Company, for the plaintiff

Mr W Lee, of William Lee & Associates, for the defendants