HK CourtDB
HomeDirectoryMCP
Hong Kong CourtDB
Back to directory
2018

KING POLICY DEVELOPMENT LTD v. WAN KIN SHING

Related cases with same parties

  • HCA354/2015WAN KIN SHING v. THE INCORPORATED OWNERS OF CITY CENTRE BUILDING AND OTHERS
  • HCA696/2015KING POLICY DEVELOPMENT LTD v. WAN KIN SHING
  • HCAL1657/2020WAN KIN SHING v. KING POLICY DEVELOPMENT LTD

Files (3)

[2020] HKCA 738-EN-2020-09-02

KING POLICY DEVELOPMENT LTD v. WAN KIN SHING

HTML content

CACV 107/2018

[2020] HKCA 738

IN THE HIGH COURT OF THE

HONG KONG SPECIAL ADMINISTRATIVE REGION

COURT OF APPEAL

CIVIL APPEAL NO 107 OF 2018

(ON APPEAL FROM HCA 696/2015)

________________________

BETWEEN  
 KING POLICY DEVELOPMENT LIMITEDPlaintiff
 and
 WAN KIN SHINGDefendant

________________________

Before:Hon Lam VP, Yuen and Chu JJA in Court
Date of written submissions:10, 23 and 30 July 2020
Date of Judgment:2 September 2020

________________________

JUDGMENT

________________________

Hon Chu JA giving the judgment of the Court:

Introduction

1.  On 5 June 2020, this Court handed down our judgment [1]dismissing the defendant’s appeal against the judgment of Chung J (“the Judge”) given on 29 March 2018[2]. By the judgment, the Judge granted two injunctions in favour of the plaintiff against the defendant, and dismissed the defendant’s counterclaim with costs to the plaintiff. 

2.  On 26 June 2020, the defendant filed a notice of motion to apply for leave to appeal our judgment to the Court of Final Appeal.

3.  Pursuant to the directions of the Registrar of Civil Appeals, the parties have put in their written submissions and authorities.

4.  Having considered the papers and the written submissions, we see no reason to depart from the usual practice of determining applications for leave to appeal to the Court of Final Appeal on paper without an oral hearing, and have therefore proceeded to determine the applicant’s application on the basis of the documents in the case.

5.  The facts and issues in the case below and in the appeal before the Court of Appeal have been set out in our judgment.  We will not repeat them.

Requirement for granting leave to appeal

6.  Under section 22(1)(b) of the Hong Kong Court of Final Appeal Ordinance, Cap. 484, leave to appeal to the Court of Final Appeal may be granted if the question involved in the appeal is one which, by reason of its great general or public importance, or otherwise, ought to be submitted to the Court of Final Appeal for decision.

Grounds for the application

7.  The notice of motion set out six proposed grounds of appeal.  The defendant’s two written submissions, the first in support of the application and the other in reply to the plaintiff’s submission (respectively “Main Submission” and “Reply Submission”), however, contained 13 questions.  The contents of the three documents are rather difficult to understand, and the 13 questions in the written submission do not correspond to the grounds in the notice of motion.  Doing the best we can, the defendant’s proposed grounds of appeal are summarized as follows:

(1) Ground 1 of the notice of motion, Questions 1 to 5, 8 and 9 in the Main Submission and Questions 10 to 12 in the Reply Submission

The plaintiff’s causes of action are breach of the consent order dated 24 June 2015 (“Consent Order”) and trespass.   The plaintiff’s solicitor misrepresented to the court that the defendant was in breach of his undertaking under the Consent Order, when the works complained of were carried out by the Water Supplies Department. As the defendant had honoured his undertaking, the plaintiff is estopped by the Consent Order from seeking injunctions against the defendant.

(2) Ground 2 of the notice of motion and Question 6 and 7 in the Main Submission

It is an abuse of legal process for the plaintiff to commence the action below (HCA 696/2015), which overlaps with the defendant’s claim for adverse possession in HCA 354/2015, and results in procedural unfairness to the defendant in the conduct of his case.  The Court of Appeal erred in not ordering the two actions to be heard together.

(3) Ground 3 of the notice of motion

The defendant has constitutional rights by reason of his payment of government rates for his shop since 1991, which indicates his shop is a separate tenement, his being in actual occupation, which gives him title to the land, and the appurtenant rights stated in the Confirmatory Assignment and Confirmatory Reassignment.

(4) Ground 4 of the notice of motion and Question 13 in the Reply Submission

This case raises questions of public interest and importance, namely, (i) is there restriction to the administration, execution and implementation of the Water Works Ordinance, Cap. 102 during the execution of the Consent Order on an open lane; (ii) can an owner of a service lane reject works carried out by the Water Supplies Department for water connection and safety measures to other lots when a common water system was situated underneath his land; (iii) can the defendant’s constitutional rights over his separate tenement be nullified when he has been paying rates continuously; and (iv) the plaintiff’s solicitor was guilty of contempt of court for making a misrepresentation in the trial bundles.

(5) Ground 5 of the notice of motion

It is not worthwhile to incur over HK$ 2 million of government revenue to re-route the pipe for supply of water to the defendant’s shop.

(6) Ground 6 of the notice of motion

The Court of Appeal initially accepted the defendant’s argument on the Water Works Ordinance and the easement defence as valid, but took a different view at the adjourned hearing and held that the easement defence was not pleaded.  However, there is no need to plead any fact if it is presumed by law

(respectively “Ground 1” to “Ground 6”). 

Ground 1

8.  The thrust of the defendant’s arguments under Ground 1 is that by agreeing to the Consent Order, which was made following negotiations between the parties, the plaintiff was happy with only claiming damages, and had waived its right to claim injunctions against the defendant.  However, the plaintiff wrongfully claimed in its solicitors’ letter dated 13 August 2015 and also at the trial that the defendant had breached his undertaking given under the Consent Order when the works complained of were carried out by the Water Supplies Department.  The plaintiff’s solicitors further misled the court by including the 13 August 2015 letter in the trial bundles[3]. The court should have found that, as the defendant has honoured his undertaking under the Consent Order, the plaintiff is estopped from claiming injunctions against the defendant.

