HK CourtDB
HomeDirectoryMCP
Hong Kong CourtDB
Back to directory
Miscellaneous References Application2016

FOOK LEE HOLDINGS LTD v. THE SECRETARY FOR TRANSPORT AND HOUSING

Related cases with same parties

  • HCA321/2010FOOK LEE HOLDINGS LTD v. JOY FUTURE INTERNATIONAL LTD AND ANOTHER
  • LDMR1/2021YIELD-THE-BEST LTD v. SECRETARY FOR TRANSPORT AND HOUSING
  • LDRW1/2015TREASURE BASE DEVELOPMENT LTD v. THE SECRETARY FOR TRANSPORT AND HOUSING

Files (2)

[2021] HKLdT 67-EN-2021-09-23

FOOK LEE HOLDINGS LTD v. THE SECRETARY FOR TRANSPORT AND HOUSING

HTML content

LDMR 2/2016

[2021] HKLdT 67

IN THE LANDS TRIBUNAL OF THE

HONG KONG SPECIAL ADMINISTRATIVE REGION

MISCELLANEOUS REFERENCE APPLICATION NO 2 OF 2016

___________________

BETWEEN

 FOOK LEE HOLDINGS LIMITEDApplicant
 and
 THE SECRETARY FOR
TRANSPORT AND HOUSING
Respondent

___________________

Before: Mr Lawrence Pang, Member of the Lands Tribunal

Date of Hearing: 1 September 2021

Date of Decision: 23 September 2021

__________________

D E C I S I O N

(Leave to Appeal)

__________________


Introduction and Background

1.  On 21 May 2021, I handed down a judgment (“the Judgment”) which, inter alia, order nil compensation be paid to the applicant by the respondent for the temporary occupation of the Temporary Occupation Area (“the TOA”) beside a hotel (“the Hotel”) during the period from 26 February 2014 to 26 April 2017 (“the Relevant Period”). This order was made on the ground that during the Relevant Period, the car parking spaces on the TOA were relocated next to it to an area (“the Temporary Carpark”) comprising the northwestern edge of the “Pink Stippled Black Cross-Hatched Green Area” and the whole “Pink Hatched Green Area” within the same lot (“the Lot”) which could accommodate 29 car parking spaces (including 9 lorry car parking spaces that were not provided in the TOA) instead of the original 20[1]. Pursuant to Item 13 of Part I of the Schedule to the Roads (Works, Use and Compensation) Ordinance, Cap 370 (“the Ordinance”) under which the TOA was created, no double compensation should be allowed for any person to recover compensation (a) in respect of a loss or expense which he has not suffered or incurred; or (b) which is greater than the loss suffered or expense incurred by him.

2.  This is the application’s application for leave to appeal against the Judgment on the following grounds (which were more particularly elaborated in the Affidavit of Au Hei Yee and draft Notice of Appeal):

(1) The Tribunal erred in deciding that Item 13(a) of Part I of the Schedule to the Ordinance applied because this section does not preclude a claimant from recovering compensation in respect of “a loss” which he has suffered or incurred;

(2) The Tribunal erred in finding that the relocation of the carparking spaces to the northern portion of the Lot is a relevant consideration because as a fact, the applicant suffered a loss of the temporary occupation of the TOA, nor was a similar piece of land for occupation provided to the applicant by the Government during the Relevant Period;

(3) The Tribunal erred in finding that evidence was required that the Temporary Carpark during the Relevant Period had any beneficial use to the applicant prior to the relocation of the carparking spaces from the TOA;

(4) The Tribunal erred in deciding that the Pointe Gourde principle applied because the restriction on user of the TOA was removed (or, more accurately, suspended) during the Relevant Period;

(5) Similarly, the Tribunal erred in misinterpreting and misapplying the Government Lease (“the Government Lease”) which governs the use and development of the Lot (including the Hotel, the TOA and the Temporary Carpark etc) whereby the provisions, more particularly Special Conditions 54 to 57, were not intended to apply to a hypothetical carpark at the TOA but the actual carpark that was built on partly within the “Pink Cross-hatched Green Area” and partly within the “Pink Stippled Black Cross-hatched Green Area” of the Lot and such carpark continued to exist at the Temporary Carpark, though a Non-Pink Area for the hotel purposes, during the Relevant Period with a consent of the Government;

(6) The Tribunal erred in finding that the 2 metres clearance requirement in Special Condition 38(b)(v)(I) of the Government Lease applied and had the adverse impact of limiting the number of carparking spaces that could be provided in the TOA;

(7) The Tribunal erred in making a mistake of fact that the TOA could only accommodate 20 carparking spaces since the original ancillary carpark for the Hotel occupied not just the TOA but also some portion of the Pink Stippled Black Cross-Hatched Green Area of the Lot so that there were 9 loading/unloading spaces and bays for tour buses outside the TOA;

(8) The Tribunal erred in making decisions adverse to the applicant on (a) the need for evidence showing that the land which had become the Temporary Carpark was of beneficial use prior to relocation; (b) the clearance of 2 metres referred to in Special Condition 38(b)(v)(I); and (c) carparking spaces or loading and unloading spaces referred to in Special Conditions 54(b) and 55(a), without first giving the applicant an opportunity to adduce evidence and make full submission thereon.

Ground 1- Loss or No Loss

3.  Under Ground 1, the applicant asserts, in essence, that the Tribunal had committed an “error of law in finding that the applicant had suffered no loss and/or in misinterpreting the relevant legislation” because “a loss” under Item 13(a) of Part I of the Schedule to the Ordinance “can and must mean the loss of temporary occupation of the TOA”. Mr Anthony Ismail (“Mr Ismail”), leading Justin Ismail (collectively hereinafter referred to as “Messrs Ismail” where appropriate), counsel for the applicant, submitted that the consequence of creating a right of temporary occupation in favour of the Government automatically caused a loss of temporary occupation to the applicant, referring to Leverson Ltd v Secretary for Transport, LDMR 32/2000 (unreported, 19 September 2003) at §43:

“We agree with the Applicant that when an easement or permanent right is created over the land of a claimant, it is fair to compensate him for the diminution in value to his interest in the land. That is his loss and he should be compensated for that loss. If the Government were to negotiate with the claimant for a consensual granting of the easement or permanent right, the claimant, as the hypothetical willing seller and the Government, as the hypothetical willing purchaser, would have agreed that the price for the easement or permanent right should, in principle, be equivalent to the diminution in value of the claimant's interest in his land, and not merely diminution in value of the part of his land subject to the creation of the permanent right or easement. Conversely, it would not be fair to compensate the owner of the land on the basis of the curtailed approach as contended for by the Respondent. In other words, the contention advanced by the Applicant is consistent with the purpose behind the compensation provisions in the Ordinance.” (underline added)

4.  Messrs Ismail argued that the Tribunal held in Leverson that the diminution in value to an applicant’s interest in the land was the applicant’s loss notwithstanding that Item 2(a)(i) of the second column of Part II of the Schedule to the Ordinance only specifies the basis on which compensation is to be assessed. It did not say that the diminution in value must be paid as a matter of compensation.

5.  Messrs Ismail then referred to Article 105 of the Basic Law which provides that “the Hong Kong Special Administrative Region shall, in accordance with law, protect the right of legal persons to the acquisition, use, disposal and inheritance of property and their right to compensation for lawful deprivation of their property.”

6.  Ms Bonnie Y.K. Cheng (“Ms Cheng”), counsel for the respondent, submitted that this Ground 1 is a non-starter and a circular argument, when one properly considers and construes the provisions in the Ordinance together in a coherent manner. Ms Cheng referred to the following sections of the Ordinance:

“26. No recovery of money except under this Ordinance

No person shall have any right against the Crown or any other person to recover any money—

(a) in respect of any use authorized under this Ordinance; or

(b) in respect of any works or anything else authorized under this Ordinance except to the extent of the rights to compensation provided for in section 27.

27. Compensation

(1) The compensation referred to in section 26 is the right to recover from the Crown for the matters set out in the first column of Part II of the Schedule a sum assessed on the basis specified opposite thereto in the second column thereof and with regard to the provisions of Part I of the Schedule, subject to—

(a) the claim being served on the Secretary within the appropriate period specified in the fourth column of Part II of the Schedule; and

(b) the other provisions of this Ordinance.

(2) Every person who is described in the third column of Part II of the Schedule shall have the right to recover compensation for the matters set out opposite thereto in the first column to the extent suffered or incurred by him as assessed under this Ordinance.

(3) The rights to compensation mentioned in the Schedule shall exist in addition to any benefit accruing to a claimant as a result of the implementation of any subsisting conditions imposed by the Governor in Council under section 11(2).” (underline added)

7.  In respect of the latter, ie section 11(2) of the Ordinance provides that the Chief Executive in Council may authorize the works and the use, with or without modification and subject to such conditions, as to the amelioration or avoidance of the effects of the works and the use or otherwise.

8.  Then Ms Cheng referred to Item 2(a) of Part II of the Schedule to the Ordinance as follows:

Matters for which
compensation may
be claimed
Basis on which compensation is
to be assessed
Persons who may claim compensation for
their respective losses
Period within which
the claim must be served on the Secretary
2. (a) The creation of an easement or other permanent right or a right of temporary occupation under section 15.(i) In the case of an easement or other permanent right, the amount by which the open market value of the claimant’s interest in the land is diminished.
(ii) In the case of the creation of a right of temporary occupation, the amount of an open market rent for claimant’s interest in the land occupied during the period of the easement.
Any person owning a compensatable interest in the land.Before the expiration of 1 year from the date on which the easement or right is created.



(underline added)

9.  Item 13 of Part I of the Schedule to the Ordinance further provides that:

“Nothing in this Ordinance shall enable any person to recover compensation—

(a) in respect of a loss or expense which he has not suffered or incurred; or

(b) which is greater than the loss suffered or expense incurred by him:

Provided that in assessing compensation under this Ordinance, no account shall be taken of any amount recovered by the claimant under a policy of insurance.” (underline added)

10.  By reference to the above, Ms Cheng submitted that the creation of the TOA is only a “matter for which compensation may be claimed”. If no TOA was created, the applicant could not even begin to lodge a claim pursuant to the Ordinance in the first place. To construe that “a loss” under Item 13 of Part I of the Schedule to the Ordinance as alleged would simply render Item 13 superfluous and otiose.

11.  Indeed, in the Judgment at §85, I opined, on the basis of the analysis of the comparables submitted by the parties, the total loss of rent from 26 February 2014 to 26 April 2017 on the basis of fee-paying car park was $4,935,840. However, this was not the end of the matter. As specified in Item 1 of Part I of the Schedule to the Ordinance. the provisions in this Part (which includes Item 13) shall, where applicable, have effect for the purpose of assessing compensation under Part II of this Schedule. In the present case, given that the car parking spaces were all relocated sideway within the same Lot during the Relevant Period, the applicant suffered no loss of the use of the car parking spaces[2]. Thus, to prevent a person from recovering compensation under Item 13 of Part I of the Schedule to the Ordinance for a loss which he has not suffered, I concluded therefore nil compensation shall be paid.

12.  Ms Cheng submitted, and I agree, that this is consistent with the judgment in Leverson, supra, where the “loss” on the facts of that case was also said to be “the diminution in value to his interest in the land” as under the second column of Part II rather than “the creation of an easement or other permanent right, ie the first column of Part II.

13.  During the hearing on 1 September 2021, Mr Ismail placed particular emphasis on “the right to recover …” under sections 26 and 27(1) of the Ordinance in support of his argument that the consequence of creating a right of temporary occupation in favour of the Government automatically caused a loss of temporary occupation to the applicant. Mr Ismail even suggested that sections 26 and 27(1) of the Ordinance are even in conflict with Item 13 of Part I of the Schedule to the Ordinance.

14.  With respect, while it is trite that causation is relevant to the question of the recoverability of damages (or compensation in the present case), the principle is that the defendant is only liable to pay damages (or compensation) for the loss and damage which his wrongful act has caused. The amount of compensation to which a person is entitled must be affected by whether he would have suffered the loss. By analogy, it simply cannot logically be suggested that the “loss” under Item 13 in the present case would somehow be simply “the creation of … a right of temporary occupation’.

15.  Further, in Land Compensation & Valuation Law in Hong Kong, 4th ed, 2017, §20.48 at p 623, it was expressly said that:

“(t)he assessment of compensation includes the valuation principles set out in Part I of the Schedule … Compensation may be claimed … on the basis specified in the second column of Part II, after having regard to the valuation principles contained in Part I.” (underline added)

16.  It is unhelpful for the applicant to simply emphasise the “right” to compensation under the Ordinance, or to assert that “the statutory scheme of compensation is not concerned with the claimant’s use of its land but his right of occupation and the temporary loss or deprivation of that right” when section 27(2) of the Ordinance only prescribes a right to compensation “to the extent suffered or incurred by him as assessed under [the] Ordinance”. The applicant’s reference to Article 105 of the Basic Law does not advance its argument when there is no loss suffered and there could be no compensation.

17.  For instance, in Supreme Honour Development Limited v The Director of Lands, LDMT 1/2001 (unreported, dated 10 March 2008), the Secretary for Planning, Environment and Lands authorized under Section 10(1)(a) of the Mass Transit Railway (Land Resumption and Related Provisions) Ordinance, Cap. 276 the closure or substantial alteration of Connaught Road Central or part thereof from 17 December 1994 so as to facilitate the airport railway construction works. The claimant in the that case filed an application to the Tribunal for determination of compensation caused by the above said roadwork in the sum of $14,702,728.30 for various floors/unit of Fung House located at Nos. 19 – 20 Connaught Road Central, Central, Hong Kong. In the least, the Tribunal found the claimant in that case had suffered no loss and therefore no compensation in respect of the ground floor retail space[3], 1/F[4], 8/F, 9/F, 16/F, 17/F, 18/F and 20/F.

18.  Then in Wo Kee Trading Company Limited v The Secretary for Transport, LDMR 28/2000 (unreported, dated 13th June 2002), Wo Kee Trading Company Limited who was the tenant of a site resumed by the Government pursuant to section 34 of the Railways Ordinance, Cap 519 was entitled to claim compensation from the Government. The following table shows the result of the claim as awarded by the Tribunal:

Partial loss of goodwillNil
Loss due to termination of contracts with suppliers, and supplier's extra storage charges and interestsNil
Loss of fixtures and facilities and cost of reinstatement$60,273
Loss on forced sale of stockNil
Severance payments to employeesNil

19.  Similar occurrence or result was found in 梁續有(以天祥參茸藥行的名營業) 對 地政總署署長, LDLR 4/2006 (unreported, dated 22 February 2008) where no compensation was awarded by the Tribunal in respect of the then claimant for loss of goodwill, forced sale of stock and rental of storeroom.

