HK CourtDB
HomeDirectoryMCP
Hong Kong CourtDB
Back to directory
Construction and Arbitration Proceedings2018

MAEDA KENSETSU KOGYO KABUSHIKI KAISHA also known as MAEDA CORPORATION AND ANOTHER v. BAUER HONG KONG LTD

Related cases with same parties

  • CACV113/2019MAEDA KENSETSU KOGYO KABUSHIKI KAISHA also known as MAEDA CORPORATION AND ANOTHER v. BAUER HONG KONG LTD
  • CACV122/2019MAEDA KENSETSU KOGYO KABUSHIKI KAISHA also known as MAEDA CORPORATION AND AND ANOTHER v. BAUER HONG KONG LTD
  • CAMP154/2018MAEDA KENSETSU KOGYO KABUSHIKI KAISHA also known as MAEDA CORPORATION AND ANOTHER v. BAUER HONG KONG LTD
  • HCCT35/2016MAEDA KENSETSU KOGYO KABUSHIKI KAISHA also known as MAEDA CORPORATION AND ANOTHER v. BAUER HONG KONG LTD
  • HCCT5/2018MAEDA KENSETSU KOGYO KABUSHIKI KAISHA also known as MAEDA CORPORATION AND ANOTHER v. BAUER HONG KONG LTD
  • HCMP1342/2017MAEDA KENSETSU KOGYO KABUSHIKI KAISHA (also known as MAEDA CORPORATION) AND ANOTHER v. BAUER HONG KONG LTD

Files (3)

[2019] HKCFI 1427-EN-2019-06-03

MAEDA KENSETSU KOGYO KABUSHIKI KAISHA also known as MAEDA CORPORATION AND ANOTHER v. BAUER HONG KONG LTD

HTML content

HCCT 4/2018

[2019] HKCFI 1427

IN THE HIGH COURT OF THE

HONG KONG SPECIAL ADMINISTRATIVE REGION

COURT OF FIRST INSTANCE

CONSTRUCTION AND ARBITRATION PROCEEDINGS

NO 4 OF 2018

______________

 IN THE MATTER of the Arbitration Ordinance (Cap 609)
 and
 IN THE MATTER of an Arbitration

______________

BETWEEN  
 MAEDA KENSETSU KOGYO KABUSHIKI KAISHA also known as MAEDA CORPORATION1st Plaintiff
(1st Respondent in the Arbitration)
 CHINA STATE CONSTRUCTION ENGINEERING (HONG KONG) LIMITED 2nd Plaintiff
(2nd Respondent in the Arbitration)
(together as the “Plaintiffs”)
 and 
 BAUER HONG KONG LIMITED Defendant
(Claimant in the Arbitration)

______________

Before:Hon Mimmie Chan J in Chambers
Dates of Written Skeleton Submissions:24 & 27 May 2019
Date of Decision:3 June 2019

______________

D E C I S I O N

______________

Background

1.  This is an application made by the Defendant for leave to appeal against my decision of 9 April 2019 (“Judgment”), whereby I allowed the Plaintiffs’ appeal against the Second Interim Award of the Arbitrator in the Arbitration between the parties.  The facts are more particularly set out in the Judgment, the nomenclature of which is adopted.

2.  Two issues are raised.  The first is whether the intended appeal is out of time, such that leave to appeal out of time is required.  The second is whether section 14AA of the High Court Ordinance (which governs appeals against interlocutory judgments and orders of the Court) applies, such that the Defendant has to show that the intended appeal has reasonable prospects of success, or whether the only conditions to be satisfied for obtaining leave to appeal are those set out in section 5 (9) of the Schedule to the Arbitration Ordinance.

Is the intended appeal out of time?

3.  I accept the Defendant’s submissions on this issue.

4.  Section 5 (5) of the Schedule states, for an appeal against an arbitral award on question of law:

“On hearing an appeal under this section, the Court may by order - (a) confirm the award; (b) vary the award; (c) remit the award to the arbitral tribunal, in whole or in part, for reconsideration in the light of the Court’s decision; or (d) set aside the award, in whole or in part.”

5.  Section 5 (8) of the Schedule provides for further appeal, and leave to appeal, stating:

“The leave of the Court or the Court of Appeal is required for any further appeal from an order of the Court under subsection (5).” (Emphasis added)

6.  By the Judgment and as reflected in the Amended Order, this Court only allowed the Plaintiffs’ appeal against the Award on the first question of law for which leave to appeal was originally granted (on 30 August 2018).  The parties had not addressed the Court at the hearing on 8 November 2018 as to the consequences of the appeal being allowed, whether pursuant to section 5 (5) of the Schedule, the Court should confirm the Award, vary the same, remit the Award to the tribunal for reconsideration in the light of the Court’s decision, or set aside the Award, in whole or in part.  It was on such basis that the Amended Order was made, simply to reflect that the appeal was allowed.

7.  It was only on 24 May 2019, after considering the further written submissions made by the parties, that the Court made the order remitting the Award to the tribunal - as opposed to setting aside the Award or varying it, which were options available under section 5 (5) of the Schedule.

8.  The appeal, for which leave is required under section 5 (8) of the Schedule, is an appeal “from an order of the Court under subsection (5)”.  Properly made, the appeal is against the order for setting aside, variation, or remission to the tribunal.

9.  The intended appeal, for which leave is sought by the Defendant, is against the order made under section 5 (5) for remission, consequent to the appeal being allowed on 9 April 2019.  The order for remission was only made on 24 May 2019.  Accordingly, the application for leave to appeal, which was made on 30 April 2019, was not out of time.

Conditions for leave

10.  Section 5 (8) of the Schedule provides for leave being required for further appeal against the order made under section 5 (5), with the conditions for leave to appeal set out in section 5 (9):

“Leave to further appeal must not be granted unless - (a) the question is one of the general importance; or (b) the question is one which, for some other special reason, should be considered by the Court of Appeal.” (Emphasis added)

11.  The Plaintiffs contend that in addition to the conditions for the grant of leave set out in section 5 (9), the Plaintiff must also satisfy the conditions set out in section 14AA (1) (4) of the High Court Ordinance (“Section 14AA”), namely, the appeal should have a reasonable prospect of success, or there is some other reason in the interests of justice why the appeal should be heard.

12.  I accept the submissions of the Defendant, that section 14AA is not applicable to the appeal presently intended.  Section 14AA only governs interlocutory judgments or orders of the Court.  The order of remission of the Award pursuant to the appeal on the question of law being allowed under the Judgment is a final judgment or order in these proceedings.  It finally determines the whole action, or the entire cause in this action.

13.  Section 5 (9) of the Schedule therefore governs the present application for leave to appeal.  The question should be one of general importance, or one which for some other special reason should be considered by the Court of Appeal. In this context, however, the decision of the Court of Appeal in Maeda Kensetsu Kogyo Kabushiki Kaisha (also known as Maeda Corporation) and anr v Bauer Hong Kong Limited HCMP 1342/2017, 4 September 2017 is relevant. The Court of Appeal decision was on section 6 (6) of the Schedule, and the criteria for leave to be granted against a decision of the Court of First Instance granting leave to appeal against an award on a question of law, but the language of section 5 (9) and section 6 (6) are identical.  The Court of Appeal held that section 14AA applies to an application for leave to appeal against a decision made under section 6 (6) to grant or refuse leave to appeal (as distinct from a decision on the appeal itself), but explained that although section 6 (6) provides for some necessary conditions which must be fulfilled before leave could be granted, section 6 (6) does not provide that these are the only conditions that need to be fulfilled. 

14.  Bearing in mind the aims and objectives of the Ordinance as set out in section 3 of the Ordinance itself, the presumption of finality of an arbitral award, and the overall scheme of the Ordinance and the Schedule, it can hardly be disputed that section 5 (8) and (9) of the Schedule are intended to be a filtering process for any further appeal.  Section 5 (9) sets out the essential conditions which must be satisfied before leave to appeal can be granted.  However, the filtering process makes no sense if the Court, in considering whether leave to appeal should be granted, does not consider the grounds of the intended appeal and be satisfied that the intended appeal is at least arguable, and have some reasonable prospects of success.  The threshold for “reasonable prospects of success” in the context of section 14 AA are not high, conveying the notion that the prospects of succeeding in the appeal must be reasonable, and therefore more than not fanciful, without having to be probable (SMSE v KL [2009] 4 HKLRD 125 and Ho Yuen Ki Winnie v Ho Hung Sun Stanley HCMP 1009/2009).  In the absence of any authorities cited by the parties, I consider it appropriate to adopt the “reasonable prospects of success” threshold for the filtering process in the grant of leave to further appeal under section 5 (8) of the Schedule.  I come to such view, having balanced the interests of finality of an arbitral award and the objectives of the Ordinance, against the fact that the parties had chosen to opt for the provisions of the Schedule (and the availability of an appeal to the courts on questions of law) to apply to their dispute.