9.  For the reasons set out below, this is not a viable ground for granting leave to appeal to the Court of Final Appeal.

10.  In the first place, it is a new argument that was not raised at the trial or in the appeal before us.  The plaintiff’s agreement to the terms of the Consent Order did not form part of the plaintiff’s course of conduct that the defendant relied on for his pleaded case of estoppel.  The defendant’s case of estoppel at the trial was based on the 2006 Agreement, the 2007 Agreement and the March 2015 encounters.[4]  His challenge to the Judge’s rejection of the defence of estoppel in the appeal was also confined to these aspects[5]. It is not the practice of the Court of Appeal to grant leave to appeal on new points that were not canvassed in the hearing before it.[6] Nor is it the practice of the Court of Final Appeal to grant leave on new fact-sensitive points not argued in the Court of Appeal.[7]  

11.  Secondly, this ground relates solely to the circumstances of the case, and does not involve any question of great general or public importance. 

12.  Thirdly, this ground is unarguable.  The Consent Order was made upon the joint application of the plaintiff and the defendant, who were both legally represented, by way of a consent summons dated 23 June 2015 (“the Consent Summons”).  The Consent Summons and the Consent Order were in respect of the plaintiff’s summons filed on 30 March 2015 (“the Plaintiff’s Summons”), in which the plaintiff applied for two interlocutory injunctions against the defendant. 

13.  The Consent Order has three features.  First, it contained an undertaking given by the defendant to the Court that (1) he would not, whether by himself or his servants or agents or any of them or otherwise howsoever, continue or carry out excavating work and connect or install water pipes at the lane[8]; and (2) he would refill and reinstate the lane.  Second, in consequence of the undertaking, it was not necessary to adjudicate on the Plaintiff’s Summons, and the Court made no order on it.  There was no refusal by the court, or abandonment by the plaintiff, of the injunctive relief sought in the Plaintiff’s Summons. Third, the Plaintiff’s Summons only sought interlocutory, not permanent, injunctions against the defendant.  The undertaking given by the defendant was also expressly stated to be pending and until the final determination of the action below.  Neither the undertaking nor the Consent Order has the effect of finally disposing of the plaintiff’s claim for injunctions.     

14.  The effect of the Consent Order is that pending trial of the plaintiff’s claim, the defendant agreed not to carry out excavation and water pipe connection or installation works and also to reinstate the lane, and because of this, the Plaintiff’s Summons was not adjudicated upon and no injunctions were made.  The Consent Order was to maintain the status quo of the parties before the trial and determination of the dispute between them.  Contrary to the defendant’s contentions, in agreeing to the Consent Order, the plaintiff did not give up its right to seek injunctions against the defendant or confine its claim to seeking damages.  The Consent Order does not have the effect of barring the plaintiff from seeking or obtaining at the trial injunctive reliefs against the defendant. 

15.  It follows that it is immaterial whether the connection of the water pipes was carried out by the Water Supplies Department and whether the defendant had complied with the undertaking given in the Consent Order.  It is incorrect for the defendant to contend that breach of the Consent Order is one of the plaintiff’s causes of action.  We have also held in [24] of our judgment that there are no merits in the complaint of misrepresentation against the plaintiff’s solicitors over the hearing bundles. The defendant’s latest assertion that the plaintiff’s solicitors had committed contempt of court is unarguable.

Ground 2

16.  Ground 2 complains that the plaintiff’s action (HCA 696/2015) overlaps with the defendant’s action (HCA 354/2015), amounting to an abuse of legal process and further results in procedural unfairness in that it has restricted the way the defendant conducted his case in the action below.  It is said that we should have ordered the plaintiff’s claim for injunctions in the action below to be heard together with the defendant’s claim for adverse possession. 

17.  This ground is unarguable.  The plaintiff has pointed out that the area where the defendant carried out the excavation works complained of in the action below was outside the area claimed in the defendant’s action.   More importantly, the defendant had never argued before the Judge or this Court that the plaintiff was not entitled to bring the action below or that he somehow suffered prejudice in the conduct of his case. Further, the defendant could have, before the trial of the action below, applied to have the two actions heard together, but he had never sought to do so.  It is now far too late to complain.  The complaint that this Court should have ordered the two actions to be heard together is misplaced. 

18.  Moreover, this ground only relates to the circumstances of the case, and does not involve any question of great general or public importance.

Ground 3

19.  Ground 3 argues that the defendant has constitutional rights by reason of the fact that he has paid rates for his shop since 1991 which indicates his shop is a separate tenement, he has been occupying his shop, which gives him title to the land, and his appurtenant rights as stated in the Confirmatory Assignment and Confirmatory Reassignment.

20.  As with the arguments under Grounds 1 and 2, the issues that the defendant has been paying government rates for his shop as well as the relevance of the payment of government rates to, and its impact (if any) on, the entitlement to install water pipes at the lane are new issues not raised at the trial or in the appeal.  If the defendant wished to rely on payment of rates as the basis for his right to lay water pipes at the lane, he would firstly have to properly raise it on the pleading, which he had not done.  In the absence of proper pleading, even if the defendant wished to argue the issues at the trial or the appeal, he would not be allowed to do so.  As pointed out in [10] above, it is not open to the defendant to raise new arguments in the application for leave to appeal. 

21.  In respect of the Confirmatory Assignment and Confirmatory Reassignment, they provide for a right of way which only entitles the defendant to go pass and repass the lane[9].  As to the claim for adverse possession based on the occupation of part of the lane by the defendant’ shop, although the defendant had referred to it in the pleading[10], he had not sought to establish the claim in the action below or claim relief based on it. In any event, these issues are case specific and do not involve any question of great general or public importance.

22.  Ground 3 therefore does not afford a proper basis for granting leave to appeal.    

Ground 4

23.  Under Ground 4, it is said that the intended appeal involves four questions of public interest and importance (see [7(4)] above). 

24.  For the reasons given under Grounds 1 to 3, the four questions either do not arise or are unarguable.  Further, they are all related to the facts and circumstances of the present case, and do not involve any question of great general or public importance.