20.  In Yip Kui trading as Tai Wo Trading Company v The Secretary for Transport, LDMR 52/2000 (unreported, dated 18 September 2002), the Tribunal made the following award of compensation under the Railways Ordinance, Cap 519:

Profit RentNil
Temporary Loss of ProfitNil
Loss of GoodwillNil
Agency Fee, Stamp Duty & Removal Cost$87,557
Severance PaymentNil
Loss of EquipmentNil
Loss of Fixtures and Fittings$23,500
Loss of StockNil

21.  When the case reached the Court of Appeal, CACV 379/2002 (unreported, dated 13 June 2003), Hon Rogers VP (as he then was) stated at §21 that:

“I have already emphasised the point that compensation can only be awarded in respect of loss or damage which has been suffered or expenses which have been incurred.”

22.  All in all, there is no ambiguity or confliction between sections 26 and 27(1) and Item 13 of Part I of the Schedule to the Ordinance. The Ordinance only prescribes a right to compensation “to the extent suffered or incurred by him as assessed under [the] Ordinance”. Section 26 further prescribes that “no person shall have any right against the Government or any other person to recover any money … except to the extent of the rights to compensation provided for in section 27”.

23.  In the present case, I held that the applicant did not suffer “a loss” because the use of the ancillary carparking spaces for the Hotel for which the TOA was restricted under the Government Lease was “relocated sideways within the Lot”. Mr Ismail argued that although the carpark was relocated and used, the TOA itself was not. The TOA was occupied by the Government (instead of the applicant) as a matter of fact.

24.  Firstly, there are numerous examples where land was compulsorily purchased but nil compensation was awarded:

- Cohen v Knowsley Metropolitan Borough Council [2004] EWLands ACQ_123_2001 (27 August 2004) where a vacant, derelict and seriously vandalised block of flats which was of unattractive appearance was acquired;

- Borough of Telford & Wrekin, Re Notice of Reference [2009] UKUT 160 (LC) (21 August 2009) where a steeply sloping area of untended former scrubland situated between a public highway and the south bank of a river was acquired;

- Obsidian FG Ltd & Others v Secretary of State for Transport [2010] UKUT 299 (LC) (20 August 2010) where tubes of subsoil were acquired for Channel Tunnel Rail Link.

25.  Indeed, in Director of Buildings and Lands v Shun Fung Ironworks Limited [1995] 2 WLR 404, [1995] 2 AC 111, the Privy Council laid down three conditions to qualify for compensation:

(a) Being causally connected,

(b) Not too remote;

(c) Not a loss which a reasonable person would have avoided.

26.  In the present case, obviously “the loss” of the use of the ancillary carparking spaces for the Hotel for which the TOA was restricted under the Government Lease was avoided by the relocation. A letter dated 15 January 2014 from the Highways Department (which was shown at Trial Bundle B/492 of the trial) is reproduced below:

“ Proposed Temporary Car Park for Harbour Grand Hong Kong

I refer to the meeting among representatives of your company, Harbour Grand Hong Kong, AECOM, Chun Wo-CRGL-MBEC Joint Venture and this office on 3 January 2014.

As requested, I attach a drawing no CWIECL/027-009[5] showing the proposed layout and entrance of the temporary car park for Harbour Grand Hong Kong for your reference. Please be advised that DLO/HKE[6] and TD[7] have expressed no adverse comments on the proposed details.

Yours faithfully,”

27.  It is manifested that the applicant made a request to the Government to permit the use of the Temporary Carpark so as to avoid the “loss”. As stated at §12 of the Judgment, the Government had already undertaken the reinstatement works arising out of or in connection with the creation of the TOA. While this Temporary Carpark was restricted under the Government Lease for non-industrial (excluding private residential, office, hotel, petrol filling station, and godown) purposes in relation to cultural, leisure and tourist-related activities[8], it appears from the “Site Plan” approved by the Building Authority on 19 September 2008 (which was Appendix IV to the applicant’s expert report)[9] and the photographs taken on 12 February 2014 and 19 February 2014[10] that there being of no beneficial use. Indeed, this particular piece of land was admitted by the applicant “to be resumed by Government after reversion of the TOA” to the applicant[11].

28.  More particularly, as stated clearly on the “Site Plan” approved by the Building Authority on 19 September 2008, this piece of land on which the Temporary Carpark was situated was designated for “future cultural, leisure and tourist-related activities complex (Max. 16.8mPD) as in approved Master Layout Plan under Town Planning Ordinance (for indication purpose only to be constructed in the future after Government confirmation on the [Island Eastern Corridor] Extension” and “future waterfront promenade as in approved Master Layout Plan under Town Planning Ordinance (for indication purpose only to be constructed in the future after Government confirmation on the [Island Eastern Corridor] Extension” respectively. (underline added)

29.  In respect of the latter, this has been reserved by Special Condition No (47)(a) of the Government Lease for the construction of a promenade of a minimum uniform width of 10 metres:

“(47)(a) The lessees shall within 36 calendar months (or such other extended periods as may be approved by the Director) after 120 calendar months from the date of [14 June 2005] or immediately after the date of a letter from the Director indicating that the part or parts of the Future Extension of the Island Eastern Corridor to be erected on the Second Reserved Areas[12] as stipulated in Condition No (38)(c) has been completed, whichever is the earlier at their own expenses and in all respects to the satisfaction of the Director, in such manner, with such materials … and to such design, standards, and specifications as the Director shall approve, form, construct, provide, landscape, develop and complete a promenade of a minimum uniform width of 10 metres along the entire length of the seawall between the points A and B … " (which comprised the area of the Temporary Carpark)

30.  As stated at §104 of the Judgment, “there had been no evidence before me that prior to the creation of a right of temporary occupation and then the relocation of the car parking spaces to the Temporary Carpark, that land which had become the Temporary Carpark during the Relevant Period had any beneficial use to the applicant”.

31.  For the above reasons, Ground 1 must fail.

Grounds 2 and 3 - Relocation

32.  Under Grounds 2 and 3, the applicant asserts that the Tribunal erred in law in finding that “the relocation of the carparking spaces to the northern portion of the Lot is a relevant consideration”, and that ‘evidence was required that the land within the Lot which had become the ancillary carpark of the Hotel … during the Relevant Period … had any beneficial use to the Applicant prior to the relocation”.

33.  Ms Cheng submitted, and I agree, that as Grounds 2 and 3 are premised on the applicant’s assertion that the “loss” under Item 13 of Part I of the Schedule to the Ordinance means the “loss of temporary occupation of the TOA” and “are to be considered together [with Ground 1], they must fall together with Ground 1.

34.  To the extent that the applicant complained that “(n)either party adduced any evidence of the beneficial use of that piece of land prior to the relocation” and “(n)or did the Tribunal inform the parties that it was or may be relevant and invite the parties to adduce such evidence or make submissions”, I had invited the parties after hearing the evidence of the experts on valuation but well before the closing submissions of the parties to consider the application of Item 13 of Part I of the Schedule to the Ordinance in the present case because of the relocation. As Ms Cheng rightly pointed out, it was the duty or burden of the applicant to adduce evidence, if any, to justify its claim. In Lancaster City Council v Thomas Newall Limited [2013] JPL 1531, [2013] EWCA Civ 802 at §31, the English Court of Appeal even held that “the tribunal's holding that [the claimant] did in fact suffer loss was an error of law, because there was no evidence justifying it”.

35.  More recently, in Sam Woo Marine Works Ltd v The Incorporated Owners of Po Hang Building, LDBM 252/2014 & LDBM 255/2018 (unreported, dated 27 May 2021), the Tribunal made the following observations at §§61 and 63-64 which should provide a complete answer to the applicant’s complaint:

“61. Sam Woo contends that it is wrong for me to proceed to analyze the figures extracted from the audited accounts, which are incomplete and unreliable, without inviting the parties to make submissions thereof, and that I erred in forming the view that Sam Woo was the one that caused or contributed to the perceived unfairness which view was without evidential basis.

…

63. Should Sam Woo consider the figures in the existing evidence incomplete and unreliable, it is always up to them to make submissions accordingly and to adduce whichever evidence they consider complete and reliable for the court’s consideration.

64. In my view, it is within my judicial function to analyze the evidence adduced by the parties in order to assess whether certain allegation is substantiated by evidence or not. Ms Ng’s suggestion that a judge is obliged to have in readiness at trial all intended analyses of evidence and judicial reasoning and to have them rehearsed or revealed to the parties in advance at trial for their comments or else such analyses or reasoning could not be included in his judgment is unorthodox and unheard of."

36.  Indeed, a claimant seeking compensation must be grounded in the evidence before the court. The court must, when quantifying loss, be astute to identify those points where the evidence falls short, and where the court becomes reliant upon estimates or assumption. Such estimates or assumptions will need to take account of the fact that the probabilities in the counter-factual world may not mean that these estimates or assumptions will inevitably hold good.[13]

37.  And to the contrary of Mr Ismail’s argument, the respondent did provide (or consent) the Temporary Carpark for the applicant’s relocation during the Relevant Period.

Grounds 4 and 5 – the Pointe Gourde Principle

38.  Under Grounds 4 and 5, the applicant alleged that the Tribunal erred in “deciding that the Pointe Gourde principle applied so that the user restriction was not removed” and “misinterpreting and misapplying the Government Lease if it should be taken into account in assessing the open the market rent”.

39.  Firstly, Mr Ismail drew my attention to that in the present case, it was the “open market rent” pursuant to Item 2(a) of Part II of the Schedule to the Ordinance instead of open market value. However, this distinction is neither here or there. I had set out the definition of “market rent” in HKIS Valuation Standards 2017 at §17 of the Judgment as follows:

“The estimated amount for which an interest in real property should be leased on the valuation date between a willing lessor and willing lessee on appropriate lease terms in an arm’s length transaction, after proper marketing and where the parties had each acted knowledgeably, prudently and without compulsion.”

40.  By analogy, this definition has little differences from the definition of “market value” in HKIS Valuation Standards 2017[14]:

“the estimated amount for which an asset or liability should exchange on the valuation date between a willing buyer and a willing seller in an arm’s length transaction, after proper marketing and where the parties had each acted knowledgeably, prudently and without compulsion.”

41.  Mr Ismail further referred to Tang Moon Kau v Secretary for Environment, Transport and Works [2008] 1 HKLRD 10 at §§11-15 where the Tribunal held that the common law principle laid down in Pointe Gourde and Melwood as enacted in section 12(aa) of the Lands Resumption Ordinance concerned land resumption cases and was not applicable to temporary occupation cases. With respect, Mr Ismail had taken the ruling of the Tribunal out of the context.

42.  In this case, Tang Moon Kau, ie the claimant, claimed for the open market rent for the portion of his agricultural land (“the Land”) that was occupied by the Government pursuant to the Railway Ordinance which has a mirror provision for compensation like the Ordinance. The claimant argued that his land which was used as a fishpond should be put to its “best possible use”, i.e. open storage under the Melhado principle.

43.  There were two main issues in that case, namely whether in assessing the open market rent of the Land, the Tribunal was permitted by law to consider “open storage” as the use of the Land, and if so, whether the Land had in fact the necessary physical attributes, such as physical access, making it suitable for such use[15]. Whereas the land was zoned “Unspecified” in the relevant Development Permission Area Plan, then “Undetermined” or “OU” (Other specified uses) in the subsequent Outline Zoning Plans, the claimant argued that the Land had been “blighted” by the respective zoning and therefore invoked the Pointe Gourde principle so that this blighting effect should be ignored. The respondent, on the other hand, argued that the Land should be valued on the basis of “fishpond” and there was no common law principle in temporary occupation cases that compensation would be payable for “blight” caused by town planning. The Tribunal then was led to the point that section 12(aa) was to an extent enactment of the Pointe Gourde principle and in that regard, section 12(aa) was not applicable for temporary occupation cases and so was the Pointe Gourde principle.[16]

44.  In this Tang Moon Kau case, the Tribunal also referred to the common law provision in Chapter One of the report of a Special Committee on Compensation and Betterment (“the Report”) as follows:

“There is no common law right to compensation or obligation to pay betterment. Where a statute authorizes the compulsory acquisition of private land, it may provide for payment of compensation. In modern times legislation has usually included an obligation to pay compensation to the private owner. Where statutory law on the right to compensation is unclear, the common law provides certain principles to assist interpretation. First, where an Act provides for taking of private land, the common law presumes that compensation is payable, unless there is a clear contrary intention. In these cases title to private land is compulsorily conveyed from the owner to the State. Secondly, where statutory law merely regulates the use of private land, the opposing common law principle is that compensation is not payable, unless there is clear statutory provision. Regulatory powers may restrict or prohibit development but do not deprive the private owner of his title to the land. These contrasting approaches are summed up in the phrase that if you take you must compensate; if you regulate you need not.” (emphasis added)

45.  The Tribunal therefore agreed with the respondent that the adverse zoning was an enactment to impose planning control rather than to “blight” the Land. Based on the common law as summarized in the Report, no compensation should be payable in respect of the alleged “blight” caused by such town planning.[17]

46.  It is particularly important to note that the Tribunal, in the following paragraph of Tang Moon Kau, ie §20 of the judgment, stated that:

“Thus, even if the Pointe Gourde principle applies, the 1991 DPA should not be ignored. The 1994 OZP may have to be ignored because the change brought by it may be due to the intended construction of the West Rail.”

47.  Returning to the present case, the Government Lease is to regulate the use of, inter alia, the TOA. It is unreasonable to expect that when the Government created a temporary occupation of the TOA, the restriction or regulation in the Government Lease should be ignored or as suggested by the applicant disappeared. The physical attribute of the TOA under the Government Lease, immediately prior to the TOA, was an ancillary carpark for the Hotel comprising 20 carparking spaces.

48.  In the latter regard, it is clear from Special Conditions 54 and 57 together that the lessee is not entitled to create as many carparking spaces on the Lot as it desires. The number of such spaces is subject to the specific stipulation in Special Condition 57 as pointed out in the Judgment at §78, such that the number of carparking spaces specified in Special Condition 54(a) cannot be increased by more than 5% or 50 in number (whichever is the less) of the number calculated in accordance with Special Condition 54(a).