15.  In granting leave to appeal on the questions of law on 30 August 2018, I was already satisfied that the question of law on the construction of Clause 21.1 and 21.2 of the Sub-Contract (on notice compliance) are of general importance.  The Defendant contends that the Court’s construction of the notice of claim provisions was wrong in law, for having failed to give consideration to the findings of fact made by the Arbitrator in the Award.  Since the threshold for “reasonable prospects of success” is not high, I consider in the light of the submissions and the draft Grounds of Appeal that this has been satisfied, and accordingly grant leave to the Defendant to appeal against the Order of remission, made as a result of the Court’s findings on the question of law decided in the Judgment.

16.  The costs of the application for leave to appeal will be in the cause of the appeal. 



 (Mimmie Chan)
 Judge of the Court of First Instance
 High Court

Pinsent Masons, for the 1st and 2nd plaintiffs

Mr Anthony Houghton SC and Mr James Niehorster, instructed by Bryan
Cave Leighton Paisner LLP, for the defendant

[2019] HKCFI 916-EN-2019-04-09

MAEDA KENSETSU KOGYO KABUSHIKI KAISHA<br>also known as MAEDA CORPORATION AND ANOTHER v. BAUER HONG KONG LTD

HTML content

HCCT 4/2018

[2019] HKCFI 916

IN THE HIGH COURT OF THE

HONG KONG SPECIAL ADMINISTRATIVE REGION

COURT OF FIRST INSTANCE

CONSTRUCTION AND ARBITRATION PROCEEDINGS

NO 4 OF 2018

______________

  IN THE MATTER of the Arbitration Ordinance (Cap 609)
  and
  IN THE MATTER of an Arbitration

______________

BETWEEN
 MAEDA KENSETSU KOGYO KABUSHIKI KAISHA
also known as MAEDA CORPORATION
1st Plaintiff
(1st Respondent in the Arbitration)
 CHINA STATE CONSTRUCTION ENGINEERING (HONG KONG) LIMITED2nd Plaintiff
(2nd Respondent in the Arbitration)
(together as the “Plaintiffs”)
and
 BAUER HONG KONG LIMITED Defendant
(Claimant in the Arbitration)

______________

Before:Hon Mimmie Chan J in Chambers
Date of Hearing:8 November 2018
Date of Judgment:9 April 2019

_______________

J U D G M E N T

_______________

Background

1.  On 30 August 2018, I granted leave to the Plaintiffs to appeal against the Second Interim Award of the Arbitrator published on 3 January 2018, as corrected on 3 March 2018, on two questions of law:

(1)   whether there was compliance with the condition precedents to give notice under Clause 21.1 and 21.2 of the Sub-Contract between the Plaintiffs and the Defendant; and

(2)   the valuation of variation of works under the Sub-Contract.

2.  The abbreviations set out in my Decision of 30 August 2018 are adopted.

3.  This is the substantive appeal against the Award on the two questions of law identified.  As such, the Court is to decide the questions of law on the basis of the findings of fact in the Award (section 5 (3) of the Schedule to the Ordinance).  In deciding the questions of law, section 5 (4) of the Schedule expressly states that the Court must not consider any of the criteria set out in section 6 (4) (c) (i) or (ii) of the Schedule (ie the criteria of “obviously wrong” or “at least open to serious doubt”).

4.  On behalf of the Defendant, it was emphasized that the Arbitrator’s findings on law, as to the construction, effect and requirements of Clause 21, are made on the basis of his findings of fact, as to the time when and the factual circumstances in which the ground conditions claims became apparent, how the impact of the ground conditions was realized by the parties, and the extent of the Plaintiffs’ knowledge of these ground conditions.  An arbitrator’s findings on facts are assumed to be correct and are not to be revisited.  Questions of law are to be decided on the basis of the findings of fact in the award (section 5 (3) of the Schedule to the Ordinance).  The Defendant submits that the proper test on an appeal on a question of law is to consider whether interference with the arbitrator’s award is necessitated because the arbitrator had obviously misdirected himself in law, by invoking legal principles which were self-evidently incorrect, and alternatively, the Plaintiffs must establish that although the law stated was correct, the decision reached was one that no reasonable arbitrator could reach (Kwan Lee Construction v Elevator Parts Engineering [1997] HKLRD 965 at 971). 

5.  In Cosemar SA v Mariamararna Shipping Co Ltd (The “Matthew”) [1990] 2 Lloyd’s Rep 323, the Court held that for an appeal to succeed on a mixed question of fact and law, it has to be shown that the decision of the arbitrator was outside the permissible range of solutions which were open to him.

6.  The case of Kwan Lee Construction Co Ltd v Elevator Parts Engineering Co Ltd [1997] HKLRD 965 concerned an application for leave to appeal against an arbitral award.  However, in the judgment of the Court of Appeal, His Lordships referred to the function of the court to which an appeal on the question of law is brought.  Both Mayo JA and  Litton VP cited Pioneer Shipping v BTP Tioxide [1982] AC 724, and reference was made to the speech of Lord Radcliffe in Edwards v Bairstow [1956] AC 14:

“If the case contains anything ex facie which is bad law and which bears upon the determination, it is, obviously, erroneous in point of law. But, without any such misconception appearing ex facie it may be that the facts found are such that no person acting judicially and properly instructed as to the relevant law could have come to the determination under appeal. In those circumstances, too, the court must intervene. It has no option but to assume that there has been some misconception of the law and that this has been responsible for the determination. So there, too, there has been error in point of law.”

Lord Denning’s summary in Edwards v Bairstow was also referred to, that to justify interference with an arbitrator’s award, it must be shown that the arbitrator had misdirected himself in law, or that the decision was such that no reasonable arbitrator could reach.

The notice compliance question

7.  By way of quick recap, the Plaintiffs in this case were the main contractors under the Main Contracts with the MTRC as Employer, to construct tunnels for the Hong Kong to Guangzhou Express Rail Link.  The Plaintiffs subcontracted the diaphragm wall works under the contracts to the Defendant.  Disputes arose which were submitted to arbitration initiated by the Defendant, and this led to various awards which have been made.  The Defendant’s primary case in the Arbitration was that the unforeseen ground conditions gave rise to a variation of the scope of works under the Sub-Contract, so as to entitle the Defendant to claim additional payment under the express variation provisions.  In the alternative, the Defendant made a “like rights” claim under sub-clause 1 of  S-CC 21.1 of the Sub-Contract (“Clause 21”). 

8.  In the Award, the Arbitrator referred to the “ground conditions claims” made by the Defendant in the Arbitration.  At paragraph 164, the Arbitrator described the Defendant’s primary case, as follows:

“Bauer’s primary case is that the ground conditions differed from those described in the Geotechnical Baselines and the (Geotechnical Baseline Report) and that this difference amounted to a Variation or a Sub-Contract Variation which is to be valued. The JV submits that Bauer’s claims based on Variations or Sub-Contract Variations are unsustainable because the ground conditions were as the parties found them, they were known to be variable and unpredictable and were not instructed. It says that Bauer was obliged to carry out the Sub-Contract Works, irrespective of whether the ground conditions were more or less difficult than envisaged.

In particular, the JV refers to Clause 17.2 of the Sub-Contract which provides that: “No Variation, Sub-Contract Variation … shall be implemented by the Sub-Contractor without an order in writing by the Contractor.” It submits that, without an order in writing there can be no claim for a Variation or Sub-Contract Variation.

The JV challenges Bauer’s contention that a change from a parameter baselined in the GBR is a variation.  It submits that there would be no change to the Sub-Contract Works which Bauer was obliged to perform merely because a baselined parameter was not met.  The JV says that, absent a route to recovery, the ground conditions are at Bauer’s risk.”