Ground 5

25.  Ground 5 merely makes the point that it will take over HK$ 2 million of government revenue to re-route the pipe to provide water supply to the defendant’s shop. No question has been formulated or identified for determination by the Court of Final Appeal.  It is not a proper ground for giving leave to appeal. 

Ground 6

26.  Ground 6 suggests that this Court took different views on the defence of easement at the first and adjourned hearings of the appeal.  It also argues that under Order 18 rule 7(3) of the Rules of the High Court, Cap. 4A, the defendant did not have to plead any fact if it is presumed by law.  

27.  At [14] of our judgment, we had explained the reason and purpose of the adjournment of the appeal at the first hearing.  As mentioned in [15], before the appeal hearing resumed, transcript of the trial was added to the appeal bundles and the parties had put in supplemental submissions.  Having regard to trial counsel’s written submissions, the transcript of the trial and for the reasons and analyses we gave at [39] to [46] of our judgment, we concluded that the Judge was entitled to proceed and determine the case on the basis that the defendant had abandoned the defence of easement.  We further explained in [47] to [52] that the defendant had failed to advance a proper plea of easement by prescription and had chosen to run his case without relying on the plea at the trial such that it was too late to allow him to argue the issue in the appeal. 

28.  Order 18 rule 7(3), on which the defendant relies, provides that “A party need not plead any fact if it is presumed by law to be true or the burden of disproving it lies on the other party, unless the other party has specifically denied it in his pleading.”  The rule has no relevance to the present case and does not relieve the defendant of the obligation to plead a proper plea of easement by prescription.

29.  There is also no question of great general or public importance arising under this ground.

30.  For the above reasons, Ground 6 has no merits. 

“Or otherwise” limb

31.  Having considered the matters raised by the defendant and the circumstances of the case, we do not see any basis for granting leave under the “or otherwise” limb.

Conclusion and costs

32.  For the reasons set out above, we refuse to grant leave to appeal to the Court of Final Appeal and dismiss the notice of motion.

33.  Applying the usual rule of costs follow event, we make an order that the defendant pays the plaintiff the costs of this application.  We had considered the plaintiff’s statement of costs for summary assessment dated 23 July 2020.  We are of the view that the costs claimed are proper and reasonable.  We allow the full amount claimed and summarily assessed the plaintiff’s costs of this application at HK$ 38,024.

(M H Lam)
Vice President
(Maria Yuen)
Justice of Appeal
(Carlye Chu)
Justice of Appeal

  

Woo, Kwan, Lee & Lo for the Plaintiff

The Defendant, unrepresented, acted in person


[1][2020] HKCA 428.

[2][2018] HKCFI 690.

[3] Trial Bundle C1, pp.178-180; and Appeal Bundle B1, pp.449-451.

[4] The Judge’s judgment at [6], [7], [18] and [19].

[5] This Court’s judgment at [17] and [18].

[6]Ageas Insurance Co (Asia) Ltd v Lam Hau Wah Inneo, CACV 65/2014, unreported, 19 May 2015, at [7] to [9]; and The Law Society of Hong Kong v A Solicitor, CACV 78/2014, unreported, 10 July 2015, at [4] to [7].

[7]Flywin Co Ltd v Strong & Associates Ltd (2002) 5 HKCFAR 356 at [39].

[8] At the area coloured pink in the plan annexed to the Consent Order.

[9] As the Judge held at [2] and [25] of his judgment.

[10] Defence and Counterclaim at [15].

[2020] HKCA 428-EN-2020-06-05

KING POLICY DEVELOPMENT LTD v. WAN KIN SHING

HTML content

CACV 107/2018

[2020] HKCA 428

IN THE HIGH COURT OF THE

HONG KONG SPECIAL ADMINISTRATIVE REGION

COURT OF APPEAL

CIVIL APPEAL NO 107 OF 2018

(ON APPEAL FROM HCA 696/2015)

________________________

BETWEEN  
 KING POLICY DEVELOPMENT LIMITEDPlaintiff
 and
 WAN KIN SHINGDefendant

________________________

Before:Hon Lam VP, Yuen and Chu JJA in Court
Date of Hearing:18 September 2019 and 26 May 2020
Date of Judgment:5 June 2020

________________________

JUDGMENT

________________________

The Court:

Introduction

1.  This is the defendant’s appeal from the judgment (“the Judgment”) of Chung J (“the Judge”) given on 29 March 2018 entering judgment for the plaintiff and dismissing the defendant’s counterclaim with costs to the plaintiff [1].  The Judge granted two injunctions in favour of the plaintiff.  The first injunction restrains the defendant from (i) excavating and/or carrying out any construction work on the plaintiff’s land; (ii) connecting and/or constructing any pipe or drain on or underneath the plaintiff’s land and/or running any pipe or drain from or through the plaintiff’s land; and (iii) placing, keeping or leaving any items, articles or chattel on the plaintiff’s land.  The second injunction compels the defendant to take steps to (i) disconnect and remove any pipe, drain and other items, articles or chattels which were connected, installed and/or placed by the defendant on and/or underneath the plaintiff’s land; and (ii) reinstate the part of the plaintiff’s land that has been dug, excavated and/or damaged by the defendant. 

The background

2.  The plaintiff is the registered owner of a multi-storey building known as “Century Court”, which is located at the junction of Stewart Road and Jaffe Road, Wanchai.  The building next to it on Stewart Road is “City Centre Building” which is a residential building (“City Centre”).  Located between the two buildings is a scavenging lane (“the lane”).  Part of the lane lies within land owned by the plaintiff and part of it lies within land owned by the registered owner of City Centre.   It is not disputed that there is a right of way over the lane whereby people can go pass and repass along it.

3.  There exists a structure at the lane built along the exterior wall of City Centre and the defendant operates a shop there (“the defendant’s shop”). The defendant claims adverse possessory title over the part of the lane occupied by the defendant’s shop. In High Court Action 354 of 2015, the defendant (as plaintiff in the action) sued the plaintiff and the owner of City Centre (as defendants in the action) for declaratory relief to that effect.  There is a dispute over whether the defendant’s shop occupies any part of the plaintiff’s land. That action has yet to come to trial.