49.  In Transport for London (London Underground Ltd v Spirerose Ltd [2009] UKHL 44, [2009] 1WLR 1797, [2009] RVR 225, [2009] 4 All ER 810, Lord Neuberger made the following remarks on the application of the Pointe Gourde principle:

55. “The only way the Pointe Gourde principle could be relied on, as a matter of logic, appears to me to be on the basis that, if the scheme in question had not been in existence, then at some time before the valuation date, the respondent land owner would have applied for, and, on the balance of probabilities, obtained permission for mixed development. … the Pointe Gourde principle … is concerned with the effect of the scheme on the value of the owner’s interest, not with the characterisation of that interest - see the remarks of Lord Cross of Chelsea in Rugby Joint Water Board v Shaw-Fox [1973] AC 202, 253, approving a dictum of Russell LJ in Minister of Transport v Pettitt (1968) 67 LGR 449, 462. ...

56. Quite apart from this, I do not consider that it is right to invoke the Pointe Gourde principle, or any other principle developed by the courts, for the purpose of adding a wholly new assumption to the statutory assumptions which have been laid down by the legislature - see per Lord Pearson in Shaw-Fox [1973] AC 202, 214-5. All the more so if that assumption is effectively inconsistent with one or more of the express statutory assumptions. I do not thereby intend to suggest the Pointe Gourde principle has no part to play in this field, but its role is relatively limited. I agree with Lord Collins, when he says in para 128 that it is “a principle of statutory interpretation, mainly designed and used to explain and amplify the expression ‘value'". As Lord Walker implies in para 36, the principle is a factor to be borne in mind when construing the compensation legislation with a view to achieving, so far as possible, a result consistent with its aim of fair compensation. That seems to me consistent with principle and with most of the authorities, including all the decisions of this House and of the Privy Council, to which your Lordships were taken.” (underline added)

50.  Recently, Golf Café Bars Limited v West Yorkshire Combined Authority & Another [2021] UKUT 0016 (LC), which was also referred to by me at §60 of the Judgment, was a claim for compensation for the temporary acquisition of parts of land within a service yard next to a golf café bar on the ground floor of a building for the construction of a railway station. For some years, the claimant let carparking spaces in the service yard to residents of the building which was however in breach of its leasehold user covenant. The English Upper Tribunal (Lands Chamber) had the following remark at §25 of its judgment:

“The basis of compensation for temporary possession … is for any loss or damage. It is not clear to me what loss or damage the claimant suffered. …”

51.  And unlike this Golf Café Bars case, the carparking spaces of the TOA was relocated in compliance of the spirit of section 11(2)(b) of the Ordinance so that “the effects of the works and the use or otherwise” was ameliorated or avoided.

52.  I agree with Ms Cheng’s submission that insofar as the applicant continues to maintain, in essence, that Special Conditions 54 to 59 only lay down the minimum requirements which, once met, the Lot owner is entitled to use the Lot for extra carparking lots, free from any of the restrictions prescribed, such contention is obviously flawed. Obviously these provisions have the clear and objective intention that any carparking spaces on the Lot should serve the Hotel. If they can be just ignored or disregarded when the Government allowed to have the carparking spaces relocated and the claimant can then do whatever as it likes on the TOA, for the purpose of compensation, it is a result inconsistent with fair compensation.

53.  In the premises, Grounds 4 and 5 have no merit and must also fail.

Grounds 6 and 7- Protection of Columns of Island Eastern Corrider

54.  Under Ground 6, the applicant complains that the Tribunal “erred in law in finding that the 2 metres clearance requirement in SC(38)(b)(v)(I) applied and had the adverse impact of limiting the number of carparking spaces that could be provided in the TOA because the 2 metres clearance requirement was to be made available for inspection and maintenance works at all times “Except with the prior written approval of the Director”, and there was no evidence that the Director had not or would not have given such kind of prior written approval”.

55.  I agree again with Ms Cheng’s submission that this complaint is ill-found. The short point is that there was no evidence before the Tribunal that the Director had or would have given any written approval to the applicant. Citing again the remark by Lord Neuberger in the Spirerose case in §49 above, “if the scheme in question had not been in existence, then at some time before the valuation date, the respondent land owner would have applied for, and, on the balance of probabilities, obtained (such approval)”? It is groundless for the applicant to suggest that the Tribunal should have assumed that the Director had or would have done so, notwithstanding the absence of evidence. There is simply “no evidence justifying it”. See the citation of Lancaster City Council v Thomas Newall Limited [2013] in §34 above.

56.  Under Ground 7, the applicant alleges that the Tribunal erred in law “in deciding that SC(23) and the 2 metres clearance requirement in SC(38)(b)(v)(I) had the adverse impact on limiting the number of carparking spaces that could be provided in the TOA because it was based on the mistaken fact that there was a difference between the number of carparking spaces that could be accommodated by the Temporary Carpark and that by the original ancillary carpark of the Applicant’s hotel” and “misunderstanding or mistaking the evidence given by Mr Ng Yiu Wah, the Applicant’s expert”.

57.  In the latter regard, Mr Ismail referred to the cross-examination of Mr Ng by Ms Cheng on 2 February 2021 (as contained at pp69-70 of the transcript) as follows:

Q.But your high-efficiency car park again goes back to your assumption that the car-parking space will be – can deviate from the lease condition.
A.Yes, you are correct.
Q.Okay. Now, can – you also took the view, Mr Ng, that no adjustments need to be made for the presence of the Island Eastern Corridor supporting columns.
A.Right.
Q.Remember, you said that in your report? And I think, in your report, you said that, because they are very small in size, about 4 square metres each, and you said they occupy about only one per cent of the affected portion of the lot, so you say that the pillars will have minimal, if no, impact on the design of the proposed vehicle car park here.
A.Yes.
Q.That’s your evidence? I’m just wondering, Mr Ng, has the four square metres you ascribe to the size of the supporting columns, have they taken into account the barriers – the protective barriers around the supporting columns or it’s just the supporting columns itself?
A.I don’t know what barriers that you mention because it’s just, well, during the day of valuation, it’s just the bare pillar.
Q.Sorry?
A.So what – it is just the bare pillar existing on the site during the time of valuation so I don’t know what barriers that you are referring to.
Q.Now, the reason I’m asking this is because, in the lease, if we go back to A1, 147, …
A.“147”?
Q.147. If we look at the Roman number v – or – yes, Roman number v here, and what we see here is that, a requirement which says, “the lessee shall ensure that adequate measures shall be taken at their own expense and in all respects to the satisfaction of the Director to protect that part of the Island Eastern Corridor passing over the area or any amendment or substitutions thereof from time to time in relation to the use of untensioned, corrugated beam barriers for the protection of columns shall be followed except with the prior written” – “with the prior written approval of the Director.” So I see that there is a requirement for the owner to maintain a barrier protection for the protection of the columns and I also see from the picture you provided at – in the same bundle, page 26, which I assume would be taken around the time you valued the site,…
A.Sorry, which page?
Q.Page 26.
A.“26”.
Q.26. That there appears to be some planters surrounding the column. So, in view of the requirement for there to be a protective barrier, as we’ve seen from the lease, and the presence of these planters in the photos that you’ve taken, would you agree with me that, when we look at the size of the column, we would have to take into account the presence of some barrier in whatever form?
A.Yes. First of all, the picture shows that those are actually – those features surrounding the pillars are actually planters so I would think those are the planters provided by the hotel itself. So, if you are talking about the protection to be given under the special condition, then it will depend on – well, because we have no sight, during our inspection, of any of such kind of the requirement that’s stated in the condition. So we have no idea whether it would cause much impact on the circulation.
Q.But you would agree with me that, for the owner to comply with the lease, obviously, he has to make some space for the barrier?
A.But, even if this is so, I would think the size would be very minimal. The column of the size is just 4 metres squared so how big would it be for the barrier? So I would think that’s again, very small area.
Q.But, just to make sure that we’re on the same page. When you design the hypothetical layout, you took no account of the protective barriers – the size of the protective barrier”
A.Yes, I would say so because I would think that the area occupied by that barrier, if there is so, would not be great.

58.  With respect to Mr Ismail, from the last two questions and answers above, it is clear that Mr Ng admitted that, in designing the hypothetical layout[18], he took no account of the protective barriers as required under Special Condition (38)(b)(v) of the Government Lease. Mr Ng simply thought the planters around the columns were provided by the Hotel instead of complying with the Special Condition (38)(b)(v) of the Government Lease. He even thought that the space for the protective barriers would be very small or minimal without giving any hint on the allowance for the 2 metres clearance from soffit and around columns. I therefore remarked in the Judgment that “Mr Ng’s defence is unbelievable by looking at the congested layout proposed by him”. As stated at §31 of the Judgment, the Tribunal is not bound to accept the submission of any party or Mr Ng and may rely upon its own experience in determining the dispute on valuation.

59.  During the hearing on 1 September 2021, Mr Ismail pointed out that the Temporary Carpark had, prior to the relocation of the carparking spaces in the TOA, provided for 9 loading/unloading spaces and bays for tour buses. But this does not disturb the fact that the TOA could only accommodate 20 carparking spaces prior to the relocation. There has been no mistake on fact.

60.  According to the layout as shown on the drawing no CWBIECL/027-009, this Temporary Carpark could accommodate 29 car parking spaces (including 9 lorry car parking spaces that were not provided in the TOA) instead of the original 20[19]. One may only say that the layout of these 9 loading/unloading spaces and bays for tour buses had been re-arranged.

61.  Thus, Grounds 6 and 7 also fail notwithstanding that Grounds 4 and 5 have no merit and failed.

Ground 8 – Natural Justice

62.  Under Ground 8, the applicant alleges that the Tribunal was in “breach of the rules of natural justice” and “erred in law in making decision adverse to the Applicant on (1) the need for evidence showing that the land which had become the Temporary Carpark was of beneficial use prior to relocation; (2) the clearance of 2 metres referred to in SC(38)(b)(v)(I); and (3) carparking spaces or loading and unloading spaces referred to in SC(54)(b) and 55(a), without first giving the Applicant an opportunity to adduce evidence and make full submission thereon”.

63.  As stated in §34 above, I had invited the parties after hearing the evidence of the experts on valuation but well before the closing submissions of the parties to consider the application of Item 13 of Part I of the Schedule to the Ordinance in the present case because of the relocation. It is for a claimant before the Tribunal to prove the loss claimed. It is manifest that when Mr Ng was asked if “no adjustments need to be made for the presence of the Island Eastern Corridor supporting columns”, Mr Ng’s answer was simply “Right”. See the transcript reproduced at §57 above. And similarly, when Mr Ng was asked if his high-efficiency hypothetical car park layout could deviate from the lease conditions, his answer was “Yes, you are correct”. What else evidence that the applicant is going to adduce?

64.  At this juncture, I would refer to the following observations by Lord Browne-Wilkinson of the House of Lords in Target Holdings Ltd v Redferns [1996] 1 AC 421 at p. 432E to H:

“At common law there are two principles fundamental to the award of damages. First, that the defendant's wrongful act must cause the damage complained of[20]. Second, that the plaintiff is to be put 'in the same position as he would have been in if he had not sustained the wrong for which he is now getting compensation or reparation:' Livingstone v Rawyards Coal Co (1880) 5 App Cas 25, 39 per Lord Blackburn. ... those two principles are applicable as much in equity as at common law. Under both systems liability is fault-based: the defendant is only liable for the consequences of the legal wrong he has done to the plaintiff and to make good the damage caused by such wrong. He is not responsible for damage not caused by his wrong or to pay by way of compensation more than the loss suffered from such wrong. The detailed rules of equity as to causation and the quantification of loss differ, at least ostensibly, from those applicable at common law. But the principles underlying both systems are the same." (underline added)

65.  The applicant was deprived of its occupation of the TOA in the public interest. It was entitled to compensation for the open market rent during the Relevant Period in the "no scheme" world but without double compensation. After a lengthy hearing, the Tribunal determined, on the basis of evidence of the valuation experts on both side. What the applicant now is, in reality, seeking in its application to admit new evidence, was a "second bite at the cherry": an opportunity to put forward new evidence.

66.  But insofar as the applicant implicitly accepts that this is not an appropriate ground of appeal, such concession must be correct.

Applicable Legal Principles for Appeal

67.  Under Section 11(1)(a) of the Lands Tribunal Ordinance (“LTO”), a decision of the Tribunal in determining the amount of compensation payable by the Government (acting on whose behalf, the Secretary for Transport and Housing) shall be the final determination thereof. However, under section 11(2) of the LTO, any party to the proceedings before the Tribunal may appeal to the Court of Appeal against a judgment, order or decision of the Tribunal on the ground that such judgment, order or decision is erroneous in point of law, subject to section 11AA.

68.  Section 11AA(1) of the LTO requires leave to be granted by the Tribunal or the Court of Appeal before an appeal under section 11(2) can be made.

69.  Section 11AA(6) provides also that leave to appeal shall not be granted unless the Tribunal is satisfied that:

(a) the appeal has a reasonable prospect of success; or

(b) there is some other reason in the interests of justice why the appeal should be heard.

70.  Such criterion of “reasonable prospect of success” was described in SMSE v KL [2009] 4 HKLRD 125 at para 17 by Le Pichon JA (as she then was) as involving the notion that the prospect of succeeding must be “reasonable” and therefore more than “fanciful” without having to be “probable”.

71.  At §85 of the Judgment, the Tribunal determined the open market rent of the TOA from 26 February 2014 to 26 April 2017 on the basis on fee-paying car park at $4,935,840. I concluded at §97 that the applicant as the hotel operator would bid for the TOA at least equal to the open market rent payable for a public fee-paying carpark. The applicant had no challenge on that.

72.  However, this was not the end of the matter. At the request of the applicant, the Government accommodated the provision of the carparking spaces next to it though within the same Lot where prior to the creation of the TOA the applicant derived no beneficial use. During the hearing on 1 September 2021, Mr Ismail pointed out that this piece of land had, prior to the relocation of the carparking spaces in the TOA, provided for 9 loading/unloading spaces and bays for tour buses. But this does not disturb the fact that the TOA could only accommodate 20 carparking spaces prior to the relocation. According to the layout as shown on the drawing no CWBIECL/027-009, this Temporary Carpark could accommodate 29 car parking spaces (including 9 lorry car parking spaces that were not provided in the TOA) instead of the original 20[21]. One may only say that the layout of these 9 loading/unloading spaces and bays for tour buses had been re-arranged.

73.  Apart from this, the applicant could not provide any evidence of beneficial use of that piece of land which had become the Temporary Carpark despite the Tribunal had invited the parties after hearing the evidence of the experts on valuation but well before the closing submissions of the parties to consider the application of Item 13 of Part I of the Schedule to the Ordinance in the present case because of the relocation.