9.  The Arbitrator rejected the Defendant’s primary claim of variation.  At paragraph 177 of the Award, the Arbitrator states:

“Whilst, as set out below, I have found that the final changes to the founding level were instructed as Variations or Sub-Contract Variations and that such changes were instructed, I do not consider that Bauer is entitled to a Variation or Sub-Contract Variation merely because there was a change in the conditions which could have been foreseen and that this had an effect on the work. An essential part of the variation mechanism is that there has to be an instruction by the Engineer and/or by the JV. Where in carrying out the diaphragm wall work, Bauer encountered unanticipated ground conditions, it was still obliged to carry out the same work in terms of the volume of material which had to be excavated and there was no change to the scope of the work. Nor was there any instruction. I therefore accept the JV’s submission that the changed ground conditions do not, in themselves, give rise to payment as a Variation or Sub-Contract Variation, in the absence of an instruction.”

10.  The Arbitrator then proceeded to consider the claims made by the Defendant to see whether the different conditions said to have been encountered differed either from the geotechnical baselines or from the conditions which could reasonably have been foreseen by an experienced contractor, and made different findings.  At paragraph 321 of the Award, he concluded:

“I have held above that, prima facie, the evidence establishes that Bauer has 4 heads of claim: Additional 1 (c) rock excavation, additional rock excavation caused by the inclination of the rock, additional rock excavation caused by instructions to deepen founding levels and excavation of HTL (hard transitional layer). I now turn to consider whether Bauer has complied with the relevant notice provisions under clauses 21 and 14.”

Clause 21 deals with service of notice of claims, and clause 14 deals with revision of the date for completion of the Contract Works.

11.  At paragraph 300, the Arbitrator repeated the findings he had made in the First Award on the notice provisions:

“In the First Award I made certain findings about the need for notice under the Sub-Contract. In paragraphs 249 to 252 of the First Award I held that in relation to the notice provisions in Clauses 21.2 to 21.3 of the Sub-Contract:

(1) Those provisions did not apply to a claim for the standby/idling rate under the Sub-Contract, alternatively actual loss, under paragraph (1)(f) of the Preambles: paragraph 249 of the First Award;

(2) Those provisions did apply to a claim based on the JV’s breach of the express or the implied terms of Sub-Contract: paragraph 250 of the First Award;

(3) Those provisions did not apply to a claim for payment for a valuation of a Variation or Sub-Contract Variation under Clause 19 but would apply to a claim for “loss or expense”: paragraph 251 of the First Award;

(4) Those provisions did apply to a claim to recover from the JV any additional payment or loss and expense Bauer incurred as a result of any circumstances or occurrence as a consequence of which the JV is entitled to additional payment or loss and expense under the Main Contract, pursuant to Clauses 8.3.4 and 21.1.1: paragraph 252 of the First Award.

In addition, at paragraph 122 of the First Award I held that Bauer was only obliged to give notices under the notice provisions of Clause 21 as from 2 August 2011 in respect of events which had occurred prior to that date.

I also held that there was no requirement for one notice to be given and therefore notice could be given by reference to previous documents and that the notice had to be construed in the light of the background knowledge which the parties would reasonably have.”

12.  The Arbitrator then considered Clause 21.  At paragraph 322 of the Award, the Arbitrator states:

“The basis of claim for additional rock excavation caused by instructions to deepen founding levels was a Variation or Sub-Contract Variation and, as stated in the First Award, the valuation of such a Variation or Sub-Contract Variation would not be subject to the requirements of notice under Clause 21.  The other claims, being “like claims” under Clause 38, do have to comply with the conditions precedent in Clause 21.

323.     The first notice under Clause 21.1 is a “notice of its intention” to claim within 14 days after the event, occurrence or matter giving rise to the claim became apparent or ought reasonably to become apparent to the Sub-Contractor.  I consider that the notice of intention does not need to specify which of Clauses 21.1.1 to 21.1.6 it is being made under but has to show an intention to make a claim.

324.     The second notice under Clause 21.2 can be one of two types. Generally under Clause 21.2 the second notice has to be given within 28 days after giving the Clause 21.1 notice and has to state: “the contractual basis together with full and detailed particulars and the evaluation of the claim” under 21.2.1 and also “details of the documents and any contemporary records that will be maintained to support such claim” under Clause 21.2.3 and “details of the measures which the Sub-Contractor has adopted and proposes to adopt to avoid or reduce the effects of such event, occurrence or matter which gives rise to the claim.

…

327.     In summary I have held that Bauer has established the following claims:

(1)   Hard Transitional Layer: This claim is based on encountering the HTL which was no (sic) shown in GBR.

(2)   Increased Inclination of Rockhead. This claim is based on the increased inclination of rockhead compared to GBR.

(3)   Additional excavation by reason of higher 1(c) rock head. This claim is for additional excavation by reason of a higher 1(c) rockhead above base slab bottom level.

(4)   Excavation below founding level in 1(c)/1(d). This claim is for additional excavation instructed by JV below “specified founding level”. I have found that the claim is based on a Variation or Sub-Contract Variation and the notice provisions of Clause 21 do not apply to the valuation of a variation.”

13.  After considering the evidence on the meetings held on 27 and 28 July 2011, the Claim Notices sent by the Plaintiffs to MTRC on 27 July 2011, and the letters from the Defendant to the Plaintiffs of 1 August, 2 August and 10 August 2011, the Arbitrator first found that the Defendant had given the notice required under Clause 21.1.  The Arbitrator considered that: (1) at the meeting on 27 and 28 July 2011, the Defendant had explained to the Plaintiff that the main cause of the slow progress of works was the additional quantity of toe-in rock which had to be excavated; (2) the Plaintiff’s Claim Notices of 27 July 2011 to MTRC had referred to the delay and disruption to the Works by adverse physical conditions, and that the event giving rise to the claim was: “The existing level of Cat 1 (c) and Cat 1 (d) rock obtained for Granodiorite rock to be encountered in the excavation … obtained from pre-drilled boreholes indicate that the levels are generally higher than the corresponding Baselines for rock levels included in the GBR”; and (3) the Defendant had referred in the letters of 1 and 2 August 2011 to an increase in quantity and quality of rock excavation, and this had to be read against the background knowledge which the Plaintiffs had at the time. 

14.  The Arbitrator then went on to consider whether the Defendant had given the appropriate notice under Clause 21.2.  In this context, the Arbitrator pointed out that he had raised in closing submissions the question of “whether the contractual basis of the claim made under Clause 21.2 had to be the same as the contractual basis of the claim made in the arbitration”.  At paragraph 332, the Arbitrator then stated:

“I consider that both as a matter of sympathy and as a matter of construction, the contractual basis of the claim stated in the Clause 21.2 notice does not have to be the contractual basis on which the party in the end succeeds in an arbitration. First, to expect a party to finalize its legal case within the relatively short period and be tied to that case through to the end of an arbitration is unrealistic. Secondly, what is important from the point of view of the Contractor is to know the factual basis for the claim so that it can assess it and decide what to do.

Indeed, as can be seen on the facts here, the JV’s view of the appropriate legal basis for the claim was that it was a Clause 38 unforeseen physical conditions claim as well as a Variation claim, as shown in the notices which were then given to the MTRC.  It therefore follows that the fact that Bauer have made its claims on the basis of the relevant claim being a Variation or Sub-Contract Variation does not preclude Bauer from making the claim on a new legal basis based on notices given by reference to a different legal basis.”

15.  The Defendant’s letter to the Plaintiffs of 1 August 2011 (held by the Arbitrator to be one of the notices under Clause 21.1) referred to the following:

“We confirm the issuance of said design information/founding levels are causing a substantial increase in the quantity and quality of rock we are required to excavate compared to what was allowed for in our Sub-Contract. Please be advised that these additional quantities and change in quality represent variations to our Sub-Contract Works under Clause 17.1 of our Sub-Contract Agreement which shall be valued under Clause 19 and for which we are entitled to and will claim an extension of time in accordance with Clause 14.3.3 and additional costs as provided for under Clause 21.1.6.” (Emphasis added)

16.  The other letter, of 2 August 2011, which was found to comprise the notice under Clause 21.1 stated the following:

“As notified in the above correspondence and meetings held with your goodselves the quantity and quality of rock excavation we have been instructed to excavate below rockhead level have increased substantially from those provided under the Sub-Contract and these amount to a variation of our Sub-Contract Works.