4.  On or about 16 March 2015, the defendant, without any consent or permission of the plaintiff, caused some excavation works to be carried outfor the purpose of installing a fresh water pipe to serve the defendant’s shop. The paved surface of part of the lane within the plaintiff’s land was dug up.  The plaintiff demanded the defendant to cease the excavation works and to reinstate the excavated area, but the defendant did not comply with the demand.

5.  On 30 March 2015, the plaintiff commenced this action seeking injunctive relief against the defendant to restrain him from carrying out any excavation and construction works at the lane for installing water pipes connecting the defendant’s shop and to compel him to reinstate the piping and the excavated part of the lane.  

6.  It is the defendant’s case that, by its nature, the lane is not exclusively for the use of the plaintiff or the Incorporated Owners of City Centre, and that a right of way exists for other people to pass and repass along the lane.  The defendant also claims to have carried out excavation works on the lane for similar purposes in or about 1991, 2002 and 2013 without seeking the prior consent or approval of the plaintiff, and the plaintiff did not object to it[2]. 

7.  The defendant further relies on:

(a)     an agreement reached in May 2006 among (i) the parties to this action; (ii) the owners of City Centre and (iii) the Buildings Department, which provided for a right to use the lane for the maintenance and servicing of Century Court, City Centre and the defendant’s shop (“the 2006 Agreement”); and

(b)     an agreement reached in July 2007 among the same parties, which provided that in return for the defendant reducing the coverage of the canopy of the defendant’s shop:

(i)     the Buildings Department would withdraw the Building Order dated 25 August 2005 against City Centre for the demolition of the defendant’s shop and

(ii)     one meter between the coverage of the defendant’s shop and the external wall of Century Court could be used by the parties and the owners of City Centre for the maintenance of, and provision of public utilities to, their respective properties (“the 2007 Agreement”)[3].

8.  The defendant further claims that on 16 to 18 March 2015 he had several encounters (collectively “the March 2015 encounters”) with people “connected to” Century Court, whom he believed were authorized to represent the plaintiff regarding the excavation and installation works carried out on the lane.  The defendant says that, in reliance on the plaintiff’s representations and conditions conveyed through these people, he carried out and continued the excavation works at the lane. 

The judgment below

9.  In the Court below, the defendant sought to rely on two lines of defence:

(a)     Estoppel, including proprietary estoppel, promissory estoppel or estoppel by convention; and

(b)     Easement.

10.  At the trial, the Judge regarded the main issue to be whether the parties had reached any agreement concerning the defendant’s entitlement to carry out the disputed excavation and installation works.  As there was no written record or document to evidence the alleged 2006 and 2007 Agreements, the Judge resolved the issue by assessment of the witnesses’ testimonies given during the trial. 

11.  The Judge found the plaintiff’s witnesses truthful and reliable and rejected the 2006 and 2007 Agreements as inherently implausible.  According to the defendant, the issue that led to the meeting in May 2006 was a canopy erected by the defendant that protruded from the defendant’s shop towards the external wall of Century Court; and the Buildings Department was involved because of a complaint lodged by Century Court.  The Judge found that the plaintiff’s witness Mr. Liu, the estate assistant of the management company engaged by Century Court, who was present in the 2006 meeting, had no authority to make any commitment concerning a property right on behalf of the plaintiff.  The Judge also found there was no valid basis, legal or otherwise, on which the Buildings Department could have conferred legal title or any land interest on any individual, and it was highly unlikely for a government department like the Buildings Department to be a party to an agreement dealing with the rights and interests of privately held land lots. For similar reasons, the judge reached the same conclusions as regard the 2007 Agreement.

12.  Regarding the March 2015 encounters, the Judge found that the people who met with the defendant at the lane were merely responsible for the daily maintenance of Century Court.  They asked the police to intervene as they considered the defendant’s acts illegal and objectionable.  Soon after the encounters, the plaintiff commenced this action. In these circumstances, the Judge considered, it was far-fetched to suggest that the March 2015 encounters could give rise to any kind of estoppel.

13.  On the totality of the evidence, the Judge found against the existence of the 2006 and/or 2007 Agreements.  The Judge also did not find any basis for estoppel of any kind to arise. The Judge granted the injunctive relief sought by the plaintiff and dismissed the defendant’s counterclaim.

The appeal

14.  At the first hearing on 18 September 2019, the appeal was adjourned part-heard due to the submission of Mr Lin, who appeared for the plaintiff, that the defence based on easement had been disallowed by the Judge due to the state of the pleadings.  To make good the submission, Mr Lin requested for an adjournment to enable the plaintiff to obtain the transcript of the trial. Counsel also indicated that he would advance a legal submission that the plea of easement cannot be advanced by a squatter as a matter of law since the doctrine of lost modern grant is not applicable.

15.  The plaintiff subsequently obtained the transcript of the trial and added it to the appeal bundle.  Supplemental submissions were also lodged by both parties.  The hearing of the appeal resumed on 26 May 2020. 

Grounds of appeal

16.  The Re-Amended Notice of Appeal filed on 18 December 2018 contains 33 pages and the content is more in the nature of a submission instead of setting out the grounds of appeal in a concise and succinct manner. Such a document is unhelpful to the proper and fair disposal of an appeal, see: Chow How Yeen Margaret v Wex Pharmaceuticals Inc [2018] 3 HKLRD 163 at [13]. 

17.  Having regard to the Re-Amended Notice of Appeal and the defendant’s submissions, the grounds advanced by the defendant can be summarized as follows:

(1)     The Judge overlooked the approval letter of the Water Supplies Department (“WSD”), and erred in finding the defendant did not complete his excavation works by 18 March 2015 when what was required of him was only to expose the main water pipe.  The Judge also erred in his findings at [29] to [31] of the Judgment due to his failure to understand water installation practice. 