74.  Insofar as the Appellant's failure to advance the “new evidence” at that stage due to some error or omission on the part of its professional advisors, the Tribunal must, when quantifying loss, be astute to identify those points where the evidence falls short. In Thomas Newall Limited supra at §31, the English Court of Appeal had the following ruling:

“TNL's problem is that there was, however, no evidence before the tribunal on which it could find that TNL had suffered the claimed, or any, loss. That was because, for the reasons explained, there was no evidence entitling the tribunal to link the time devoted by the Loxam directors on acquisition matters to consequential loss suffered by TNL ... In this case, however, TNL adduced no evidence of any such nature, and so there was no basis upon which the tribunal could find that it had suffered any 'management time' loss. … that head of claim was exclusively dependent upon factual evidence that only TNL could adduce. In the event, TNL adduced no relevant evidence. Its claim under this head should therefore have been rejected. The tribunal's holding that it did in fact suffer loss was an error of law, because there was no evidence justifying it.”

75.  On the contrary in the present case, as stated in §27 above, there was evidence from the “Site Plan” approved by the Building Authority on 19 September 2008 (which was Appendix IV to the applicant’s expert report)[22] and the photographs taken on 12 February 2014 and 19 February 2014[23] that there being of no beneficial use. Indeed, this particular piece of land was admitted by the applicant “to be resumed by Government after reversion of the TOA” to the applicant.

76.  In the above regard, I hold that the intended appeal has no reasonable prospect of success.

77.  As submitted by Ms Cheng, the applicant asserted for the first time in this intended appeal that it could rely on the limb of “other reason in the interests of justice” in support, because “the appeal would present the Court of Appeal with a question of general principle, decided for the first time; or a question of importance which upon further argument and a decision would be to the public advantage; and/or provide much needed clarification on an area of the law or to entertain an argument that the law ought to be changed”.

78.  Mr Ismail relied on the point that there had been no authority having to examine and/or turning on Item 13 of Part I of the Schedule to the Ordinance despite its long existence. But avoidance on double compensation has always been a rule of law. The Ordinance cannot have been intended to provide compensation over and above the value, actual or potential, that the TOA had before or after the temporary creation was initiated.

79.  In the present circumstances, I was referred to by Ms Cheng Daimler AG v Leiduck [2020] 3 HKLRD 579 where an application for leave to appeal was also on the arguments as Mr Ismail. Lisa Wong J dismissed the application for leave on the same limb at §26:

“ … [The legal provision] has a long existence. Despite its history and the habitual exceeding diligence of counsel on both sides in this case, I have not been referred to a single authority, whether direct or indirect, on any aspect of [the legal provision]. I find it difficult to envisage the recurrence of the same or similar combination of facts and circumstances, the resolution of which would turn on the burden of proof so that some future case or cases might benefit from a judgment of the Court of Appeal on the incidence of the burden of proof under [the legal provision].”

80.  I agree the same in the present case. As submitted by Ms Cheng, the present case is very peculiar on its own facts and circumstances (including the relocation of the carparking spaces within the same Lot, the lack of evidence showing that the land which had become the Temporary Carpark had any beneficial use to the applicant, as well as the various restrictions imposed under the Government lease on the permitted use of the TOA). I agree that the problem encountered by the applicant would unlikely surface in another case where an applicant can discharge its burden of adducing evidence (including evidence of any beneficial use of the Temporary Carpark) to support its claim for compensation. Hence it is difficult to envisage the recurrence of the same or similar combination of facts and circumstances, the resolution of which would turn on Item 13 of Part I of the Schedule to the Ordinance as in the present case.

Conclusion

81.  For the above reasons, I dismissed the applicant’s application on 18 June 2021 seeking leave to appeal against the Judgment. I also make an order nisi that the applicant should pay the respondent’s costs with certificate for counsel, to be taxed on High Court Scale if not agree.

 Lawrence Pang
  Member
 Lands Tribunal

Mr Anthony Ismail and Justin Ismail, instructed by Messrs Woo Kwan Lee & Lo, for the Applicant

Ms Bonnie Y.K. Cheng, instructed by the Department of Justice, for the respondent



[1]   See §98 of the Judgment.

[2]   See §101 of the Judgment.

[3]   See §39 of the judgment.

[4]   See §71 of the judgment.

[5]   This drawing was referred to at §98 of the Judgment.

[6]   DLO/HKE stands for District Lands Office, Hong Kong East of the Lands Department.

[7]   TD stands for the Transport Department.

[8]   See §5 of the Judgment.

[9]   Trial Bundle A1/197.

[10]   Trial Bundle A1/25 & 26.

[11]   Trial Bundle A1/27.

[12]   The airspace at and above a level of 12 metres above the Hong Kong Principal Datum of the Pink Stippled Black Cross-hatched Green Area with the TOA in between.

[13]   See also Britned Development Ltd v ABB [2018] EWHC 2616 (Ch) at §12(9) which was affirmed by the English Court of Appeal [2019] EWCA Civ 1840, [2019] WLR(D) 610.

[14]   The concept of Market Value presumes a price is negotiated in an open and competitive market, a circumstance that occasionally gives rise to the use of the adjective open before the words Market Value. The words open and competitive have no absolute meaning. The market for one property could be an international market or a local market. The market could consist of numerous buyers and sellers, or could be one characterized by a limited number of participants. The market in which the property is exposed for sale is not a definitionally restrictive or constricted market. Stated conversely, the omission of the word open does not indicate that a transaction would be private or closed.

[15]   See §5 of the judgment.

[16]   See §16 of the judgment.

[17]   See §17 of the judgment.

[18]   See Tribal Bundle A2/268.

[19]   See §98 of the Judgment.

[20]   In the present case, it is tantamount to the first column of Item 2(a) of Part II of the Schedule to the Ordinance.

[21]   See §98 of the Judgment.

[22]   Trial Bundle A1/197.

[23]   Trial Bundle A1/25 & 26.

[2021] HKLdT 36-EN-2021-05-21

FOOK LEE HOLDINGS LTD v. THE SECRETARY FOR TRANSPORT AND HOUSING

HTML content

LDMR 2/2016

[2021] HKLdT 36

IN THE LANDS TRIBUNAL OF THE

HONG KONG SPECIAL ADMINISTRATIVE REGION

MISCELLANEOUS REFERENCE APPLICATION NO 2 OF 2016

________________

BETWEEN

 FOOK LEE HOLDINGS LIMITEDApplicant
 and
 THE SECRETARY FOR
TRANSPORT AND HOUSING
Respondent

________________

Before: Mr Lawrence Pang, Member of the Lands Tribunal

Dates of Hearing: 1-3 February 2021

Date of Closing Submissions: 15 April 2021

Date of Judgment: 21 May 2021

________________

J U D G M E N T

________________


Background

1.  This is an application for determination of the amount of compensation payable for temporary occupation of land under the Roads (Works, Use and Compensation) Ordinance, Cap 370 (“the Ordinance”).  By a gazette notice dated 21 November 2013 (GN 6953) to facilitate implementation of “PWP Item No 6579TH – Central-Wan Chai Bypass and Island Eastern Corridor Link, a right of temporary occupation was created for some 1,480m2 of Section A of Inland Lot No 7106 and Extension thereto below the level of 12 metres above the Hong Kong Principal Datum (the Temporary Occupation Area is hereinafter referred to as “the TOA” whilst the said lot (together with its extensions thereto) are collectively referred to as “the Lot”) as shown coloured purple stippled black on the Plan No HKM8529a[1].

2.  Initially, the TOA was created for a period from 26 February 2014 to 31 May 2017 in favour of the Government. Pursuant to GN 396 dated 26 January 2017, the period of creation of TOA was subsequently amended to a period from 26 February 2014 to 26 April 2017 (ie approximately 38 months) with the subject land of the TOA remaining unchanged.

The Lot

3.  The applicant is the registered owner of the Lot. The latter is situated on the southwestern side of Oil Street at its end towards the harbourfront. It is erected thereon a hotel known as the Harbour Grand Hong Kong (“the Hotel”) which the applicant terms it as a luxury 5-star hotel. The area in the vicinity comprises a mixture of commercial and residential/commercial composite buildings of various ages.

4.  Use and development of the Lot is governed by Conditions of Exchange No 5036 dated 26 May 1954, as varied and modified by Conditions of Extension No 11717 dated 2 December 1983 and Letters of Modification dated 7 November 1986 and 14 June 2005 respectively (which are collectively referred to as “the Government Lease”).

5.  Special Condition 3 of the Government Lease provides that the Lot is restricted for hotel purposes within the “Pink Area”, and non-industrial (excluding private residential, office, hotel, petrol filling station, and godown) purposes in relation to cultural, leisure and tourist-related activities within the “Pink Hatched Green Area”, the “Pink Cross-hatched Green Area”, the “Pink Stippled Black Cross-hatched Green Areas” and the “Pink Hatched Black Area” as defined in the Letter of Modification dated 14 June 2005. More particularly, pursuant to Special Condition 3(b), the Director of Lands shall have sole discretion in determining what comprises non-industrial (excluding private residential, office, hotel, petrol filling station, and godown) purposes in relation to cultural, leisure and tourist-related activities.

The TOA

6.  The TOA having an area about 1,480m2, has about 1,195 m2 sheltered under the Island Eastern Corridor and about 285m2 unsheltered in open area. In fact, it falls partly within the “Pink Cross-hatched Green Area” and partly within the “Pink Stippled Black Cross-hatched Green Area” of the Lot.

7.  It is not in dispute that the majority portion of the TOA was the ancillary car park for the Hotel accommodating the parking and loading/unloading spaces as required under Special Conditions 54, 55, 56 and 57 of the Government Lease:

“(54) (a) Spaces shall be provided within (the Lot) to the satisfaction of the Director for the parking of motor vehicles at the rate of one space for every 100 hotel rooms and one space for every 1000 seats for conference and banquet facilities. For the purpose of calculating the number of spaces to be provided under this Condition, any floor area to be used for parking spaces and loading and unloading purposes shall be excluded.

(b) Spaces shall be provided within the Pink Hatched Green Area, the Pink Cross-hatched Green Area, the Pink Stippled Black Cross-hatched Green Area and the Pink Hatched Black Area to the satisfaction of the Director for the parking of motor vehicles at the rate of one space for every 250 square metres or part thereof of gross floor area in the building or buildings erected or to be erected on the said Areas. For the purpose of calculating the number of spaces to be provided under this sub-clause, any floor area to be used for parking spaces and loading and unloading purposes shall be excluded.

(c) Each of the above space so provided as specified in sub-clause (a) and (b) hereof shall occupy an area of 2.5 metres in width and 5.0 metres in length with a minimum headroom of 2.4 metres provided that any of the said spaces to be used for the parking of motor vehicles by disabled persons as defined in the Road Traffic Ordinance shall be of such dimensions as may be approved by the Director. Such spaces shall not be used for any purpose other than for the parking for motor vehicles licensed under the Road Traffic Ordinance and belonging to the occupiers of the building or buildings erected or to be erected on (the Lot) and the bona fide guests, visitors or invitees and in particular the said spaces shall not be used for the storage, display or exhibiting of motor vehicles for sale or otherwise.

(55) (a) Subject to sub-clause (b) of this Condition, spaces shall be provided within the Pink Hatched Green Area, the Pink Cross-hatched Green Area, the Pink Stippled Black Cross-hatched Green Areas and the Pink Hatched Black Area to the satisfaction of the Director:

(i) for the loading and unloading of goods vehicles at the rate of one space for every 1,000 square metres or part thereof of gross floor area in the building or buildings erected or to be erected on the said Areas.

(ii) the spcaes to be provided shall each measure 3.5 metres x 11.0 metres with minimum headroom of 4.7 metres. Such spaces shall not be used for any purpose other than for the loading and unloading of goods vehicles in connection with the said building or buildings referred to in sub-clause (a)(i) of this Condition; and

For the purpose of calculating the number of spaces to be provided under this Condition, any floor area to be used for parking spaces and loading and unloading purposes shall be excluded.

(b) For the Pink Area or any part thereof being used for the purposes of a hotel or hotels the following requirements shall apply in addition to the requirements specified in Condition No (54) hereof and sub-clause (a) of this Condition but not in substitution therefor

(i) spaces shall be provided within (the Lot) to the satisfaction of the Director for the following:

(I) One space for every 100 hotel rooms, each measuring 11.0 metres x 3.5 metres with a minimum headroom of 4.7 metres for the loading and unloading of goods vehicles;

(II) 4 spaces, each measuring 5.0 metres x 2.5 metres with a minimum headroom of 2.4 metres for the picking up and setting down of passengers from motor vehicles (including taxis); and

(III) 3 spaces, each measuring 12.0 metres x 3.5 metres with a minimum headroom of 3.8 metres for the picking up and setting down of passengers from single-deck tour buses;

(ii) (I) the spaces to be provided under sub-clause (b)(i)(I) of this Condition shall not be used for any purpose other than for the loading and unloading of motor vehicles licensed under the Road Traffic Ordinance and belonging to the owners or occupiers of the hotel or hotels erected or to be erected on (the Lot) and their bona fide guests, visitors or invitees.

(II) the spaces to be provided under sub-clause (b)(i)(II) and sub-clause (b)(i)(III) of this Condition shall not be used for any purpose other than for the picking up and setting down of passengers; and

(III) in particular the spaces to be provided under sub-clause (b)(i) of this Condition shall not be used for the storage, display or exhibiting of motor vehicles for sale or otherwise.

(56) …

(57) Notwithstanding sub-clause (a) of Condition No (54) hereof, sub-clause (a) and (b) of Condition No (55) hereof and Condition No (56) hereof, the lessees may increase or reduce the respective numbers of each type of spaces specified in the said sub-clauses to be provided on (the Lot) by not more than 5 percent or 50 in number (whichever is the less) of the numbers calculated in accordance with the said sub-clauses.” (underline of “Such spaces” of 54(c) added)

8.  It is not disputed that 20 carparking spaces had been designated immediately prior to the creation of TOA and a small portion of the TOA was part of the landscaped terrace of the Hotel’s café.

9.  During the Relevant Period, the said car parking facilities of the Hotel was relocated to the seaward side of the Lot temporarily (“Temporary Carpark”)[2] in order to reduce the disturbance to the daily operation of the Hotel and to comply with Special Conditions 54, 55, 56 and 57 of the Government Lease.

10.  This Temporary Carpark was physically separated from the Hotel by the TOA; the hoarding erected by Government around the TOA had also completely screened the sight of the Temporary Carpark from the Hotel. This rendered the staff of the Hotel no longer possible to overlook the parking area directly from the ground floor of the Hotel building[3].