…

This substantial increase in the quantity and quality of our work represents a variation under Clause 17.1 of our Sub-Contract Agreement which shall be valued under clause 19 of the Sub-Contract Agreement. In addition, we are entitled to an extension of time under Clause 14.3.3 for execution of the aforesaid additional works and would calculate our entitlement as follows…

In accordance with the Sub-Contract Agreement we are entitled to claim additional costs under Clause 21.1.6 in respect of the instructed variations and resultant extension of time to our Sub-Contract Works which is a course we will follow…” (Emphases added)

17.  Essentially, the Arbitrator’s finding is that the appropriate Clause 21.2 notice had been given, despite the fact that the Defendant had made its claims in its letters of 1, 2 and 10 August 2011 on the basis of a Variation or Sub-Contract Variation (under Clause 21.1.6), and not on a “like rights” basis under Clause 21.1.1.  The Arbitrator made it clear in the Award that the claim allowed in the Arbitration is a new legal basis, but that the Defendant was not precluded under Clause 21.2 to pursue a different contractual or legal basis.  This is reflected in paragraphs 333 and 334 of the Award:

“Indeed, as can be seen on the facts here, the JV’s view of the appropriate legal basis for the claim was that it was a Clause 38 unforeseen physical conditions claim as well as a Variation claim, as shown in the notices which were then given to the MTRC. It therefore follows that the fact that Bauer have made its claims on the basis of the relevant claim being a Variation or Sub-Contract Variation does not preclude Bauer from making the claim on a new legal basis based on notices given by reference to a different legal basis.

Bauer then sent further letters on 19,20 and 25 August 2011 which between them provided further details of the claims for the purpose of Clause 21.2. I consider that certainly by the time of Bauer’s letter of 29 August 2011 it had complied with Clause 21.2.2. … ”

18.  With respect, in coming to such a conclusion, the Arbitrator failed to pay heed and give effect to the express provisions of Clause 21.2, which is clearly stated to be a condition precedent for any claim to additional payment or loss and expense, and is required by the express provisions of clause 21.3 to be “strictly complied with”. 

19.  Clause 21 is set out below:

“21.1 If the Sub-Contractor intends to claim any additional payment or loss and expense pursuant due to:

21.1.1 any circumstances or occurrence as a consequence of which the Contractor is entitled to additional payment or loss and expense under the Main Contract;

21.1.2 any alleged breach of the Sub-Contract, delay or prevention by the Contractor or by his representatives, employees or other sub-contractors;

21.1.3 any claim for discrepancy between Sub-Contract Drawings and documents pursuant to Clause 8.4;

21.1.4 any claim under Common Law, statute laws or by-law;

21.1.5 any extension of time granted to the Sub-Contractor with exception to those cases which the delay are caused by typhoon signal no. 8 and/or force majeure etc.

21.1.6 any Variation of Sub-Contract Variation,

as a condition precedent to the Sub-Contractor’s entitlement to any such claim, the Sub-Contractor shall give notice of its intention to the Contractor within fourteen (14) days after the event, occurrence or matter giving rise to the claim because apparent or ought reasonably to have become apparent to the Sub-Contractor. For the avoidance of doubt, the Sub-Contractor shall have no entitlement to any additional payment or any additional loss and expense and no right to make any claim whatsoever for any amount in excess of the Sub-Contractor Sum in respect of any event, occurrence or matter whatsoever unless this sub-Contractor sets out an express right to that additional payment, additional loss and expense or claim.

21.2 If the Sub-Contractor wishes to maintain its right to pursue a claim for additional payment or loss and expense under Clause 21.1, the Sub-Contractor shall as a condition precedent to any entitlement, within twenty eight (28) Days after giving of notice under Clause 21.1, submit in writing to the Contractor:

21.2.1 the contractual basis together with full and detailed particulars and the evaluation of the claim;

21.2.2 where an event, occurrence or matter has a continuing effect or where the Sub-Contractor is unable to determine whether the effect of an event, occurrence or matter will be continuing, such that it is not practicable for the Sub-Contractor to submit full and detailed particulars and the evaluation in accordance with Clause 21.2.1, a statement to that effect with reasons together with interim written particulars. The Sub-Contractor shall thereafter, as a condition precedent to any entitlement submit to the Contractor at intervals of not more than twenty eight (28) Days (or at intervals necessary for the Contractor to comply with his obligations under the Main Contract, whichever is shorter) further interim written particulars until the full and detailed particulars are ascertainable, whereupon the Sub-Contractor shall as soon as practicable but in any event within twenty eight (28) Days (or as necessary for the Contractor to comply with his obligations under the Main Contract, whichever is shorter) submit to the Contractor full and detailed particulars and the evaluation of the claim;

21.2.3 details of the documents and any contemporary records that will be maintained to support such claim; and

21.2.4 details of the measures which the Sub-Contractor has adopted and proposes to adopt to avoid or reduce the effects of such event, occurrence or matter which gives rise to the claim.

21.3     The Sub-Contractor shall have no right to any additional or extra payment, loss and expense, any claim for an extension of time or any claim for damages under any Clause of the Sub-Contract or at common law unless Clauses 21.1 and 21.2 have been strictly complied with.”

20.  The claim pursued by the Defendant in the Arbitration, and the subject matter of the Award and the present appeal, is a claim for additional payment or loss and expense pursuant to “any circumstances or occurrence as a consequence of which the Contractor is entitled to additional payment or loss and expense under the Main Contract”, under Clause 21.1.1.  Notice of intention to make such a claim must, under Clause 21.1, be given “as a condition precedent to (the Defendant)’s entitlement to such claim”. 

21.  Clause 21.2 expressly provides that, “as a condition precedent to any entitlement”, if the Defendant wishes to maintain its right to pursue a claim for additional payment or loss and expense under Clause 21.1, the Defendant “shall” within 28 days after giving notice under Clause 21.1 submit in writing (under clause 21.2.1) “the contractual basis together with full and detailed particulars and the evaluation of the claim”.  (Emphases added)

22.  Clause 21.3 clearly states that the Defendant “shall have no right” to any additional or extra payment, loss and expense, under any Clause of the Sub-Contract or at common law “unless Clauses 21.1 and 21.2 have been strictly complied with”.

23.  In my view, there can be no dispute, and no ambiguity, from the plain and clear language used in Clause 21, that the service of notices of claim in writing referred to in Clause 21.1 and 21.2 are conditions precedent, must be “strictly” complied with, and failure to comply with these conditions will have the effect that the Defendant will have “no entitlement” and “no right” to any additional or extra payment, loss and expense.

24.  On behalf of the Defendant, it was argued that Clause 21 is in substance an exclusion or time-bar clause, and such clauses are strictly construed.  Leading Counsel for the Defendant referred to Keating on Construction Contracts:

“… Ambiguity in an exclusion clause may be given a narrow construction because it cuts down or detracts from the ambit of an important obligation in a contract or a remedy conferred by the general law, such as an obligation to give effect to a contractual warranty by paying compensation for breach of it. Parties are not likely to be taken to have intended to cut down the remedies which the law provides for breach of important contractual obligations without using clear words having that effect. However, this approach is not now regarded as a presumption nor a special rule justifying the giving of a strained meaning to a provision merely because it is an exclusion clause. Instead, all the tools of linguistic, contextual, purposive and common sense analysis should be deployed to establish the proper construction of the provision. Only if that approach still results in an ambiguity in the meaning of the exclusion clause may it have to be resolved by a preference for a narrower construction. In construction contracts, exemption clauses should be seen as part of the contractual apparatus for distributing risk and there should be no predetermined mindset to cut them down.”

25.  As recognized in the above cited passage, it is only in the event of ambiguity that a narrower construction may be applied.  As the court made clear in Waterfront Shipping Co Ltd v Trafigura AG [2007] EWHC 2482 (Comm), the words in a time-bar provision must be given their ordinary and natural meaning, notwithstanding that it must be clear and unambiguous if effect is to be given to it.  At paragraph 16 of the judgment, Gloster J stated in Waterfront Shipping:

“The authorities show that parties are obliged to comply carefully and strictly with demurrage time-bar clauses of this sort, which are well known within the industry. Importance is also attached to requirements for signed documents were included. …”

Gloster J explained at paragraph 17 of his judgment that the commercial purpose of such clauses is to achieve finality, citing The Yellow Star [2000] 2 Lloyd’s Rep 637 at 641.