(2)     The Judge misunderstood and overlooked the evidence that (i) part of the lane has been occupied by the defendant’s shop for over 60 years and the defendant is currently claiming adverse possession of the same in HCA 354/2015, and excavation works had been carried out in the past for the installation and maintenance of utilities services; and (ii) the 2006 Agreement was supported by documents, meeting records and communication and exchanges with the Buildings Department.

(3)     The Judge neglected the evidence of Ho Kin who gave evidence at the trial. The defendant also complained that his trial counsel failed to conduct sufficient cross-examination of the plaintiff’s witnesses.  

(4)     The Judge failed to pay proper regard to “the timing and responses of events” concerning the excavation works from 16 to 18 March 2015 in the analysis of the defence of promissory estoppel.

Discussion

(A)     Estoppel

18.  Grounds (3) and (4), as well as (2)(ii), relate to the defence based on estoppel.  They can be addressed together since they are all directed at the Judge’s findings against the defendant in respect of representations alleged to have been made on behalf of the plaintiff that underline the defence case on estoppel.  The Judge found, in a nutshell, there were no 2006 and 2007 Agreements.

19.  As regard the March 2015 encounters, the Judge held at [20] of the Judgment that the encounters, at the highest, only showed that the people responsible for the daily maintenance of the plaintiff’s building did not see a need to take imminent legal action, despite that they considered the defendant’s act to be unlawful or objectionable. The Judge concluded that the encounters could not give rise to any estoppel.   

20.  Ho Kin was the plaintiff’s witness.  He was an assistant property manager employed by the manager of the plaintiff’s building in 2015. His evidence[4] concerns what happened on 17 March 2015. To some extent, it overlaps with the evidence of Chan Kin Sang, another witness of the plaintiff.  Like Chan, Ho refuted the defendant’s suggestion that there was an agreement to allow him to continue with the excavation works.  As pointed out by the Judge, the manager made a complaint to the police about the defendant’s excavations, and police officers had attended the scene.  After hearing what the parties said, the police officers regarded the dispute was a civil matter and left it to the parties to resolve by legal proceedings. 

21.  We have reviewed the video and audio clips of the encounter on 17 March 2015[5]. There is nothing in them to support the defendant’s assertion that either Ho or Chan had promised to allow him to continue the excavations even though this involved works being done on the plaintiff’s land, as opposed to works on the other part of the lane.

22.  Hence, there is nothing in Ho’s evidence that can assist the defendant. The defendant’s arguments in the Re-amended Notice of Appeal are based on a misreading of Ho’s affirmation. Importantly, the Judge had referred to, and accepted, the evidence of Chan.  His omission to refer to Ho’s evidence does not materially affect the analysis of the defendant’s case on estoppel based on the 17 March 2015 encounter.

23.  As regard the cross-examination of witnesses, the defendant is bound by how his counsel conducted the trial.  In our judgment, there is no merit in the criticism that the defendant levelled against his trial counsel in the Re-amended Notice of Appeal, which were simply premised on the number of questions asked in cross-examination.  

24.  There is also no merit in the defendant’s attempts to implicate the plaintiff’s solicitors for misleading the court through the trial bundles. The defendant was legally represented at the trial. If there were anything misleading in the trial bundles, one would expect his lawyers to have pointed it out to the Judge.  No such complaint was made at the trial.  There is no evidence from the defendant’s former lawyers to account for the absence of such complaint.  In these circumstances, this Court cannot act on the defendant’s bare assertions, which were based on his impression of the arrangement of the trial bundles formed by reference to the state of the bundles returned to him.

25.  As to the evidence relating to the sequence of events between 16 and 18 March 2015, we have read them. We do not discern any incontrovertible evidence that can invalidate the Judge’s observations at [20] of the Judgment.

26.  In respect of the 2006 Agreement, the Judge’s reasoning in rejecting the defendant’s case is set out in [12] to [17] of the Judgment.  Having considered it against the defendant’s submissions and the evidence identified in his revised summary of 20 August 2019, we do not find any valid basis for faulting the reasoning.  We are not persuaded that the Judge had misunderstood or overlooked any material evidence in coming to his finding on the facts that there was no agreement reached in 2006 about the right of the defendant to use the lane.  The evidence identified by the defendant in his revised summary (apart from those assertions made by the defendant which the Judge was entitled to reject in assessing the evidence and the weight to be attached) is consistent with the Judge’s analysis.

27.  There is, in short, no palpable error on the part of the Judge, and the defendant has failed to show that the Judge is plainly wrong in his finding on the facts.  This being the case, there is no basis for this Court to disturb the Judge’s rejection of the 2006 and 2007 Agreements and his finding on the March 2015 encounters: see China Gold Finance Ltd v CIL Holdings Ltd CACV 11/2015, 27 November 2015; Hoptai Sharkfins Co Ltd v Productos Pesqueros Gallegos SL CACV 240/2014, 7 December 2015.

28.  It follows that the defendant fails in his challenge of the Judge’s rejection of the defence based on estoppel.

(B)      Easement

29.  As to the other grounds advanced by the defendant in this appeal, they may be seen as somehow related to his other line of defence based on easement. 

30.  In the Judgment, the Judge did not specifically address the issue of easement as his focus was solely on the defence of estoppel and the evidence associated with it.  In the section under the heading “Other Matters”, the Judge alluded to the defendant’s reference to the pre-2006 events, and rejected the evidence and the related legal argument as “too weak and/or ambiguous to properly ground any kind of estoppel”[6]. The Judge also rejected the defence case that the works were undertaken by the Waterworks Department[7] (sic).[8] With regard to the defendant’s plea in [104] of the counterclaim that he had acquired a right to arrange for the laying of underground water supply pipes to connect the water mains to the defendant’s shop, the Judge rejected it as “nothing more than a recent invention”[9].

31.  Mr Lin submits that the defendant should not be allowed to raise any ground of appeal on the basis of easement by prescription or based upon a lost modern grant as it has not been distinctly pleaded and the evidence adduced at the trial does not support it.  