Compensation Claim

11.  On 16 February 2015, Messrs Woo Kwan Lee & Lo, on behalf of the applicant, submitted its claim for compensation in respect of the TOA to the respondent for a total sum of HK$19,274,470 (excluding professional fees and interest), together with the particulars of claim prepared by James Ng Surveyors Ltd.

12.  As the Government had already undertaken the reinstatement works arising out of or in connection with the creation of the TOA, in the present proceedings, the only head of compensation which remains under dispute is the total open market rent of the TOA for the Relevant Period under section 2(a) of Part II of the Schedule to the Ordinance: “the amount of an open market rent for claimant’s interest in the land occupied during the period of the easement.”

13.  Item 12 of Part I of the Schedule to the Ordinance stipulates that:

“Where, under the second column of Part II of this Schedule, compensation is to be assessed on the basis of the value of land, or the value of a claimant’s interest in land, or of a rent, that value or that rent shall be assessed as at the date of the happening of the relevant event mentioned in the first column of Part II of this Schedule; and the person entitled to claim shall be the person fitting the description mentioned in the third column of Part II of this Schedule on that date.”

14.  On the applicant’s case, the total market rent was initially HK$18,904,799 (starting at HK$5,467,278 per annum with annual upward adjustments over the Relevant Period) whereas on the respondent’s case, the total market rent was HK$3,933,000 (at a flat rate of HK$1,332,000 per annum over the Relevant Period).

Undisputed Legal Principles

15.  Both parties refer to Ease Gold Development Ltd v Secretary for Transport, LDMR 13/1999 (unreported, dated 7 January 2003) which concerned also the assessment of open market rent for the claimant’s interest as a result of creation of a temporary occupation area under the Ordinance. Then HH Judge Chow of the Tribunal stated at §4 as follows:

“It is important to consider the matters a tenant would consider when deciding the amount of rental for the suit lots. No doubt he will put the land leased to its best possible use. In this respect he will take into account the area, the location, the lease conditions and the zoning of the suit lots.”

16.  Also both parties refer to Discreet Ltd v Secretary for the Environment, Transport and Works, LDMR 4/2005 (unreported, dated 15 March 2006) where the Tribunal was again concerned with the assessment of open market rent for the claimant’s interest as a result of creation of a temporary occupation area under the Ordinance. Then the Tribunal ruled at §§34 & 35 as follows:

“34. It is trite law that in assessing compensation, we cannot simply assume that the land could be used for the specific purpose for which the land was compulsorily resumed. Although the present case involves temporary occupation of land, the same general principle should also apply.

35. In addition AW argued that since the Lots were held for the purpose of building and garden, subject to what was usually known as the “G.N. 364 conditions”, the Lots should be valued on the basis that it could put to car repairing uses and fee paying car park uses, and that we should assume that the Lots could be let out, not only with the benefit of the house structure then standing on the Lots but with the benefit of a much larger notional structure with the gross floor area extending to 1.33 times the area of the Lots. It seems to us that AW lost sight of the need to ascertain the market situation surrounding the Lots. In valuation of a property, we should not assume that since there is no restriction under the lease, we should value the property for all the uses that are permitted. Certainly we have to consider the location of the property, the demand for the proposed uses, particularly if it was not the actual use or a former use, as well as the market reality before deciding whether the property should be put to the proposed uses.” (underline added)

17.  Whereas “open market rent” is not defined in the Ordinance, “market rent” is defined in HKIS Valuation Standards 2017 as follows:

“The estimated amount for which an interest in real property should be leased on the valuation date between a willing lessor and willing lessee on appropriate lease terms in an arm’s length transaction, after proper marketing and where the parties had each acted knowledgeably, prudently and without compulsion.”

The parties have no dispute on adopting this definition.

Expert Evidence

18.  For the purpose of assisting the Tribunal in its determination of the open market rent, the applicant and the respondent have produced the following expert reports:

(1) Expert report dated 30 October 2019 by Mr Ng Yiu Wah (“Mr Ng”) on behalf of the applicant;

(2) Expert report dated 28 November 2019 by Ms Li Sze Man (“Ms Li”) on behalf of the respondent;

(3) Supplemental expert report dated 31 January 2020 by Mr Ng on behalf of the applicant;

(4) Supplemental expert report dated 31 January 2020 by Ms Li on behalf of the respondent;

(5) Joint expert statement dated 28 May 2020 by Mr Ng and Ms Li setting out the areas of agreement and disagreement.

19.  Ms Li was then an Estate Surveyor of the Government’s Lands Department but left its employ in or around late 2020. In the circumstances, Mr Poon Kai Man Simon (“Mr Poon”), also an Estate Surveyor of the Lands Department, has replaced Ms Li as the respondent’s expert. Ms Bonnie Y K Cheng (“Ms Cheng”), counsel for the respondent, submitted that upon considering Ms Li’s expert reports and the joint expert statement afore-mentioned, Mr Poon agreed with the opinions of Ms Li stated therein. Mr Poon had confirmed that he would adopt the same as his own opinions for the purpose of this trial. Mr Poon’s computation of the open market rent of the TOA during the Relevant Period is as follows:[4]

Site Particulars 
Temporary Occupation Area (“TOA”):1,480m2
Relevant Period (26.2.2014 to 26.4.2017):3.164 years
Date of Valuation:26.2.2014
Compensation Assessment 
Open Market Rent 
1,480m2 x $900/m2 per annum$1,332,000
YP for 3.164 years @ 3.4%x2.9525
$3,932,730
say$3,933,000

20.  Initially, Mr Ng’s computation of the open market rent of the TOA during the Relevant Period is as follows[5]:

Open Area285m2  
Unit Rate$212.0/m2  
 $60,420.0 
Sheltered Area1,195m2  
Unit Rate (56% higher than open area)$330.7/m2  
$395,186.5 
Open Market Rent per month$455,606.5 
1st year rental (26.2.2014 to 25.2.2015) $5,467,278
2nd year rental (26.2.2015 to 25.2.2016) $5,926,529[6]
3rd year rental (26.2.2016 to 25.2.2017)  $6,385,781[7]
Rental for the period from 26.2.2017 to 26.4.2017  $1,125,211[8]
Total Compensation $18,904,799

21.  In Mr Christopher Chain (leading with Mr Brian Fan but hereafter referred to collectively as “Mr Chain”)’s closing submission, he informed that Mr Ng had revised his valuation because of the following concessions:

(a) Mr Ng agreed that the comparable of the Tung Tao Court indoor car park should be excluded, since there are issues of illegal use arising from that particular car park.

(b) Mr Ng also agreed that, upon reflection, his previously held opinion of a year-on-year 8.4% adjustment over the course of 3 years should not be applied, as the STT rental rates (ie the rental for the 3 Core Comparables used in the Market Rent Valuation) are also reviewed once every 3 years.

22.  Mr Ng’s revised valuation is as follows:

Open Area285m2  
Unit Rate$205.5/m2  
 $58,567.5 
Sheltered Area1,195m2  
Unit Rate (56% higher than open area)$324.7/m2  
$388,016.5 
Open Market Rent per month$446,584.0 
1st year rental (26.2.2014 to 25.2.2015) $5,359,008
2nd year rental (26.2.2015 to 25.2.2016) $5,359,008
3rd year rental (26.2.2016 to 25.2.2017)  $5,359,008
Rental for the period from 26.2.2017 to 26.4.2017  $908,054
Total Compensation $16,985,078
 ie a discount about 10%

Mr Poon’s Evidence

23.  In his opening as well as his closing submission, Mr Chain contended that no weight should be given to Mr Poon’s evidence on the basis his being employed by the Director of Lands, which had conducted this case on behalf of the respondent.

24.  Although I had referred Mr Chain to Tang Ping Choi v Secretary for Transport [2004] 3 HKC 178 during trial, Mr Chain persisted in his concern by referring to what Rogers VP stated (as he then was) in that case:

“17. … (the employee) might wish to justify previous advice given. In the second place many of the problems which have arisen with regard to expert evidence have been caused by the fact that the witnesses have not been frank with the court. In some cases they have given evidence which is half truthful, keeping back knowledge which they knew as experts and which was relevant to the matter in respect of which they were giving evidence…”

25.  Mr Chain submitted that Mr Poon, in defending Ms Li’s opinion, had clearly demonstrated partisanship, lack of objectivity, bias and lack of independence:

(a) Mr Poon had accepted during cross-examination that he had the overriding duty to assist the Tribunal impartially and independently, and this was his paramount duty as an expert witness. However, Mr Poon admitted that at certain point in time harboured strong doubts towards the reasoning and conclusions of Ms Li. Then notwithstanding, Mr Poon still proceeded to sign the Statement of Truth to declare that his opinion was honestly held.

(b) For example, during evidence-in-chief, Mr Poon suddenly disclaimed Ms Li’s location adjustments made to the following comparables previously fully adopted by himself, and instead suggested that no adjustments were necessary except for a -5% to Comparable 3. While Mr Poon suggested that he changed his views after hearing Mr Ng’s evidence, he conceded upon cross-examination that his misgivings on the location adjustments existed as early as when he adopted Ms Li’s evidence.

26.  Mr Chain submitted that the justification Mr Poon gave for his actions clearly showed that he not only prioritized but actively participated in protecting his employer’s interest. Mr Poon conceded that he made a conscious decision not to set out any his disagreements or uneasiness with Ms Li’s opinions, because doing so would require putting in a further supplemental expert report at a late stage (after Ms Li left its employ in or by the Lands Department around late 2020), which could lead to objection by the applicant and derailing of this trial with cost consequences to the respondent.

27.  Mr Chain also referred to an instance during cross-examination when Mr Poon suddenly alleged that there was another relevant open-air car park comparable near Carson Mansion, near King’s Road whereby I questioned Mr Poon why he did not mention this car park earlier or during the site inspection when he had every opportunity to do so.

28.  Mr Chain then referred to Best Origin Limited v Commissioner of Rating and Valuation, LDGA 14/1998 (unreported, dated 29 June 2006) where Lam J (as he then was) emphasized that:

“… if a particular omission has been drawn to (the expert’s) attention which might affect his opinion he should also inform the court accordingly if there is anything that suggests the opinion set out in the existing report could be misleading by reason of some other matters, which only came to the expert’s attention subsequent to the writing of his report, the tribunal expects the expert to correct it and give disclosure voluntarily.”

29.  With respect to Mr Chain, I must repeat the Tribunal or other courts’ agreement that valuation is not an exact science. In particular, when it comes to the choice of comparables and the ensuing adjustments on location, there exists no formula or mechanistic reference but highly depends on the subjective assessment of the valuation expert on the basis of his experience and familiarity of the area. On the one hand, valuation experts of both parties in litigation may accept compromise in working out their joint expert statements on agreement and disagreements. On other occasions, a valuation expert may as well change his opinion on location adjustment after a joint site inspection when he found something he did not observe earlier or overlooked. In Success Active Limited v Harbourview International Holdings Limited & Others, LDCS 31000/2018 (unreported, dated 19 April 2021), the Tribunal even remarked that the valuation expert tried to switch his opinion on location adjustments during trial[9]. While this may affect the reliability of the expert’s evidence, it does not necessarily mean that his evidence is biased or inadmissible. I have sympathy with Mr Poon in having to adopt or otherwise the evidence of Ms Li so soon after her departure. In fact, Rogers VP continued further in Tang Ping Choi as follows:

“19. The fact that Mr Cheng might have derived income directly or indirectly from carrying out his function of giving evidence is irrelevant. Expert witnesses are usually paid. If they were not paid they would be hardly likely to give up their valuable time in the preparation and giving of evidence. The reality of the situation in this regard is as put by Laddie J in Cala Homes (South) Ltd and Others v Alfred McAlpine Homes East Ltd [1995] FSR 818 where he said at page 843 that the court would obviously be aware that a party is likely to choose as its expert someone who holds views that are most sympathetic to its position. Put in another way, it can hardly be supposed that a party will call an expert to give evidence which contradicts its own case.”

30.  Mr Poon disclaimed Ms Li’s location adjustments at trial made to the comparables previously fully adopted by himself, and instead suggested that no adjustments were necessary except for a -5% to Comparable 3. Mr Poon put forward this change voluntarily in the examination-in-chief in favour of the applicant without compulsion from the applicant or any one. I only deplored that Mr Poon did not carry out a physical inspection of the comparables before adopting Ms Li’s evidence. But this did not have any material difference from Mr Ng making concessions also on not adopting certain comparable he had previously adopted or even on the methodology of assessment. See §21 above.

31.  More importantly, as the Tribunal pointed out in Supergoal Investment Limited v Five F Ming House Limited & Others [2014] 1 HKLRD 286 and Cheer Capital Limited v Unibase Investment Limited & Others, LDCS 5000 & 6000/2013 (unreported, dated 12 June 2015), it is not bound to accept the submission of any party and may rely upon its own experience in determining the dispute on valuation, relying on Myers v. South Lakeland District Council [2005] EWCA Civ 498; [2005] RVR 301 and Checkpoint Limited v. Strathclyde Pension Fund [2003] 14 EG 124, [2003] EWCA Civ 84. And this is often the case particularly on the issue on the valuation adjustments. In Lingrade Development Limited v Secretary for Environment, Transport and Works (2011) 14 HKCFAR 439, the Court of Final Appeal remarked as follows:

“20. These remarks seem to me to demonstrate some degree of misapprehension about the exercise which the Tribunal was required to undertake. It had to form the most accurate view it could about what apartments built according to the original scheme would have fetched … Valuation is not of course an exact science, but the Tribunal’s assessment was solidly based upon which actually happened to very similar apartments soon after the relevant time.

…

23. The question is not whether Mr Wong’s evidence was accepted or rejected but whether there was evidence to support the decision of the Tribunal.  They had before them the evidence of the sales of apartments by Lingrade and the index which they thought appropriate.  There is no challenge to the methodology which they, as an expert specialist tribunal, chose to adopt.”

32.  I am content to give due consideration to the expert evidence of Mr Poon and put appropriate weight on it. See also section 10(6) of the Lands Tribunal Ordinance.