26.  Clause 21 of the Sub-Contract is in my view clear and unambiguous in its provision and requirement for written notices to be served as a condition precedent to any claim or entitlement of the contractor.  The Defendant argued that the ambiguity or uncertainty arises in relation to the requirement under clause 21.2.1 to state “the contractual basis” of the contractor’s claim for additional payment, loss and expense.  The Arbitrator appears to base his findings on the fact that notice had been adequately given to the Plaintiffs, at the meetings and in the August correspondence, of the “ground conditions” encountered by the Defendant, and the fact that there was a substantial increase in the quantity and quality of the work encountered.  He made it clear that the Defendant’s claims made in the Arbitration were on a “new legal basis” or “a different contractual basis”, compared to the basis referred to in the August correspondence comprising the Clause 21.1 notice.  Yet, the Arbitrator considered that as the Plaintiffs were able in this case to notify MTRC in the Claim Notices of delay and disruption to the Works by adverse physical conditions, the principal purpose of Clause 21 - to enable the contractor to know the factual basis for the claim so that it can assess it and decide what to do - had been complied with.

27.  Again, with due respect to the Arbitrator, what the Defendant had done by service of the letters of 1, 2 and 10 August 2011 was simply to give notice of the ground conditions encountered at the site, and the additional quantities and quality of the rock to be excavated.  At most, these form the factual basis which may, or may not, give rise to a claim under the Sub-Contract.  The facts may result in different consequences and give rise to different rights and entitlement of the Sub-Contractor.  Clause 21.1 itself envisages different bases for claims of additional payment or loss and expense: namely, circumstances as a consequence of which the Contractor is entitled to additional payment or loss and expense under the Main Contract; alleged breach of the Sub-Contract, delay or prevention by the Contractor; claim for discrepancy between Sub-Contract drawings and documents; any claim under common law; extension of time granted; and/or any Variation. 

28.  Clause 21.2 requires the Defendant, again as a condition precedent, to submit “the contractual basis”, together with the detailed particulars and evaluation of the claim which the Defendant wished to pursue after the service of the Clause 21.1 notice.  The sub-clause refers not only to the submission of the detailed factual particulars, but “the contractual basis” together with the full detailed particulars.  What is required under Clause 21.2 therefore must be the basis which the Defendant claims it is entitled under the Sub-Contract to maintain and pursue its claim, by reason or as a result of the factual circumstances which have arisen.  There may be one, or more, contractual bases, which can be stated in the Clause 21.2 notice, but the “contractual basis” under Clause 21.1 is one or more of the different causes or events set out in Clause 21.1.1 to Clause 21.1.6 as giving rise to a claim.

29.  The August letters found by the Arbitrator to constitute the notices under Clause 21.1 state the factual basis of changed ground conditions, and further state the contractual basis of the Defendant’s claims to be Variations.  There is no basis to find that the Defendant had complied strictly with Clause 21.2.1, in relation to any “like rights” claim made under Clause 21.1.1 and maintained under Clause 21.2.  As such, by operation of Clause 21.3, the Defendant should have no right to the additional extra payment, loss and expense claimed.

30.  The Arbitrator pointed out that it was unrealistic to expect a party to finalize its legal case within a relatively short period of time and to be tied to that case through to the end of an arbitration.  As Leading Counsel for the Plaintiffs pointed out, the Defendant had 42 days from the event or occurrence giving rise to the claim to serve the notice required under Clause 21.2.  That is not an unrealistic timeframe to identify the contractual basis of a claim. 

31.  In any event, however much sympathy the contractor may deserve, Clause 21 employs clear and mandatory language for the service and contents of the notices to be served, with no qualifying language such as “if practicable”, or “in so far as the sub-contractor is able” (cf Multiplex Construction (UK) Ltd v Honeywell Control Systems (No 2) [2007] 111 Con LR 78).  As the passage in Keating on Construction Contracts recognizes, exemption clauses in construction contracts should be seen as part of the contractual apparatus for distributing risk.  There is commercial sense in allocating risks and attaining finality by designating strict time limits for claims to be made and for the contractual basis of claims to be specified.  In particular, the language used in Clause 21.1 is in my view clear on its plain reading, and the decisions in Rainy Sky SA v Kookmin Bank [2011] UKSC 50 and Arnold v Britton [2015] AC 1619 highlight the importance of the language used in the provision to be construed, notwithstanding the need to read such language in the proper factual and commercial context.  There is no basis for a court or tribunal to rewrite the Sub-Contract or Clause 21 for the parties after the event. 

32.  If, on the facts of a particular case, a claim of waiver or estoppel may be made as a result of the way in which the parties had conducted themselves in relation to a claim or claims made and notified, that may well be pleaded and raised in the Arbitration but it should not affect the construction of a contractual provision which is clear and unambiguous on its face as to its requirements and the effect of non-compliance with its requirements. 

33.  I come to the conclusion that on proper construction of Clause 21 of the Sub-Contract, the Defendant had failed to give proper notice under Clause 21.2, and that the Arbitrator’s decision to allow the Defendant’s claim of “like rights” was wrong in law.

The valuation of variation question

34.  The Defendant contended in the Arbitration, and the Arbitrator accepted, that the deferment of the Area 1a panels for the diaphragm wall constituted a variation under the Sub-Contract (“Variation”).  The Arbitrator proceeded to assess the value of the Variation, including the Defendant’s claim for standby of the plant and equipment required for the diaphragm wall for the period from 19 May to 4 July 2012. 

35.  The relevant contractual provision for valuation is S-CC 19 of the Sub-Contract (“Clause 19”), which is set out below.

“19.1 The value of any Variation, Sub-Contract Variation or Sub-Contract Change required pursuant to Clause 17 to be implemented by the Sub-Contractor shall be ascertained and determined by the Contractor in accordance with the following principles:

19.1.1 any work added or omitted which is the same as or similar in character to and executed under the same or similar conditions to any item of work priced in the Sub-Contract Pricing Document shall be valued at the Sub Contract Rate for that item of work. Provided that if the nature or extent of any Variation or Sub-Contract Variation relative to the nature and extent of the whole of the Sub-Contract Works shall be such that any Sub-Contractor Rate for any item of work is rendered unreasonable or inapplicable in such manner that the Sub-Contractor is unable to achieve the same return on his employed resourced as if such work would have not varied, such Sub-Contract Rate shall be varied and a new rate shall be determined taking into account all the relevant circumstances as may be reasonable and appropriate;

19.1.2  any work added which is not the same as or of a similar character or is not executed under similar conditions to work priced in the Sub-Contract shall be valued at a rate or price based on the Sub-Contract Rates so far as may be reasonable, failing which, at a rate or price agreed between the Parties as being a fair and reasonable rate or price. If the Parties are unable to agree a fair and reasonable rate or price, such rate or price shall be determined by the Contractor for preliminary and interim provisional payment until the final rate will have been agreed mutually or under the dispute regulation/determination.”

36.  Notwithstanding the fact that, as the Arbitrator found (in paragraph 672 of the Award), the plant and equipment in question was in storage during the relevant period and was not in use, the Arbitrator valued the Variation on the basis of “cost plus OH&P (overheads and profit)” (paragraph 679 of the Award), and accepted the cost, OH&P figure of HK$3,991,333 on the expert evidence adduced by the Defendant.

37.  According to the Plaintiffs, the Arbitrator was in error to include as “cost” an amount not actually incurred by the Defendant, when the Arbitrator stated that he was using a “cost plus” valuation approach (paragraph 679 of the Award).

38.  The Plaintiffs pointed out that Clause 19 provides in essence for “fair valuation”, but allowing the Defendant to recover a considerable sum for the value of the plant which the Defendant did not own and did not actually incur any costs nor make any payment for, together with overheads and profit, results in a windfall for the Defendant which is not fair to the Plaintiffs.  The Plaintiffs emphasized that the equipment was in storage, was not operating at all, and that it would not cost anything to the Defendant, for the purposes of valuation.

39.  Both the Plaintiffs and the Defendant referred to various legal authorities and text books in support of what they contend to be the correct method of valuation, but it appears from these authorities that there is no fixed rule as to how variations should be valued.