32.  In the Defence and Counterclaim, after referring to the nature of the lane and averring in [12] that the occupiers of the other portions of Inland Lot 2756 “have a right to go pass and repass along [the lane]”, it avers in [18] that “by virtue of the Confirmatory Reassignment and Confirmatory Assignment, the defendant as owner of the Wall Shop, enjoys at least a right of way over [the plaintiff’s land]” (emphasis added).  This is an ambiguous plea because it is not clear whether it is contending that there are some additional rights over and above the right to go pass and repass the lane and, if so, what are the rights.

33.  At [20] to [22], it refers to past excavation works carried out in 1991, 2002 and 2013 by the defendant on the lane, for which no consent was sought from the plaintiff or any other person.  At the plaintiff’s request, the defendant had provided further and better particulars of these excavation works. The 1991 and 2013 excavations concerned the laying and maintenance of power cables for the supply of electricity to the defendant’s shop, and the 2002 excavation was for the maintenance of broken water pipe.  It is also averred that in 2002 and 2013, the plaintiff observed and took photos of the excavation works and did not raise objection to them.

34.  At [26] to [42], the Defence and Counterclaim pleads the 2006 and 2007 Agreements and the representations made at the 2006 and 2007 meetings.  At both [32] and [37], it is averred that the excavation works at the lane were necessary because the water mains and the electricity power cables for Inland Lot 2756 were laid underneath the lane.  At [39], it pleads that the plaintiff’s course of conduct gave rise to various estoppel (i.e. promissory estoppel, estoppel by convention and estoppel by representation). Then at [40], it avers that “Further, or in the alternative, the Plaintiff’s course of conduct gave rise to a proprietary estoppel in favour of the Defendant, and the Defendant thereby acquired an easement and/or proprietary right to lay underground water pipes and electricity power cables to connect the Wall Shop to the water supply pipes and electricity supply underneath the Service Lane.” (emphasis added)

35.  The pleading goes on to make averments to support the estoppel defence. At [43], reference is made to the approval given by the Water Supplies Department on 4 February 2015 for the installation of fresh water supply to the defendant’s shop.  Then at [44], which is related to Ground (1) in this appeal, the defendant makes the point that while the excavation works were arranged by the defendant (as required by the Water Supplies Department), the work of attaching a pipe to connect the water mains to the water meter of the defendant’s shop was to be undertaken by the Water Supplies Department or its contractor. This is reiterated at [52] of the Defence and Counterclaim.

36.  Between [54] and [96], the events that took place between 16 and 18 March 2015 are set out in great detail as if the pleading was a witness statement.  This culminates in averments in [97] of various estoppels. Then at [98], it avers in terms similar to [40] that “Further, or in the alternative, the Plaintiff’s course of conduct gave rise to a proprietary estoppel in favour of the Defendant, and the Defendant thereby acquired an easement and/or proprietary right to arrange for lay underground water pipes to connect the Wall Shop to the water supply pipes underneath the Service Lane …”  (emphasis added)

37.  The plea is further repeated in the Counterclaim at [104], which states that “By reason of the matters pleaded above, the Defendant has acquired a right to arrange for laying underground water supply pipes in the Service Lane to connect the Wall Shop to the water mains pipe … by way of proprietary estoppel.” (emphasis added)

38.  Looking at [40], [98] and [104] of the Defence and Counterclaim, it can be seen that what is pleaded is an easement or “proprietary right” to lay underground water pipes based on proprietary estoppel by virtue of the plaintiff’s course of conduct.

39.  However, what the defendant sought to advance at the trial is an easement based on prescription.  In his written opening submission at [43(1)],  the defendant’s trial counsel formulated the issue as “whether or not the defendant (as a squatter) has acquired an easement and/or proprietary right to lay underground water pipes and electricity underneath the Service Lane.”[10].  He outlined the arguments on prescriptive easement at [46] to [52] of the written submission, referring to passages in Chung Yeung Hung & Ors v Law Man Nga [1997] HKLRD 1022, at 1025I to 1026B and Jourdan and Radley-Gardner on Adverse Possession (2nd ed) at [23.21] at p. 497.[11]

40.  In opening the plaintiff’s case on the first day of the trial, Mr Lin referred to the defendant’s written opening submission and indicated that he would be taking the point that it was not open to the defendant to raise the defence of easement because it was not pleaded.[12]

41.  In the same afternoon at the start of the defence case, the defendant’s counsel applied to amend the Defence and Counterclaim by adding a few words to [18], [19] and [105], which counsel contended would remove any obscurity as to whether the issue of easement had been pleaded[13].  The amendments were opposed by Mr Lin primarily on the basis that the amendments were useless.[14] In the course of exchanges with counsel, the Judge remarked that the proposed amendments did not seem to him to make much difference.[15]  We have perused the proposed amendments.  They do not advance a case of easement by prescription based on the doctrine of lost modern grant.  On the contrary, it is clear that he was trying to advance a case of easement based on the Confirmatory Reassignment and Confirmatory Assignment.[16]  In the end, the Judge refused the application.[17] 

42.  Although the Judge refused the amendments, he had not ruled on whether the defendant was entitled to raise the issue of prescriptive easement.  That this was the position can be seen from the parties’ written closing submissions. The plaintiff’s written closing submission referred to [46] to [52] of the defendant’s opening submission and contended that it was not open to the defendant to raise the issue of prescriptive easement because it was not pleaded.[18] The defendant’s closing submission, on the other hand, reiterated that whether the defendant as a squatter had acquired an existing easement and/or proprietary right to lay underground water pipe and electricity power cable under the lane was an issue to be determined, and went on to canvass the evidence and legal principles in detail.[19] 

43.  Mr Lin informed us that, after the parties had put in their written closing submissions and before the case resumed to hear the closing submissions, the Judge had, through his clerk, referred counsel to Bullen & Leake & Jacob’s Precedents of Pleadings (18th ed) at pp 766-767.  There is a passage at [93-07] which stated that “Where a claim is based on express or implied grant, or upon a lost grant, or even upon prescription at common law, the basis on which it arises should be distinctly pleaded.” 

44.  In his oral submission, the defendant’s counsel did not submit on the passage in Bullen & Leake & Jacob’s Precedents of Pleadings.  Neither side’s counsel addressed the court on the issue of easement by prescription, and the Judge did not refer to counsel’s written submissions on the issue. 