Comparables

33.  Both valuation experts, Mr Ng and Mr Poon, agreed to adopt the following 3 contemporaneous Government-tendered short term tenancies (“STT”) for open-air car parks as their comparables for arriving at the open market rent of the TOA:[10]

CompSTT NoLocationUserTerm Annual RentalArea (m2)Annual Unit Rental
(/m2)
Current Hourly Charge
1EHX-501Hing Man Street/ Hoi Foo Street, Shau Kei WanA fee-paying public carpark for the parking of motor vehicles (excluding tractors, trailers, container vehicles with or without tractors or trailers, gas vehicles and any motor vehicle carrying or laden with any cylinder, receptacle or container, whether empty or not, which is used or to be used to contain liquefied petroleum gas for any purpose other than as the motor fuel for such motor vehicle) …1 year certain commencing on 9.9.2013 and thereafter quarterly$4,561,2003,520$1,296$11 (mon-fri)/
$13 (Sat-Sun & PH)
2EHX-527Junction of Oi Yee Street and Hing Man Street, Shau Kei Wan1 year certain commencing on 3.11.2014 and thereafter quarterly$2,100,0001,320$1,591$11 (mon-fri)/
$13 (Sat-Sun & PH)
3EHX-515Junction of Lei King Road and Tai On Street, Sai Wan Ho1 year certain commencing on 16.1.2015 and thereafter quarterly$4,836,0002,720$1,778$14

34.  Notwithstanding the above, save for the size adjustments for Comparable 2 and Comparable 3 at 0% and 5% respectively, the two experts have the following disagreements.

Adjustments for Location

35.  Ms Li, as adoptd by Mr Poon, described the comparables in her expert report dated 28 November 2019 as follows:[11]

“5.6 (Comparable 1) having an area of about 3,520 m2 was located at Shau Kei Wan fetching a unit rental of $1,296/m2 pa. This comparable was irregular in shape and abutted on Hoi Foo Street, branching off from Shau Kei Wan Road. It was situated in a traditionally densely populated area dominated by pencil commercial and residential developments affording no in-house spaces for provision of car parking facilities. Compared with the subject land located at the seaward side pretty distant away from the main commercial areas surrounding MTR Fortress Hill Station, (Comparable 1) was considered superior to the subject land in terms of location warranting downward adjustment…

5.7 (Comparable 2) having an area of about 1,320 m2 was located at Shau Kei Wan fetching a unit rental of $1,591/m2 pa. This comparable was rectangular in shape and was situated at the junction of Oi Yee Street and Hing Man Street, branching off from Shau Kei Wan Road whereas its size is similar to the subject land. Being located in close proximity to (Comparable 1), this comparable possessed the same locational characteristics as mentioned in paragraph 5.6 above and thus warrants downward adjustment to location.

5.8 (Comparable 3) having an area of about 2,720 m2 was located at Aldrich Bay, Sai Wan Ho fetching a unit rental of $1,778/m2 pa. This comparable was elongated in shape. It was located at a well-planned and developed residential area established by estate-type residential developments such as Lei King Wan, Les Saisons and Grand Promenade. Coupled with the eateries beneath Lee King Wan, the demand for car parking facilities there is considered large. (Comparable 3) is therefore considered superior to the subject land in terms of location warranting downward adjustment…” (underline added)

36.  In contrast, Mr Ng was of the view that an upward location adjustment of 58% to all the 3 comparables should be made. He formed his opinion on the basis of hourly rates of indoor car parks in different districts. Mr Ng remarked at §5.2.5 of the joint statement that: “Be it open or indoor, the use of a car park is for car parking. So long as the car park comparables adopted are either all indoors or open, it makes no difference even if indoor car parks are used as comparables given the difference in hourly rates serves as good as that of open car park comparables in reflecting the appropriate adjustment due to location difference. Moreover, the difference between indoor and open car parks due to restrictions and characteristics such as users under lease and floor levels … will become irrelevant when all the comparables are of the same type, ie either all open or all indoor.”[12]

37.  Mr Ng relied on the following hourly rates of indoor car parks obtained in August 2017 for the purpose of comparison:[13]

North PointSai Wan Ho / Shau Kei Wan
Olympia Plaza at 255 King’s Road$27Grand Promenade at 38 Tai Hong Street$17
AIA Tower at 183 Electric Road (off its junction with Oil Street)$28Tung Tao Court at 33 Oi Shun Road (opposite EHX-501 across the street)$15
Harbour Heights with carpark entrance at the end of Watson Road$23Oi Tung Estate Oi Tung Shopping Complex at 18 Oi Yin Street$16
Victoria Centre at 15 Watson Road$23  
Average:$25.25Average:$16

where

38.  Mr Ng tried to support his analysis by asserting that location is a predominant factor which would affect the hourly rate of a fee-paying public car park.

39.  At trial, I had pointed out that the 2 indoor car park comparables in Shau Kei Wan might not be so relevant because they are built by the Housing Authority who has been notoriously known to have high carparking ratios though I appreciate that car drivers may be attracted to the Oi Tung Estate Oi Tung Shopping Complex for regional shopping purposes. Tung Tao Court in particular would not be a suitable comparable because the carparking spaces there are offered for general public use which is prima facie in breach of the relevant condition. Mr Ng fairly made concession and revised his assessment of market rent downwards as stated in Mr Chain’s closing submission.

40.  On the other hand, AIA Tower in North Point is a high-class commercial/office building which attract many day-to-day visitors. Indeed, both AIA Tower and Olympia Plaza occupy a convenient and busy location in proximity to the hustling and bustling King’s Road and the MTR Fortress Hill Station.

41.  In such regard, I consider an adjustment of  more appropriate.

42.  Ms Li instead put forward other STT comparables for outdoor fee-paying public car parks in her supplemental report dated 31 January 2020 for direct adjustment to account for the locational difference:[14]

STTs in Sai Wan Ho and Shau Kei Wan:

CompSTT NoLocationUserTermAnnual RentalArea (m2)Annual Unit Rental (/m2)
A1EHX-461Hing Man Street/ Hoi Foo Street, Shau Kei Wan (Same location as Comparable 1)A fee-paying public carpark for the parking of motor vehicles (excluding tractors, trailers, container vehicles with or without tractors or trailers, gas vehicles and any motor vehicle carrying or laden with any cylinder, receptacle or container, whether empty or not, which is used or to be used to contain liquefied petroleum gas for any purpose other than as the motor fuel for such motor vehicle) …1 year certain commencing on 1.2.2010 and thereafter quarterly$3,624,0003,820$949
A2EHX-487Junction of Oi Yee Street and Hing Man Street, Shau Kei Wan (Same location as Comparable 2)1 year certain commencing on 1.11.2011 and thereafter quarterly$1,536,0001,320$1,164
A3EHX-452Junction of Lei King Road and Tai On Street, Sai Wan Ho (Same location as Comparable 3)1 year certain commencing on 1.10.2009 and thereafter quarterly$3,420,0002,730$1,253
     Average:$1,122

STTs in North Point:

CompSTT NoLocationUserTermAnnual RentalArea (m2)Annual Unit Rental
(/m2)
B1EHX-395Oil StreetA fee-paying public carpark for the parking of motor vehicles (excluding lorries, coaches, tractors, trailers, container vehicles with or without tractors or trailers, and gas vehicles and any motor vehicle carrying or laden with any cylinder, receptacle or container, whether empty or not, which is used or to be used to contain liquefied petroleum gas for any purpose other than as the motor fuel for such motor vehicle) …6 months certain commencing on 19.12.2005 and thereafter monthly$2,587,032
(effective from 1.1.2010)
3,980$650
B2EHX-430Junction of Shu Kuk Street and North Point Estate LaneA fee-paying public carpark for the parking of motor vehicles (excluding tractors, trailers, container vehicles with or without tractors or trailers, gas vehicles and any motor vehicle carrying or laden with any cylinder, receptacle or container, whether empty or not, which is used or to be used to contain liquefied petroleum gas for any purpose other than as the motor fuel for such motor vehicle) …6 months certain commencing on 19.9.2008 and thereafter monthly$6,613,440 (effective from 19.9.2011)7,960$831
B3EHX-428Junction of Java Road and Shu Kuk StreetI year certain commencing on 1.5.2009 and thereafter monthly$3,492,000
(effective from 1.5.2012)
4,060$860
     Average:$780

43.  In rebuttal, Mr Ng remarked that the two sets of comparables were different in nature and (there were factors other than location difference (eg user, size time, layout and configuration) that would have material impacts on the rentals…)[15] Mr Ng referred to the comparables in North Point were rent review cases as distinguished from fresh leases as a result of open tenders. Mr Ng commented that the rental agreed may not necessarily reflected the open market rent and may be affected by other factors or private consideration of the parties, eg saving in Government’s man-power and costs involved in re-tendering, consideration of committed programme for the implementation of planned uses/development of the STT sites that will pose uncertainties on the period of continuous occupation under the monthly tenancy. In that regard, I must agree with Mr Ng. For instance, the land for EHX-395 (ie B1) was tendered for sale as part of Inland Lot 8920 in mid-2011, which was only some a year and half after the rent review and the land for EHX-430 (ie B2) was tendered for sale as part of Inland Lot 9020 in early 2013, which was less than a year and half after the rent review. Judicial notice is also taken of Kwong Fat Loong Shipyard v Commissioner of Rating and Valuation, LDRA 5/1988 (unreported, dated 9 January 1990) in which the Tribunal was of the opinion that the new rent negotiated for a short term tenancy upon rent review might not represent open market rent. Further, the user clause of B1 was more restrictive in that the parking of lorries and coaches were specifically excluded. As well, the unit rental for B2 would require upward adjustments for

(a) its significant size of 7,960 m2;

(b) the constraint on flexibility by the minimum provision of 25 numbers of space with dimensions 12m x 3.5 for the parking of bus and goods vehicles and 40 numbers of space with dimensions 2m x 1m for the parking of motor cycles; and

(c) the requirement for protection of 8 numbers of trees and their metal shoring and the non-parking areas that were located in the central part of the site.

44.  Mr Ng also managed to find out the hourly rates charged for private cars in 2011 for these new comparables put forward by Ms Li in her supplemental report:[16]

Comparable NosHourly RateComparable NosHourly Rate
A1 (EHX-461)$9B1 (EHX-395)$12
A2 (EHX-487)$9B2 (EHX-430)$11
A3 (EHX-452)$10B3 (EHX-428)$11

45.  Having made such comparison, Mr Ng remarked that B1, being situated just opposite the TOA fetched an even higher hourly rate than the other two North Point car park comparables B2 and B3 which were situated within primarily residential neighbourhoods. I agree with Mr Ng that the TOA was situated in a much better location than all other car park comparables in these new sets of comparables.

46.  In addition, Mr Ng drew the Tribunal’s attention to there being abundant supply of open car parks in North Point in 2011 with the presence of the 3 open car parks B1, B2 and B3 providing about 772 to 888 parking spaces in total (assuming the average site area occupied by each car park is 20 m2 and 23 m2 respectively). These open car parks had however been lost in 2014 when B1, B2 and B3 were then devoted to new developments[17]. I agree with Mr Ng that the location adjustment for the three comparables adopted for direct comparison should be upwards instead of downwards.

47.  In such regard, I agree with Mr Ng that comparison of the hourly rates charged by carpark operators in different areas will provide good guidance on the difference that may be caused by locational difference. I also agree with Mr Ng that so long as there is no material change in the condition of the immediate neighbourhood that would materially affect the demand and/or supply of carparking, eg large scale redevelopment in the area causing loss or increase in supply and/or demand, etc, the location difference analysed from the indoor car park comparables in 2017 should be very similar, if not exactly the same, for 2014.

48.  That said, I agree with Mr Poon that indoor car parks are not the same as the open fee-paying public car parks due to restrictions and characteristics such as users under the Government leases and floor levels. That 35.29% might be applicable to the retail parking but not necessarily applicable to the open market rent payable by a car park operator as in the STTs. In Top Sail International Limited v Wong Lai Wei, LDCS 19000/2010 (unreported, dated 26 October 2011), the expert on behalf of the respondent was criticized by the Tribunal to have based on the daily room rate of $800, the average unit rate for the “domestic GDV” of the proposed hotel on the lots in question instead of calculating the net rental income of the hotel, or the net sale price of the hotel accommodation.[18]

49.  Thus, if I just take EHX-527 (which has a similar area as the TOA) as example, assuming it could derive receipt of R for running the carpark, the cost of running it and the profit the operator expected are taken as C, then R – C = $1,591/m2 (being open market rent of the carpark that the operator afforded to pay) which can be rearranged to become C = R - $1,591/m2. Then if R is subject to an addition of 36% for location, and assuming C is relatively constant, then the open market rent of such location would be 1.36%R – C[19] or 1.36%R – (R - $1,591/m2)

ie $1,591/m2 + 36%R

50.  Thus, assuming that R is some 20% higher than $1,591/m2, this is not too far away from Mr Ng’s assertion of 58%.

51.  As regards Mr Poon’s sudden disclaiming Ms Li’s location adjustments and replacing instead new adjustments at 0%, 0% and -5%, I am not persuaded, especially having conducted the inspection of the comparables.

Adjustment for Time

52.  Initially, in attempting to arrive at the time adjustments, Mr Ng relied on four pairs of STT transactions, the tenancies of which were offered for tender by Government again upon expiry of the original ones. His analysis is as follows:[20]

 1st Pair2nd Pair3rd pair4th Pair
STTEHX 452EHX 515EHX 487EHX 527*EHX 491EHX 516EHX 527*EHX 548
LocationLei King Road/Tai On Street, Sai Wan HoHing Man Street/Oi Yee Street, Shau Kei WanSheung On Street, Chai WanHing Man Street/Oi Yee Street, Shau Kei Wan
Tender Award Date18.09.200930.12.201419.10.201117.10.201423.11.201121.11.201417.10.201419.07.2016
Monthly Rental$270,000$403,000$128,000$175,000$105,000$128,000$175,000$188,999
Area (m2)2,7302,7201,3203,0601,320
Unit Rate (/m2)$98.9$148.2$97.0$132.6$34.3$41.8$132.58$143.18
Increase49.8%36.7%21.9%8.0%
Increase per year9.4%12.2%7.3%4.6%

*ie Comparable 2

53.  In his Supplemental Report of 31 January 2020, however, Mr Ng considered Ms Li’s proposed time adjustment on the basis of the Private Retail Index compiled by the Rating and Valuation Department being in line with his adjustments. “As such, (Mr Ng) would have no objection to adopt the Respondent Expert’s time adjustments”.[21]

54.  Yet, in the joint expert statement dated 28 May 2020, Mr Ng asserted that the time adjustments he had initially proposed “should be preferred to that derived from the Private Retail Index … since retail properties are wholly different from open car parks both in nature and market performance.”[22] To this I agree and in any event, the differences between the two experts are less than 4%.