40.  The Plaintiffs rely on Max Abrahamson’s Engineering Law and the ICE Contracts, 4th Edition, and contend that a “fair valuation” normally means cost plus a reasonable percentage for profit.  Reliance is also placed on the judgment in Henry Boot Construction v Alstorm Combined Cycles Ltd [1999] BLR 123 at 137, where it is stated:

“A fair valuation when used as an alternative to a valuation by, or by reference to, contract rates and prices generally means a valuation which will not give the Contractor more than his actual costs reasonably and necessarily incurred plus similar allowances for overheads and profit - for anything more would confer on him an additional margin for profit and would not be fair to the Employer.” (Emphasis added)

41.  In FloodsofQueensferry Ltd v Shand Construction Ltd [1999] 319 at 324, the same judge stated:

“Where, in general, contract rates and prices are not available or appropriate and where the contractor’s actual costs of labour, plant and materials reasonably and properly incurred can be established with an acceptable degree of certainty then those figures, together with an appropriate addition for site and head office overheads and profit, would produce a fair and reasonable valuation.” (Emphases added)

42.  It should be borne in mind that under the contractual framework provided for in Clause 19, for any work added which is not the same or of a similar character or is not executed under similar conditions to work priced in the Sub-Contract, the value of the variation is to be ascertained at “a rate or price based on the Contract Rates so far as may be reasonable, failing which, at a rate or price agreed between the parties as being a fair and reasonable rate or price”.  Under Clause 19.1.2, if the parties are unable to agree “a fair and reasonable rate or price”, the final rate or price is to be agreed or determined under the dispute determination. 

43.  At paragraph 4-037 of Keating on Construction Contracts 10th Edition, the learned author stated, in the context of assessment of “a reasonable sum”:

“The courts have laid down no rules limiting the way in which a reasonable sum is to be assessed. Different considerations can arise depending on whether the claim is for a quantum meruit in the absence of a contract or a reasonable price payable within a contractual framework. Where a quantum meruit is recoverable for work done outside an existing contract, the work cannot generally be regarded as though it had been performed to any extent under the contract. A restitutionary award made on the basis of unjust enrichment should be calculated as the value of the benefit received by the defendant at the expense of the claimant. The enrichment should be valued at the time it was received and, where the benefit was in the form of services, the starting point was normally the objective market value of the services, tested by the price which a reasonable person in the defendant’s position would have had to pay for them and taking into account conditions which increased or decreased their objective value to any reasonable person in that position….

In relation to construction contracts, the starting point should be that the contractor should be paid at a fair commercial rate for the work done but taking account of any applicable conditions as described above.”

44.  In the case of Laserbore Limited v Morrison Biggs Wall Limited [1993] Lexis Citation 2055 25th of August 1993, the Court construed an agreement to “reimburse” the contractor “fair and reasonable payment for all works executed and agreed” as meaning a liability to pay the contractor costs plus profit and overheads.  On assessment of the amount payable, the plaintiff-contractor’s expert attempted to assess “reasonable rates” while the defendants’ expert considered the matter on a “costs plus” basis.  In deciding the “fair and reasonable payment” to which the contractor is entitled, the court referred to the statement in the 10th edition of Hudson’s Building and Engineering Contracts:

“In practice, in determining a reasonable price, the courts may act upon evidence calculated upon the cost of labour, plant and materials plus a reasonable percentage for profit, or they may act upon evidence of what reasonable rates or prices for the physical work involved would be. This is a perennial problem in the conduct of building litigation arising out of less formal contracts or disputed variations and there is no general rule of practice with regard to it. The decision may depend upon the nature and amount of the work involved, or upon whether the work has been actually carried out, or is hypothetical work, eg in a claim for damages for loss of profit, or upon the nature of the issues raised between the parties, and will be influenced by considerations of convenience from the evidentiary point of view. As stated, some work is, of course, by its nature incapable of accurate measurement by means of rates.”

45.  In Laserbore, the judge considered that the better approach (citing Keatingon Building Contracts and Greenmast Shipping Co v Jean Lion et Cie (The Saronikos) [1986] 2 Lloyd’s Rep 277 at 279) was to ask, “What would be a fair commercial rate for the services provided?” Referring to the “reasonable rates” basis and the “costs plus” basis of the experts, the judge then stated:

“I am in no doubt that the costs plus basis in the form in which it was applied by the defendant’s quantum expert (though perhaps not in other forms) is wrong in principle even though in some instances it may produce the right result.  One can test it by example.  If a company’s directors are sufficiently canny to buy materials for stock at knockdown prices from a liquidator, must they pass on the benefit of their canniness to their customers?  If a contractor provides two cranes of equal capacity and equal efficiency to do an equal amount of work, should one be charged at a lower rate than the other because one crane is only one year old but the other is three years old?  If an expensive item of equipment has been depreciated to nothing in the company’s accounts but by careful maintenance the company continues to use it, must the equipment be provided free of charge apart from running expenses (fuel and labour)?  On the defendants’ argument, the answer to those questions is, “Yes”. I cannot accept that that begins to be right.”

46.  Leading Counsel for the Defendant emphasized that valuation, as opposed to assessment of damages, is a contractual entitlement and does not require proof of loss.  He referred to paragraph 298 of the judgment in Floods of Queensferry, where the judge stated:

“Thus FOQ is not entitled to recover as part of any damages for breach of contract the cost of any plant or management services covered by any credit note. Its other claims are unaffected since valuation is a contractual entitlement and does not require proof of actual loss.”

47.  The Defendant further relies on Sergeant and Wieliczko’s Construction Contract Variations, 2014 Edition, where the authors state at paragraphs 11.78:

“Most contracts provide that, if contract rates and prices are inappropriate, a “fair” or “reasonable” valuation should be undertaken. …

Such terms as “fair” and “reasonable” are, of course, very vague. In practice such an assessment is likely to be undertaken in one of 2 ways:

• Cost-based analysis. It is possible to undertake the analysis by asking what the variation work has actually caused, or what it would cost the contractor. Such an approach may be tempered by allowing only reasonably incurred costs. Overhead and profit may be added. Certain contracts specifically stipulate such a cost-based approach.

• Market rate analysis.  Rather than asking what the work cost, an alternative approach is to ask what the market price for the additional work is.  Evidence of the market rate for work can be sought, or a party could use its company’s norms or published pricing books to justify sums claimed.”

48.  The learned authors conclude at paragraph 11.90 as follows:

“If a valuation is undertaken by reference to cost, this raises questions as to the evidence that needs to be provided by a contractor to justify payment. The right to be paid for a variation is contractual and the valuation process exists to determine the level of the contractor’s entitlement for the changed work it has been instructed to undertake. A variation provision does not normally provide for the compensation of loss, as may be the case with other contract mechanisms, such as the loss and expense provision. Under a variation clause “valuation is a contractual entitlement and does not require proof of actual loss”. In most cases a valuation will be undertaken using extrapolated rates and therefore the question of a contractor proving what costs it has incurred does not arise. Since proof of actual loss should not be required, it could be said that establishing “cost” should involve assessing what certain work would have cost it, rather than having to prove what the work did cost.” (Emphases added)

49.  I accept the submissions made on behalf of the Defendant, that the Arbitrator’s decision on the valuation of the Variation is a mixed question of law and fact.  The Arbitrator received and considered evidence from the parties and their experts on the nature of the work involved, and the costs and value asserted by the Defendants and examined by the Experts, and concluded on all the evidence available before him that the quantification of HK$3,991,333 represents the “fair and reasonable rate” to be decided and allowed under Clause 19.  He stated at paragraph 684 of the Award:

“Whilst it seems that Bauer did not have to pay for the items of plant during the period, I am concerned with valuation of a variation and the issue of whether a party has or has not paid for a piece of plant does not determine the issue of the value of the piece of plant.  I consider that in valuing the variation it is the “cost” in terms of what it would cost which is the relevant information and that the issue does not depend on questions of payment.”

50.  On review of the authorities, it cannot be said that the Arbitrator had misdirected himself in law, or that his decision was outside the permissible range of solutions which were open to him (Cosemar SA v Mariamararna Shipping Co Ltd (The “Matthew”) [1990] 2 Lloyd’s Rep 323).

Disposition

51.  The appeal on the first question of law on notice compliance is allowed.  The appeal on the second question of law on variation valuation is dismissed.