45.  Looking at the events in the round, although the Judge did not specifically say so, it must be clear to both counsel he was of the view that in the absence of a distinct plea of easement by prescription, it was not open to the defendant to take the issue.   

46.  Had the defendant’s counsel still wished to pursue a line of defence based on easement by prescription, he should have addressed the Judge how he could have done so without amending his pleadings. As he did not do so, the Judge was entitled to proceed on the basis that he had abandoned that line of defence.

47.  It is trite that pleadings serve the important function of defining the issues in a trial and dictating the course of proceedings both before and at trial.  A pleading must therefore fairly and precisely inform the other party in the litigation of the pleader’s case and the issues to be tried so that proper preparation for the trial can be made, and time and costs are not expended unnecessarily on other issues. The requirements of pleadings are to ensure fairness between the parties and to protect parties against being taken by surprise by unpleaded issues: see Kwok Chin Wing v 21 Holdings Ltd (2013) 16 HKCFAR 663 at [21]; and Sinoearn International Ltd v Hyundai-CCECC Joint Venture (2013) 16 HKCFAR 632 at [30], [31] and [34].       

48.  A claim for easement should be pleaded distinctly with the basis giving rise to it and the material facts relevant to it clearly identified and set out.  As the discussions above show, the defendant’s pleading in this regard is unsatisfactory. The only easement pleaded in the Defence and Counterclaim is an easement based on proprietary estoppel by virtue of the plaintiff’s course of conduct (see [40], [98] and [104]).  There is no plea of a claim for a prescriptive easement. Proprietary estoppel and easement are two different concepts. While some material facts giving rise to the two concepts may overlap, there are also matters which are relevant to one but not to the other.  It is therefore confusing to link easement to proprietary estoppel.  It is also not clear from the Defence and Counterclaim whether the defendant is relying on some other “proprietary rights”, and if so what are these rights, to “arrange for” the laying of underground piping to connect the water mains to enable the supply of water to the defendant’s shop. 

49.  At the same time, the pleading has not clearly identified the material facts relied on for the prescriptive easement to arise.  Putting aside the representations and the 2006 and 2007 Agreements (which the Judge had rejected), it may be argued that the following matters are relevant to the defendant’s case on easement or proprietary right:

(a)     the right of way provided in the Confirmatory Assignment and Confirmatory Reassignment relating to the land;

(b)     the occupation of the part of the lane by the defendant’s shop since 1952 and the claim for adverse possession;

(c)     the past excavation works; and

(d)     the approval given by the Water Supplies Department and the undertaking of the installation of the connection piping to the water mains underneath the lane.

50.  It can be readily seen that the right of way in the assignments can only give rise to a right to go pass and repass the lane (as held by the Judge at [2] and [25] of the Judgment).  Further, although there is reference to the claim for adverse possession in HCA 354/2015, [20] the defendant is not seeking to establish this in the action below.  

51.  As to the past excavation works and the past dealings with the Water Supplies Department, Mr Lin points out that although the pleading has referred to these matters, it has not related them to a claim of easement.  These matters are not admitted by the plaintiff in the Reply and Defence to Counterclaim.  Mr Lin submits that had the pleading contained a distinct plea of prescriptive easement and these matters properly pleaded as material facts supporting the plea, the plaintiff would have explored and/or adduced additional evidence at the trial, including the history of water supply to the defendant’s shop and whether there was any interruption when excavation works were carried out in the past.  In particular, it is observed that the excavation works in March 2015, which gave rise to these proceedings, were to enable fresh water supply from the water mains underneath the lane to the defendant’s shop. This, he argues, suggests that before 2015 there was no supply of water from the water mains and/or through the water pipes underneath the lane to the defendant’s shop.  

52.  In our view, these are valid points that highlight the importance of a proper plea for a claim of prescriptive easement. At the trial, the defendant had been alerted to the inadequacy in the pleading.  He had an opportunity to amend the Defence and Counterclaim to properly plead his case on prescriptive easement so that the plaintiff could properly consider and prepare for it.  The proposed amendments, however, fail to advance a proper plea of easement by prescription.  Further, in view of the way the defence case was conducted by counsel at the trial as stated above, the defendant had actually through counsel chosen to run his case without reliance on easement by prescription at the trial.  It is now too late to allow the defendant to argue the issue in this appeal.  It would also be unfair to the plaintiff to allow the argument to be run.  Accordingly, we hold that it is not open to the defendant to advance arguments relating to easement by prescription in this appeal.     

Disposition

53.  For the reasons set out above, we dismiss the appeal.

54.  Applying the usual rule of costs follow the event, we make an order nisi that the defendant pays the plaintiff the costs of the appeal, to be taxed if not agreed. 

(M H Lam)
Vice President
(Maria Yuen)
Justice of Appeal
(Carlye Chu)
Justice of Appeal

  

Mr Kenny Lin, instructed by Woo, Kwan, Lee & Lo, for the Plaintiff

The Defendant appeared in person


[1][2018] HKCFI 690.

[2] [20] of the Defence and Counterclaim, Bundle A, p.91.

[3] [6] of the Judgment

[4] He made an affirmation on 12 June 2015 and a witness statement on 15 June 2016.

[5] Appeal bundle B2 pp.558 to 572, including the two discs containing the relevant video and audio files.

[6] At [26] of the Judgment.

[7] It should be the Water Supplies Department.

[8] At [29] to [31] of the Judgment

[9] At [33] of the Judgment.

[10]  Appeal Bundle A p.271-55.

[11] Appeal Bundle A pp271-56 to 271-59.

[12] Appeal Bundle C p.687 lines I to O.

[13] Appeal Bundle C p.714 lines M to P.

[14] Appeal Bundle C p.718.

[15] Appeal Bundle C p.717 lines C to J.

[16] Appeal Bundle C p.716 lines M to Q. See also p.715 line E where counsel said his case was not entirely by way of prescription.

[17] Appeal Bundle C p.719 line C.

[18] At [8] to [10], Appeal Bundle A pp289 to 290.

[19] At [23] to [32], Appeal Bundle A pp. 345 to 349.