Adjustments for Size

55.  As said, the two experts have agreed the size adjustments for Comparable 2 and Comparable 3 at 0% and 5% respectively. However, when compared with the TOA of 1,480m2, Comparable 1, having the size of as much as 3,520m2, is more than doubling the size of the TOA. I consider the adjustment of 10% as proposed by Mr Ng appropriate.

Adjustments for Layout & Configuration

56.  Mr Ng proposed no adjustment for layout in respect of Comparable 2 and Comparable 3; on the other hand, Mr Ng considered the configuration of Comparable 1 awkward, being long, narrow and of irregular shape. He recommended +15%.

57.  Mr Poon, adopting the reports prepared by Ms Li, proposed an adjustment of -15% for each comparable because the TOA was subject to a right of passage of motor vehicles to the adjoining lot to and from Oil Street under Special Condition 23 which provides as follows:

“There is excepted and reserved to the owner of all that piece or parcel of ground known and registered in the Land Registry as The Remaining Portion of Inland Lot No 7106 And The Extension Thereto (hereinafter referred to as “IL 7106 RP & Extension”)[23], his tenants, servants, visitors, workmen and other persons authorized by him in that behalf, a free and uninterrupted right from time to time and at all times for all purposes connected with the proper use and enjoyment of IL 7106 RP & Extension to pass and repass on, along, over, by and through the Pink Cross-hatched Green Area and for the passage of motor vehicles to or from IL 7106 RP & Extension from or to Oil Street or the extension thereto between the points X and Y through Z shown and marked on the plan annexed hereto (ie Plan No HKM7007).”

58.  Ms Li suggested that in this connection, this part of the TOA could not be fully and freely used for car parking purposes. Also apart from reserving a right of way to IL 7106 RP & Extension, the presence of four supporting columns of the Island Eastern Corridor within the TOA would reduce its utility, giving rise to constraints to the overall design and layout for car parking purposes.[24]

59.  In contrast, Mr Ng managed to designate 74 carparking spaces on the TOA (“the Hypothetical Car Park”)[25]. Mr Ng tried to support his adjustments by making reference to the number of carparking spaces that may be accommodated in each of the STT comparables. Mr Ng assumed that the average site area to be occupied by a carparking space (including the circulation space) for Comparable 2 and Comparable 3 is 20m2 whereas that for Comparable 1 is 23m2:

STTEHX-501
(Comparable 1)
EHX-527
(Comparable 2)
EHX-515
(Comparable 3)
No of Carpark156[26]65[27]135[28]
Carparking Size (including circulation space)23m220m220m2

That is .

60.  From the above, it appears that Mr Ng’s adjustments for layout or configuration has double counted that for size. Assuming Mr Ng’s estimations of the number of carparking spaces for the respective comparables are correct, I consider more appropriate to carry out the analysis on the basis of number of carparking spaces instead of on site area, following Hongda Containers Limited v Secretary for Transport, LDMR 7/2000 (unreported, dated 4 June 2002) and more recently Golf Café Bars Limited v West Yorkshire Combined Authority & Another [2021] UKUT 0016 (LC). This approach has the further advantage of having obliterated the adjustments for size, layout and configuration which are mostly subjective.

61.  Therefore, whereas Mr Ng’s adjustments for location and time are preferred, the analysis should have been conducted on the basis of number of car parking spaces available:

CompMonthly RentalNo of CarparkRental per carparkAdjustmentAdjusted Rental per carpark
LocationTimeSize*Total
1$380,100156$2,43658%4.2%0%64.64%$4,012
2$175,00065$2,69258%-5.4%0%48.47%$3,997
3$403,000135$2,98558%-7.1%0%46.78%$4,381
        $4,130

* With this approach, there should not be any adjustment for quantum (size) because when the number of carparking space is larger, the operator enjoys economy of scale with relatively the same fixed cost of management. Otherwise, as can be observed, if the size adjustments proposed by Mr Ng be included, the disparity among the adjusted rates would become larger. In that event, as the TOA is closer in size with Comparable 2 and the difference in the number of carparking spaces to be accommodated is smaller, more weight should have been place on the adjusted rate of this comparable, resulting in similar final figure.

Shelter Effect

62.  In addition to the above, both Mr Ng and Mr Poon agreed that

(a) the 3 comparables above are open land without any shelter; and

(b) upward adjustment should be given to recognize the value of the “shelter effect” of the Island Eastern Corridor covering the sheltered part (“the Sheltered Part”) which made up 1,195 m2 of the 1,480 m2 of TOA.

63.  In particular, Mr Ng explained the significance of the “shelter effect” as follows:

(a) Sheltered car-parking spaces are preferred by drivers as they provide better weather protection and more comfort and convenience;

(b) The “shelter effect” given by the Island Eastern Corridor over the Sheltered Part does not only mitigate the impact of rain, but more importantly against the impact of sunlight and direct heat that would otherwise be absorbed by the parked cars.

64.  For the purpose of determining the extent of the “shelter effect”, Mr Ng made reference to a pair of different STT comparables in Tsuen Wan as follows:

STT NoAddressTender Award DateOpen Area (m2)Sheltered Area (m2)Monthly RentalAdjustment on Size onlyAdjusted Monthly RentUnit Rent  (Open Area)Unit Rent  (Sheltered Area)
1524Junction of Hoi Shing Road and Hoi Kok Street28 Aug 141,3400$146.1000%$146.100$109 
1521Junction of Hoi Shing Road and Hoi Hing Road22 Aug 141,770960$362,0005%$380.100$109$195

65.  While the above analysis gives a difference of , Mr Ng made further reference to the hourly rates of open and covered car parks in Shau Kei Wan and Sai Wan Ho in §§33 & 37 above and noted the difference of hourly rates between open and covered carpark would be .[29] Taking the average therefore, Mr Ng arrived at 58% which he proposed as the adjustment for sheltered car park.

66.  On the other hand, Mr Poon, adopting Ms Li’s evidence, only allowed an adjustment of 5% because the Island Eastern Corridor would provide minimal cover from storms and rain as it was at a height as much as 8 metres[30].

67.  As regards the two comparables in Tsuen Wan above, Ms Li commented in §3.1.3 of her Supplemental Report dated 31 January 2020 that the flyover at Tsuen Wan Road above STT 1521 is as high as 20 metres, “serving nearly no waterproof function for the cars parked under the flyover”[31]. She suggested there were many factors that may affect the rentals of two car parks with different attributes and characteristics; it was not accurate to allege that the difference of the unit rentals between STT 1524 and STT 1521 were all brought by the “shelter effect”.

68.  Ms Li stated that these two STTs were indeed awarded to the same company ie Forerun Management Limited. She suggested that operating two car parks located so close to each other may generate some special interests that other operators in the market could not enjoy. Therefore, the tenderer might be willing to offer a higher rental than the market level for the benefits of such economics of scale. But with respect, this suggestion by Ms Li cannot explain why Forerun Management Limited offered two significantly different unit rentals for the two carparks which appear to be the same in locality.


69.  On the other hand, as pointed out by Mr Poon, the hourly charges between the open car park at Sai Wan Ho, being EHX515, ie Comparable 3 at $14 and the Grand Promenade Public Car Park at $17 close to it provide the best indication of the consumers’ preference between covered and sheltered car parks. This difference is only . While Mr Ng explained that open-air sheltered car parking spaces on the ground floor would be generally more convenient than indoor multi-storey car-parking spaces like the Grand Promenade Public Car Park, the latter may provide better management.

70.  In the absence of further evidence, however, I cannot but adopt the average of 78.9% and 21.4%, which is equal to 50%.

71.  It is important to note that at the time of the site inspection, the Sheltered Part had already been halved because of the demolition of one-line traffic of the Island Eastern Corridor. But by reference to the Plan No HKM8529a which was prepared for the purpose of creating the TOA vis-à-vis the layout plan of the car parking spaces, I note all the carparking spaces were supposed to be sheltered by the Island Eastern Corridor.

72.  Whereas there were only 20 carparking spaces prior to the creation of the TOA, it appears that the open market rent of the TOA assuming that it could have been used as a fee-paying public carpark as the comparables would be: $4,130 per month x 20 x 1.5 = $123,900 per month as at 26 February 2014.

User Restriction

73.  In spite of the above, applying the similar site area occupied by each car park at 20m2, Mr Ng managed to designate 74 carparking spaces on the TOA instead of 20. Mr Ng conceded that this 20m2 per carparking space paid no heed to Special Conditions 54, 55, 56 and 57 of the Government Lease pertaining to the TOA (as stated in §7 above). Mr Chain advocated in support that the ancillary car park for the Hotel as required under Special Conditions 54 to 57 had been temporarily relocated to the northern portion of the Lot so that those lease conditions were at all times compiled with during the TOA period.

74.  This cannot be right as, for instance, Special Conditions 54(b) and 55(a) requires carparking spaces to be provided within the Pink Hatched Green Area, the Pink Cross-hatched Green Area, the Pink Stippled Black Cross-hatched Green Areas and the Pink Hatched Black Area of the Lot. It is trite that “any increase (or decrease) in value which is entirely due to the scheme underlying the acquisition” should be disregarded, the well-known Pointe Gourde principle following the Privy Council decision in Pointe Gourde Quarrying and Transport Co Ltd v Sub-Intendent of Crown Lands [1947] AC 565. Thus, any action carried out by the Government as a result of the scheme underlying the creation of the TOA should not have the effect of removing any restriction on user on the Pink Hatched Green Area, the Pink Cross-hatched Green Area, the Pink Stippled Black Cross-hatched Green Areas and the Pink Hatched Black Area of the Lot.[32]

75.  Under Special Condition 54(c), each of those spaces so provided shall occupy an area of 2.5 metres in width and 5.0 metres in length instead of the smaller dimensions of 2.1-2.3 metres x 4.2-4.6 metres suggested by Mr Ng. That is, the proposed area for each parking space is at least 20% smaller than that required under Special Condition 54(c). Mr Ng would have exaggerated the number of car parking spaces that can be accommodated on the TOA by more than this percentage if the maneuvering spaces are also taken into consideration. This should not be a simplistic exercise of arithmetic division but requires substantial re-alignment and reconfiguration of the 4 parades of parking spaces proposed by Mr Ng. That Mr Chain’s claim that Special Condition 54(c) is not applicable to the car parking spaces to be provided in the Lot is totally out of question.

76.  In that regard, I agree with the respondent that Special Conditions 23 and 55(a) limits the flexibility in layout of the carparking spaces within the TOA. Special Condition 23 is repeated as follows:

“(23)    There is excepted and reserved to the owner of all that piece or parcel of ground (referred to as “IL 7106 RP & Extension” behind the Hotel), his tenants, servants, visitors, workmen and other persons authorized by him in that behalf, a free and uninterrupted right from time to time and at all times for all purposes connected with the proper use and enjoyment of IL 7106 RP & Extension to pass and repass on, along, over, by and through the Pink Cross-hatched Green Area (which largely covered by the TOA) and for the passage of motor vehicles to or from IL 7106 RP & Extension from or to Oil Street or the extension thereto between the points X and Y through Z shown and marked on the plan annexed hereto (ie Plan No HKM7007)”

Mr Chain, in his opening submission at §19(a)(ii), admitted that the TOA did cover the access between the points X and Y through Z.

77.  Mr Chain suggests that “Such spaces” as referred to in Special Condition 54(c)[33] are not confined to be provided only in the TOA but can be provided anywhere on the Lot. He submits that “(t)he purpose of Special Condition 54 is to ensure that adequate parking spaces would be provided for the exclusive use of Hotel guest. It does not purport to stipulate that extra car-parking spaces provided on top of the “parking requirements” must also be confined to for the use of “occupiers of the building or buildings erected or to be erected on the New Lot(ie the Lot) and the bona fide guests, visitors or invitees.””

78.  With respect, Mr Chain did not observe Special Condition 57 which limits the extra car-parking spaces that can be provided by not more than 5% or 50 in number (whichever is the less). That his interpretation of Special Condition 54(a) towards the counting the floor area to be used for parking spaces is totally misplaced.

79.  In addition, in designating the 74 carparking spaces, Mr Ng failed to observe the following Special Condition:

“(38) (b) (v) The lessees shall ensure that adequate measures shall be taken at their own expense and in all respects to the satisfaction of the Director to protect that part of the Island Eastern Corridor passing over the Pink Cross-hatched Green Area … from time to time in relation to the use of untensioned corrugated beam barriers for the protection of columns shall be followed except with the prior written approval of the Director. The form of protective measures to be used for the Island Eastern Corridor shall be subject to the prior written approval of the Director. In particular, the lessees shall comply with the following requirements:

(I) Except with the prior written approval of the Director, a 2 metres clearance from soffit and around columns and abutments shall be made available for inspection and maintenance works at all times.”

80.  Mr Ng did give the honest answer that this was not within his contemplation when he first drew up the plan for the Hypothetical Car Park on the TOA. But in defending his failure to allow for these 2 metres clearance in calculating the number of carparking spaces, Mr Ng suggested that the 2 metres clearance would have minimal impact on the layout of the Hypothetical Car Park. While Mr Chain tried to persuade me to disregard the discount of 15% put forward by Mr Poon in this regard as off the cuff, Mr Ng’s defence is unbelievable by looking at the congested layout proposed by him[34]. Indeed, the fact that the Temporary Carpark could accommodate 29 car parking space instead of 20 demonstrates that the right of way under Special Condition 23 and the 2 metres clearance requirement did have the adverse impact on limiting the number of car parking spaces that could be provided in the TOA.

81.  By Special Condition 57 however, giving the benefit of doubt in favour of the applicant, I take that the 20 numbers of carparking spaces within the TOA can be increased by 5% to 21. Thus, the open market rent of the TOA assuming that it could have been used as a fee-paying public carpark as the comparables would be: $4,130 per month x 21 x 1.5 = $130,095 per month, say $130,000 per month as at 26 February 2014.

82.  In this connection, I consider the methodology of capitalization adopted by Mr Poon on behalf of the respondent is correct and should be followed because the payment of compensation should be assessed on the first day of the creation of the TOA (ie 26 February 2014) and be paid in one go. Indeed, the Tribunal in Ease Gold Development Ltd, supra, stated at §23 of the judgment that: “If the rent for three years is to be paid in one lump sum, the Present Value of the rent above for the second and third year at the appropriate respective prime bank rates for time deposit at similar amount and duration should be ascertained.”  