52.  A fair costs order nisi would be for the Defendant to pay to the Plaintiffs 50% of the costs of the appeal. 

 
 

 (Mimmie Chan)
 Judge of the Court of First Instance
High Court

  

Mr Peter Clayton SC, instructed by Pinsent Masons, for the 1st and 2nd plaintiffs

Mr Anthony Houghton SC and Mr James Niehorster, instructed by Bryan Cave Leighton Paisner LLP, for the defendant

[2018] HKCFI 2001-EN-2018-08-30

MAEDA KENSETSU KOGYO KABUSHIKI KAISHA also known as MAEDA CORPORATION AND ANOTHER v. BAUER HONG KONG LTD

HTML content

HCCT 4/2018

[2018] HKCFI 2001

IN THE HIGH COURT OF THE

HONG KONG SPECIAL ADMINISTRATIVE REGION

COURT OF FIRST INSTANCE

CONSTRUCTION AND ARBITRATION PROCEEDINGS

NO 4 OF 2018

______________

 IN THE MATTER of the Arbitration Ordinance (Cap 609)
 and
 IN THE MATTER of an Arbitration

______________

BETWEEN  
 MAEDA KENSETSU KOGYO KABUSHIKI KAISHA also known as MAEDA CORPORATION 1st Plaintiff
(1st Respondent in the Arbitration)
 CHINA STATE CONSTRUCTION ENGINEERING (HONG KONG) LIMITED 2nd Plaintiff
(2nd Respondent in the Arbitration)
(together as the “Plaintiffs”)
 and 
 BAUER HONG KONG LIMITED Defendant
(Claimant in the Arbitration)

______________

Before:  Hon Mimmie Chan J in Chambers

Dates of Written Skeleton Submissions:  7, 14 & 21 August 2018

Date of Decision:  30 August 2018

______________

D E C I S I O N

______________

1.  This is an application made by the Plaintiffs for leave to appeal against the 2nd Interim Award of the Arbitrator published on 3 January 2018, as corrected on 3 March 2018 (“Award”). The application is made pursuant to s 6 (1) (b) of Schedule 2 (“Schedule”) to the Arbitration Ordinance (“Ordinance”), and 4 questions of law were identified for the intended appeal.

2.  Under s 6 (3) of the Schedule, the Court “must” determine an application for leave to appeal without a hearing unless it appears to the Court that a hearing is required.  Under s 6 (4), leave to appeal is to be granted only if the Court is satisfied that (a) the decision of the question will substantially affect the rights of one or more of the parties; (b) the question is one which the arbitral tribunal was asked to decide; and (c) on the basis of the findings of fact in the award, the decision of the tribunal on the question is “obviously wrong”; or the question is one of general importance and the decision of the tribunal is “at least open to serious doubt”.

3.  Pursuant to directions of the Court, written submissions (confined to 8 pages for each party) were filed on behalf of the parties in support and in opposition to the application.  The Court further directed that no hearing is required.

4.  The directions of the Court, and the provisions of s 6 (3) of the Schedule, are in line with the objectives of the Ordinance, set out in s 3, to facilitate the fair and speedy resolution of disputes by arbitration without unnecessary expense, and the principles that, subject to the observance of the safeguards that are necessary in the public interest, the parties to a dispute should be free to agree on how the dispute should be resolved, and that the Court should interfere in the arbitration of the dispute only as expressly provided for in the Ordinance.

5.  It has to be borne in mind that an application for leave to appeal on a question of law arising out of an award is a filtering process.  As highlighted in the decision of Mustill J (as His Lordship then was) in Vinava Shipping Co Ltd v Finelvet AG (The “Chrysalis”) [1983] 1 Lloyd’s LR 503, the court at the first stage, of the application for leave, gives effect to the policy whereby “the interests of finality are placed ahead of the desire to ensure that the arbitrator’s decision is strictly in accordance with the law.” As His Lordship explained:

“Some examination of the merits takes place at this stage, because the stronger the applicant’s case for saying that the arbitrator was wrong, the better his prospect of obtaining leave to appeal. But the examination of the law is summary in nature, and does not lead to any definite conclusion. The exercise is discretionary throughout; the mesh of the filter is fine; and it must, I think, he recognized that some cases will be caught in the filter which would, if the appeal had been allowed to go forward, result in a decision that the award could not stand.”

6.  The objectives of the Ordinance and the structure prescribed under s 6 of the Schedule (including the high threshold for granting leave to appeal) reflect the important consideration that the parties had chosen to resolve their dispute by arbitration and to put their dispute before an arbitrator of their choice, often an arbitrator with the relevant experience and expertise to determine the particular issues which had arisen in the dispute.  As the learned judge in the case of A v B [2017] EWHC 3557 (Comm) observed (at paragraph 13 of the judgment), and with whom I respectfully agree, the court dealing with an appeal against an arbitrator’s decision on a question of law has to approach the matter with care: “care to respect the choice of the parties to resolve this dispute by arbitration; care to respect the proper province of the, here, very experienced tribunal; and care - in the course of according that respect - to have full regard of the views they felt able to reach, on matters of business sense or commercial sense that form an important dimension of the context within which a decision - which is a decision of law - is to be reached on the true interpretation of the (relevant contract)”. 

7.  In the present case, there is no dispute that the questions for which leave to appeal is currently sought were questions which the tribunal had been asked to decide.  These questions, as identified in this application for leave, relate to:

(1)  idling deduction and the construction of paragraph 1 (f) of Section C of the Sub-Contract Schedule of Prices;

(2)  whether there was compliance with the condition precedents to give notice under Clause 21.1 and 21.2 of the Sub-Contract;

(3)  the founding levels and criteria under the Sub-Contract and whether there was variation under the Sub-Contract;

(4)  the valuation of variation of works under the Sub-Contract.

Idling

8.  The 1st question of law is the interpretation of paragraph 1 (f) of Section C of Part IV of the Appendix to the Sub-Contract, which relates to the measurement of items of work under the Sub-Contract.  The Sub-Contract Schedule of Price sets out the rates for items of work, and refers to a rate for “standby and/or idling per rig”.  The relevant paragraph 1 (f) of Section C (under “General Preambles and Particular Preambles”) (“Para 1 (f)”) states as follows:

“The item of ‘standby and/or idling per rig’ shall only be measured if the delay is proved to be caused by the Engineer’s fault and the rate is deemed to include for the relevant plant operator(s) and associated plants and equipments. For clarity and cite of an example, any delay of the Sub-Contract Works which is proved to be caused by the unforeseen obstructions and/or utilities, and/or the Contractor’s fault etc, the actual loss (ie net costs and expenses) shall be reimbursed to the Sub-Contractor by the Contractor. It is also expressly agreed that the following items shall not be measured under the Sub-Contract: (1) time of idling of resources for archaeological investigation as stipulated under the Contract; and (2) the first twenty four (24) hours of time of idling of resources for reasons other than the Engineer’s responsibility. The Sub-Contractor shall be entitled for payment under the Sub-Contract, cumulative from the commencement of and up to the completion of the Sub-Contract Works.”

9.  As identified by the Arbitrator at paragraph 429 of the Award, the issue between the parties was whether the 24 hour period of deduction applies to each event of idling, as the Plaintiffs contend, or to all events of idling cumulatively, as the Defendant contends.

10.  I accept that this question substantially affects the rights of the parties.  The Award includes the Defendant’s claims for idling as well as additional time spent which includes idling time.  If the Arbitrator is shown to have erred in his interpretation of Para 1 (f), the Award would be reduced by a significant sum, to substantially affect the rights of both parties.

11.  It has not been asserted that the 1st question of law is a matter of general importance.  As such, the applicable test for granting leave to appeal is that the decision of the Arbitrator has to be “obviously wrong”.

12.  I do not agree with the Plaintiffs that the Arbitrator had failed to apply the applicable principles of contractual construction: to undertake a unitary process, checking a putative meaning against the commercial context, the commercial purpose and the commercial consequences.  As can be seen from paragraphs 430 to 439 of the Award, this was exactly what the Arbitrator did, after considering the submissions made by the parties on the basis of the decisions in ICS v West Bromwich [1998] 1 WLR 896, Rainy Sky SA v Kookmin Bank [2011] UKSC 50, Norwich Union Life and Pensions v Linpac Moldings Ltd [2009] EWHC 1602 (Ch), Arnold v Britton [2015] AC 1619, and Wood v Capita Insurance Services Ltd [2017] UKSC 24.