[20] Defence and Counterclaim at [15], Appeal Bundle A p.90.

[2019] HKCA 1094-EN-2019-10-03

KING POLICY DEVELOPMENT LTD v. WAN KIN SHING

HTML content

CACV 107/2018

[2019] HKCA 1094

IN THE HIGH COURT OF THE

HONG KONG SPECIAL ADMINISTRATIVE REGION

COURT OF APPEAL

CIVIL APPEAL NO 107 OF 2018

(ON APPEAL FROM HCA 696/2015)

________________________

BETWEEN  
 KING POLICY DEVELOPMENT LIMITEDPlaintiff
 and
 WAN KIN SHINGDefendant

________________________

Before :Hon Lam VP, Yuen and Chu JJA in Court
Dates of Written Submissions : 29 August, 4 and 9 September 2019
Date of Judgment : 18 September 2019
Date of Reasons for Judgment : 3 October 2019

________________________________

REASONS FOR JUDGMENT

________________________________

Hon Lam VP (giving the Reasons for Judgment of the Court):

Introduction

1.  This is the defendant’s appeal from the judgment of Chung J (“the Judge”) on 29 March 2018 (“the Judgment”) granting an injunction in favour of the plaintiff to restrain the defendant from (i) damaging, excavating and/or carrying out any construction work on the plaintiff’s land and (ii) disconnecting and removing any pipe, drain and other items or articles which was connected, installed and/or placed by the defendant on the plaintiff’s land. 

2.  On 30 July 2018, the defendant issued a summons seeking leave to adduce further evidence on appeal.  The application was determined on the papers based on submissions lodged with the Court.  The main contention was whether the defendant has shown special grounds and satisfied the three conditions in Ladd v Marshall [1954] 1 WLR 1489 at 1491 for admission of further evidence on appeal.

3.  After considering the submissions from the parties, we dismissed the defendant’s application to adduce new evidence.  The following are our reasons for such determination.

Application for admission of fresh evidence

4.  In the summons dated 30 July 2018, the defendant sought to adduce the following new evidence for the purpose of this appeal:

(1)  eight pictures taken at different locations displaying installation and connection of water pipes and water meters (referred as “exhibit N-1” by the defendant);

(2)  seven drawings which the defendant called “water work progress plan” (made apparently either by himself or someone on his behalf though he did not identify the maker of the drawings and the remarks set out at the bottom of each drawing) to illustrate the excavation and installation works at the lane (referred as “exhibit N-2” by the defendant);

(3)  a video file recording conversation between Mr Wang Jun and the defendant on 16 March 2015 (produced as “WKS-54” by the defendant in his affirmation of 30 July 2018);

(4)  a video file recording conversation between the defendant and a Mr Chan Kin Sang on 17 March 2015 (referred as “WKS-29” by the defendant in his affirmation);

(5)  several pictures taken from a video file recording two police officers attending the scene on 17 March 2015 upon report made by the plaintiff regarding the excavation works carried out by the defendant (referred as “WKS-55a” by the defendant in his affirmation); and

(6)  audio file of the video described at (5) (referred as “WKS-55b” by the defendant in his affirmation). 

5.  It is well established that this court will not admit fresh evidence on an appeal unless the party who wishes to do so satisfied the criteria in Ladd v Marshall, supra by showing that:

(a)  The evidence could not have been obtained for use at the trial with reasonable diligence;

(b)  The evidence would, or might, if believed, have an important influence on the outcome, though not necessarily decisive, and

(c)  The evidence would probably be accepted as truthful.

6.  The defendant did not explain how the new evidence would satisfy the three conditions in Ladd v Marshall in his supporting affirmation and/or his skeleton arguments to admit the new evidence. He merely explained how the documents may from his point of view assist his appeal. 

7.  According to the defendant, he had tried to adduce documents (1) and (2) at the trial at a very late stage[1] but the Judge refused to admit the documents.  He did not produce for our consideration the relevant transcript of the trial where the alleged attempts were made and rejected.  There is no appeal against the exercise of discretion by the Judge.

8.  In the absence of such appeal, this Court will not admit documents (1) and (2) as fresh evidence since they were obviously available before the trial and the defendant had failed to exercise due diligence in procuring their disclosure and production in a timely manner before trial to facilitate admission of the same at the trial.  Thus, it is not open to have such evidence to be admitted on appeal when there is no appeal against the refusal by the judge to admit the same. 

9.  Further, we also fail to see how these documents could have important influence on the outcome of this appeal.  The mere examination of the photographs and drawings were of no assistance to the defendant in establishing a defence and his remarks on them needed explanation. The defendant has not produced any witness statement to account for the remarks and how these documents related to his defence based on the Waterworks Ordinance Cap 102.  It is not acceptable for such substantial evidence to be adduced in the form of some written remarks alongside the photographs and drawings or by way of submissions in support of an application for admission of fresh evidence. Such evidence should have been prepared well before the trial and adduced orally at the trial and the witness would have to be available for cross-examination.

10.  Though the defendant tried to account for the relevance in his submissions, those submissions should have been tested by cross-examination and might have been challenged by evidence from the plaintiff in response.  In the absence of such testing and challenges, we are unable to accept that such evidence would probably be accepted as truthful.

11.  In relation to documents (3) to (6), the relevant video and audio files were put in evidence at the trial.  They were also included in the appeal bundles[2].  If necessary, the Court can view the same on its own.  We do not find it necessary to have the so-called legible copies of those clips prepared by the defendant to be admitted as further evidence for the proper conduct of the appeal.

12.  We therefore dismissed the defendant’s summons dated 30 July 2018 at the beginning of the hearing of the appeal.

(M H Lam)(Maria Yuen)(Carlye Chu)
Vice PresidentJustice of AppealJustice of Appeal

Mr Kenny C.P. Lin, instructed by Woo, Kwan, Lee & Lo, for the plaintiff

The defendant acting in person



[1] According to his own submissions, attempts were made to produce these documents at the stage of closing submissions.

[2] Appeal bundle B2 p.558 to 572, including the discs containing the relevant video and audio files