83.  And in in Discreet Limited, supra, the capitalization rate of 1.5% was adopted when the date of creation of the rights of temporary occupation was 27 October 2001. At that time, the time deposit rate was reduced from 1.33% or higher to 0.58% in October 2001:

MonthTime and savings deposit rates on deposits of less than HK$ 100,000 (Percent for annum (%))Best Lending Rate (Percent for annum (%))
1 week1 month3 months6 months12 monthsSavings deposit rate
Jul 20012.012.292.292.342.561.976.77
Aug 20011.92.092.092.172.341.886.69
Sept 20011.361.591.581.631.731.336.3
Oct 20010.510.870.870.871.020.585.55
Whole of 20012.12.362.362.392.532.167

* Hong Kong Dollar interest rates from the Census and Statistics Department.

84.  Similarly, in Tang Moon Kau v Secretary for Environment, Transport and Works [2008] 1 HKLRD 10 at §40, the valuation expert then opined that his estimated annual open market rent of $2,000 was capitalized for a rounding up period of 5 years at a rate of 5% the latter of which was based on “the prevailing interest rate for time deposits for capital of less than $100,000 for a fixed period of 12 months, as at May 1999” i.e. 5.59%, according to the Hong Kong Monthly Digest of Statistics.

85.  Taking into account the above and the time deposit rate was just 0.01% in 2014, I assess the total loss of rent from 26 February 2014 to 26 April 2017 on the basis on fee-paying car park as follows:

Site Particulars 
Temporary Occupation Area (“TOA”):1,480m2
Relevant Period (26.2.2014 to 26.4.2017):3.164 years
Date of Valuation:26.2.2014
Compensation Assessment 
Open Market Rent 
$130,000 per month x 12$1,560,000
3.164 yearsx3.164
$4,935,840

86.  On the other hand, I must comment that the methodology initially adopted by Mr Ng was wrong because the rental payable for the STT comparables from which he derived the open market rent would prevail for at least 3 years according to Government policy and this information should be well-known by the carpark operators. It was wrong for Mr Ng to assume the rental payable for the STT comparables would be re-assessed or re-determined after 1 year of the tenancies when he was comparing like-with-like. In Discreet Limited, supra, the Tribunal made the following remark at §30 of the judgment:

“We do think that expert surveyors should pay more attention to this issue of the correct valuation date from the beginning to avoid the need to make amendments both before and during a hearing for compensation claims. As pointed out by counsel for the Respondent, the date of valuation is clearly set down under s.12 (Date of valuation and interest) of Part 1 of the Schedule to the Ordinance. If an expert surveyor has any problem in confirming the relevant date of valuation, he should be prepared, subject to taking instruction from his client, to consult his client’s lawyer. This would obviously simplify the differences in computations between the parties and alleviate the tasks of the Tribunal in understanding their different figures in their series of valuation reports produced.”

87.  Mr Ng has corrected his methodology when Mr Chain submitted his closing submission on 8 April 2021.

Hotel or Cultural, Leisure and Tourist-Related Activities

88.  Mr Poon opined that the car parks on the TOA must be ancillary to the Hotel for use only by its owners, occupiers and bona fide visitors under the Government Lease, but not for the public through fee payment like the STT Comparables.

89.  Mr Chain submitted otherwise, referring to Special Condition 3(b) which permits the TOA to be used for purposes in relation to cultural, leisure and tourist-related activities. In that regard, Mr Chain is referring to the Oil Street Art Space run by the Leisure, Cultural Services Department at the junction of Oil Street and Electric Road opposite AIA Tower, Ngo Wong Temple (岳王古廟), and even the North Point Alliance Church at 238 King’s Road near its junction with Oil Street. He submits therefore the TOA could be used in relation to such cultural, leisure and tourist-related activities, as a result of which the TOA can be comparable to a public fee-paying carpark.

90.  To this I cannot agree. If Mr Chain’s argument is correct, anyone going elsewhere could park his/her car at the TOA. In Fully Profit (Asia) Limited v Secretary for Justice (2013) 16 HKCFAR 351, the Court of Final Appeal ruled at §15 of the judgment that when construing contractual terms, it was not particularly helpful in most cases to refer to the “ordinary and natural meaning” of words because there could often be much debate over exactly what was the ordinary or natural meaning of words. The surer guide to interpretation is context which is a key and starting point (together with purpose).

91.  The purpose of Special Condition 3 as a whole was to restrict user of the Lot. Reading in context, the clause “not be used for any purpose other than for non-industrial (excluding private residential, office, hotel, petrol filling station and godown) purposed in relation to cultural, leisure and tourist-related activities” must mean the non-industrial purposes conducted within the Lot but not elsewhere.

92.  Referring to Moody’s Investors Service Hong Kong Ltd v Securities and Futures Commission[2018] HKCFA 42 at §35, Mr Chain submitted that “relating to” or in the present case “in relation to” should have “the widest possible meaning of any expression intended to convey some connection … between the two subject matters to which the words refer”. But with respect, Mr Chain had not noted that Lord Neuberger continued his judgment at §37 as follows:

“While the phrase “relating to” has a naturally wide meaning, like any word or set of words it must, in any particular case, take its meaning from its contest …”

This principle is no different from that pronounced in Fully Profit.

93.  In his closing submission, Mr Chain also referred to Sam Woo Marine Works Ltd v The Incorporated Owners of Po Hang Building [2020] HKLdt 56 (24 December 2020) where Deputy District Judge Michelle Soong listed out the general rule as stated in Lewison on Interpretation of Contracts, para 5.03, for the consideration of implying a term as follows:

(a) Reasonable and equitable;

(b) Necessary to give business efficacy to the contract, so no term will be implied if the contract is effective without it;

(c) So obvious that “it goes without saying”, the so-called “officious bystander” test;

(d) Capable of clear expression; and

(e) Does not contradict any express term of the contract.”

94.  Mr Chain submitted that at least (b), (c) and (e) above had not been satisfied by interpreting Special Condition 3(b) as requiring the non-industrial purposes to be conducted within the Lot. I hold otherwise.

95.  That notwithstanding, I consider the provision of carparking next to a hotel especially a luxury 5-star hotel as claimed by the applicant is important. In Inland Revenue Commissioners v Clay [1914] 3 KB 466 at §475, Swinfen Eday LJ stated as follows:

“… It scarcely needed evidence to inform us - it is common knowledge - that when the fact becomes known that one probable buyer desires to obtain any property, that raises the general price or value of the thing in the market. Not only is the probable buyer a competitor in the market, but other persons, such as property brokers, compete in the market for what they know another person wants, with a view to a resale to him at an enhanced price, so as to realize a profit. A vendor desiring to realize any land would ordinarily give full publicity to all facts within his knowledge likely to enhance the price. The local conditions and requirements, the advantages of the situation of the property for any particular purpose, and the names of the persons who are probable buyers, would ordinarily be matters of local knowledge to the property brokers and agents and speculators. In order to arrive at the amount which land might be "expected to realise," all these matters ought to be taken into consideration. "Expected" refers to the expectations of properly qualified persons who have taken pains to inform themselves of all the particulars ascertainable about the property, and its capabilities, the demand for it, and the likely buyers. The price actually realized by a sale is not necessarily the price which it might have been expected to realize, but if the valuer be competent, and has taken proper pains in the matter, there ought to be little difference between the two figures. The fact that No. 83 had a potential value, by reason of its proximity to the nurses' home, and the very rapid increase of the work of that institution, pointing to a necessary extension at an early date, ought properly to be taken into consideration in arriving at the value it might be expected to realize. …” (emphasis added)

96.  Indeed, Scrutton J said in the lower court:

“He” (the referee) “was right in this, not because of the sale for 1000l., but because of the reasonable expectation that a willing seller could get 1000l. or more from the nurses' home” which owned the neighbouring house and needed further accommodation near, No 83 was so adjacent and offered such suitable accommodation that it would be advantageous to them to pay at least 1000l., probably more, for it.”

97.  I consider likewise, the applicant as the hotel operator would bid for the TOA at least equal to the open market rent payable for a public fee-paying carpark. Indeed, in her closing submission, at §30, Ms Cheng stated as follows:

“In any event, even leaving the Lease restrictions aside, it is more likely than not the Hotel would, as a matter of practicality, have to reserve at least a portion of the carparking spaces for its guests and patrons …”

Item 13 of Part I of the Schedule to the Ordinance

98.  As stated at §9 above, the car parking spaces were relocated elsewhere within the same Lot during the Relevant Period. More importantly, according to the layout as shown on the drawing no CWBIECL/027-009, this Temporary Carpark could accommodate 29 car parking spaces (including 9 lorry car parking spaces that were not provided in the TOA) instead of the original 20[35].

99.  Item 13 of Part I of the Schedule to the Ordinance provides as follows:

“No double compensation

Nothing in this Ordinance shall enable any person to recover compensation—

(a) in respect of a loss or expense which he has not suffered or incurred; or

(b) which is greater than the loss suffered or expense incurred by him:

Provided that in assessing compensation under this Ordinance, no account shall be taken of any amount recovered by the claimant under a policy of insurance.”

100.  Mr Chain submitted that in the present proceedings there are two heads of compensation under item 2 of Part II of the Schedule to the Ordinance:

(a)(ii) the amount of an open market rent for claimant’s interest in the land occupied during the period of the easement.

(b)    a disturbance payment.

101.  Mr Chain submitted that the amount of compensation for disturbance under item 2(b) was agreed but the loss suffered by the applicant which was still pending to be determined was the loss of use of the TOA during the Relevant Period. However, when the car parking spaces were relocated sideway with even more number of carparking spaces (including 9 lorry car parking spaces that were not provided in the TOA), was there any loss of use of the car parking spaces?

102.  Mr Chain submitted that Item 13 of Part I of the Schedule to the Ordinance would only bar the applicant from recovering, as a hypothetical example, purported rent of “alternative accommodation” of ancillary car parking spaces under the guise of disturbance claims. Mr Chain put forward the following arguments:

(i) Clearly, the applicant was able to satisfy its business requirement by relocating the ancillary car parking spaces to the northern portion of the Lot without renting another piece of land.

(ii) Therefore, this claim – which the applicant has never made – would have been impermissible “double compensation”. This claim would be for losses the applicant “has not suffered” (as it needs not pay additional rent for the relocated car parking space on the Lot), or alternatively is a claim “greater than the loss suffered by him” (as the applicant’s disturbance losses which were settled were limited to additional costs of setting up and maintenance of the relocated ancillary car parking spaces.

(iii) However, this has nothing to do with the value of the applicant’s loss of use and possession over the TOA, which is specifically provided for by the Ordinance to be assessed by reference to the open market rent.

103.  With respect, notwithstanding Mr Chain’s skillful arguments, I am not persuaded. Item 2(a)(ii) of Part II of the Schedule to the Ordinance only specifies the basis on which compensation is to be assessed, which in the case of creation of a right of temporary occupation under section 15 is the open market rent. It does not say that open market rent must be paid as a matter of compensation. For the purpose of illustration, I gave an example on 15 April 2021 that in case the Government compulsorily expropriates a land from somebody but provides him with a similar piece of land next to it, does this somebody suffer any loss apart from disturbance?

104.  Coming back to the present case, there had been no evidence before me that prior to the creation of a right of temporary occupation and then the relocation of the car parking spaces to the Temporary Carpark, that land which had become the Temporary Carpark during the Relevant Period had any beneficial use to the applicant. I consider the applicant having suffered no loss by having the car parking spaces relocated to land from which it could derive no beneficial use.

105.  But if I am wrong, and for any reason Item 13 of Part I of the Schedule to the Ordinance is not applicable, I would have ordered the respondent be pay the applicant in the sum of $4,935,840 for the temporary occupation of TOA during the Relevant period.

Orders

106.  Accordingly, I order that nil compensation be paid to the applicant by the respondent for the temporary occupation of TOA during the Relevant period because of Item 13 of Part I of the Schedule to the Ordinance which is provided to avoid double compensation.

107.  The matters of professional fees, interest and costs are adjourned to a date to be fixed.

 Lawrence Pang
 Member
 Lands Tribunal

Mr Christopher Chain and Mr Brian Fan, instructed by Messrs Woo Kwan Lee & Lo, for the Applicant

Ms Bonnie Y.K. Cheng, instructed by the Department of Justice, for the Respondent



[1]   See Bundle A1/14.

[2]   See the drawing no CWBIECL/027-009 at Bundle B/493.

[3]   See Bundle A1/18 &19.

[4]   See Bundle A2/257.

[5]   See Bundle A2/321.

[6]   Mr Ng assumed an 8.4% increase in rental each year during the Relevant Period.

[7]   Ditto.

[8]   Ditto.

[9]   See §§37 & 38 of the judgment.

[10]   See Bundle A2/251 & 321.

[11]   See Bundle A2/220.

[12]   See Bundle A2/310.

[13]   See Bundle A1/205 & 206.

[14]   See Bundle A2/300.

[15]   See Bundle A2/311.

[16]   See Bundle A2/313.

[17]   I do not agree with Mr Poon that the TOA being opposite to B1 which was the construction site for a residential development, Harbour Glory, during the Relevant Period would be adversely affected while I am given to understand that the Hotel was in operation

[18]   See §§76 & 77 of the judgment.

[19]   The cost of running an open carpark should be independent of location.

[20]   See Mr Ng’s analysis at Bundle A1/204 or Bundle A2/321.

[21]   See Bundle A2/264.

[22]   See Bundle A2/317.

[23]   The Lot is known as Section A of Inland Lot No 7106 and Extension thereto.

[24]   See Bundle A2/219.

[25]   See Bundle A2/268.

[26]   See Mr Ng’s hypothetical layout of carparks at Bundle A2/278 & 279.

[27]   See Mr Ng’s hypothetical layout of carparks at Bundle A2/280 & 281.

[28]   See Mr Ng’s hypothetical layout of carparks at Bundle A2/282 & 283.

[29]   See Bundle A1/206 and the revision at the Annex of Mr Chain’s closing submission.

[30]   See Bundle A2/219.

[31]   See Bundle A2/296.

[32]   In Golf Café Bars Limited v West Yorkshire Combined Authority & Another

[2021] UKUT 0016 (LC) at §23, “The acquiring authority disputed the validity of this as a head of claim (for Compensation for temporary possession) on the grounds that the use did not have planning permission, it was in breach of the user covenants of the long lease, and that such breach had not been regularised by landlord’s consent. Ms Noble submitted that if a claimant in a permanent acquisition situation is prevented by section 5 of the 1961 Act from recovering compensation generated by illegal or unlawful uses, equally it cannot do so in a claim for temporary possession. The authority’s principal position was therefore that this element of the claim should be assessed at zero.” 

[33]   See para 7 above.

[34]   See Bundle A2/268.

[35]   See Bundle B/493.