13.  The parties’ submissions on common sense and the commercial realities affecting the interpretation of Para 1 (f) were referred to, and considered by the Arbitrator.  At paragraph 438, the Arbitrator considered the plain reading of the provision, and found that “it is the first 24 hours of time of idling of resources for reasons other than the Engineer’s responsibility which are not measured, and that the 24 hour period applies to the first 24 hours of all idling and is not applied to each period of idling”.  From this, it can be seen that the Arbitrator considered the meaning to be clear from the plain reading of the relevant provision, including the references to “any delay”.  Nevertheless, the Arbitrator went on to say that “if there had been ambiguity”, and he had to turn to business common sense, then he considered that business common sense would favor there being a reduction from the total hours of idling rather than from each and every idling occurrence.  His analysis was set out in paragraph 439.

14.  I do not agree that the Arbitrator can fairly be said to have approached the interpretation of the contractual provision incorrectly, by reaching his decision “purely on a plain reading of the provision”.  The decisions in Rainy Sky and Arnold Britton highlight the importance of the language used in the provision to be construed, notwithstanding the need to read such language in the proper factual and commercial context.  The language in Para 1 (f) was considered as it was actually used (“the first twenty four (24) hours of time of idling”, as opposed to “the first twenty four (24) hours of time of each idling”, and the Arbitrator considered that on its plain reading, the provision does not apply to each period of idling.

15.  The decision of the Arbitrator on the construction of Para 1 (f) took into consideration the fact that the “24 hours rule” applies in order to cut down the liability of the Plaintiffs to pay for the works of the Defendant, such that in the case of any ambiguity in the construction of the provision, Para 1 (f) should be given a more confined meaning in preference to a broader meaning (paragraph 439 of the Award).  I agree with the Defendant, that the Arbitrator is entitled to take such a view, as supported by Nobahar-Cookson v Hut Group Ltd [2016] EWCA Civ 128, the rationale being that parties are not lightly to be taken to have intended to give up valuable rights without making it clear that they intend to do so, or to cut down remedies which the law provides for breach of important contractual obligations, without using clear words having that effect.  It cannot be shown that the Arbitrator is “obviously wrong” to have given consideration to the “cutting down of liability” effect of Para 1 (f).

16.  The Arbitrator did (in paragraph 439 of the Award) consider the commercial or business sense of the alternative constructions.  Bearing in mind that the entire commercial context of the Sub-Contract had been presented to and argued before the Arbitrator, I cannot say on my reading of paragraphs 428 to 440 of the Award that the Arbitrator’s construction of Para 1 (f) is not in tune with the commercial reality of the case as compared to the rival construction suggested by the Plaintiffs.   

17.  As the courts sought to explain in Arnold v Britton (paragraphs 17, 19-20 of the judgment), commercial common sense should not be invoked to undervalue the importance of the language of the provision to be construed, and commercial common sense should not be invoked retrospectively, as it is not the function of the court when interpreting an agreement to relieve a party from the consequences of an imprudent term or arrangements which are ill advised, nor to rewrite the contract for the parties to achieve a result which the court considers more desirable. 

18.  It may well be that the “24 hours rule” in Para 1 (f) was already the result of a balancing made, at the time of the Sub-Contract, of the respective interests of, and likely prejudices to, the paying party on the one part and the party to be paid on the other part, after consideration of the relevant factual circumstances known to the parties at the time of the Sub-Contract: such as the length of the contract period, the wide range of resources required, the pricing, etc.

19.  It cannot be seen, from the Arbitrator’s analysis in paragraphs 438 and 439 of the Award, that the Arbitrator’s decision on the construction of Para 1 (f) is “obviously wrong”. 

Notice Compliance

20.  The 2nd question of law relates to whether Clause 21 of the Sub-Contract had been complied with, so as to entitle the Defendant to claim against the Plaintiffs for additional sums due under the Sub-Contract.

21.  The Defendant was awarded around HK$x for claims made on the basis of unforeseen ground conditions, in addition to being awarded substantial extension of time and prolongation costs for the additional time spent in excavation.  Its entitlement to these substantial amounts depends on the proper interpretation of Clauses 21.1 and 21.2 of the Sub-Contract.  I accept that the decision of the application for leave will substantially affect the rights of the parties.

22.  Clause 21 reads as follows:

“21.1 If the Sub-Contractor intends to claim any additional payment or loss and expense pursuant due to:

21.1.1 any circumstances or occurrence as a consequence of which the Contractor is entitled to additional payment or loss and expense under the Main Contract;

21.1.2 any alleged breach of the Sub-Contract, delay or prevention by the Contractor or by his representatives, employees or other sub-contractors;

21.1.3 any claim for discrepancy between Sub-Contract Drawings and documents pursuant to Clause 8.4;

21.1.4 any claim under Common Law, statute laws or by-law;

21.1.5 any extension of time granted to the Sub-Contractor with exception to those cases which the delay are caused by typhoon signal no. 8 and/or force majeure etc.

21.1.6 any Variation of Sub-Contract Variation,

as a condition precedent to the Sub-Contractor’s entitlement to any such claim, the Sub-Contractor shall give notice of its intention to the Contractor within fourteen (14) days after the event, occurrence or matter giving rise to the claim became apparent or ought reasonably to have become apparent to the Sub-Contractor. For the avoidance of doubt, the Sub-Contractor shall have no entitlement to any additional payment or any additional loss and expense and no right to make any claim whatsoever for any amount in excess of the Sub-Contractor Sum in respect of any event, occurrence or matter whatsoever unless this Sub-Contractor sets out an express right to that additional payment, additional loss and expense or claim.

21.2 If the Sub-Contractor wishes to maintain its right to pursue a claim for additional payment or loss and expense under Clause 21.1, the Sub-Contractor shall as a condition precedent to any entitlement, within twenty eight (28) Days after giving of notice under Clause 21.1, submit in writing to the Contractor:

21.2.1 the contractual basis together with full and detailed particulars and the evaluation of the claim;

21.2.2 where an event, occurrence or matter has a continuing effect or where the Sub-Contractor is unable to determine whether the effect of an event, occurrence or matter will be continuing, such that it is not practicable for the Sub-Contractor to submit full and detailed particulars and the evaluation in accordance with Clause 21.2.1, a statement to that effect with reasons together with interim written particulars. The Sub-Contractor shall thereafter, as a condition precedent to any entitlement submit to the Contractor at intervals of not more than twenty eight (28) Days (or at intervals necessary for the Contractor to comply with his obligations under the Main Contract, whichever is shorter) further interim written particulars until the full and detailed particulars are ascertainable, whereupon the Sub-Contractor shall as soon as practicable but in any event within twenty eight (28) Days (or as necessary for the Contractor to comply with his obligations under the Main Contract, whichever is shorter) submit to the Contractor full and detailed particulars and the evaluation of the claim;

21.2.3 details of the documents and any contemporary records that will be maintained to support such claim; and

21.2.4 details of the measures which the Sub-Contractor has adopted and proposes to adopt to avoid or reduce the effects of such event, occurrence or matter which gives rise to the claim.

21.3 The Sub-Contractor shall have no right to any additional or extra payment, loss and expense, any claim for an extension of time or any claim for damages under any Clause of the Sub-Contract or at common law unless Clauses 21.1 and 21.2 have been strictly complied with.”

23.  The question of law identified in the application for leave is whether the Defendant’s notification of a claim for unforeseen ground conditions, on a contractual basis of variation, could constitute proper notice as required under Clause 21.2.1, for the Defendant’s claim for unforeseen ground conditions on the contractual basis of like rights in the arbitration - and on the basis of which the Award was made.

24.  Service of notice under Clause 21 is expressed as a condition precedent. The Plaintiffs claim that the construction of Clause 21 is of general importance to the construction industry in Hong Kong, as the notification of claim provision is commonly used in the construction industry, and there are identical or similar provisions contained in the standard form conditions of contract used by the MTR Corporation for major projects, such as the Express Rail Link and the Shatin to Central Link, and by the Hong Kong Government and the Hong Kong Institute of Architects for their building projects in Hong Kong.

25.  The Defendant has pointed out that the language used in Clause 21 is in fact different to the language used in the notification of claim clauses used in the standard form contracts referred to by the Plaintiffs as being employed for projects of the MTR Corporation, the Government or the Institute.  Yet, I am prepared to accept the submissions made on behalf of the Plaintiffs, that despite the absence of identical wording, these notification of claim clauses may be compared in the sense that construction of one version of such clause may be of relevance in the construction of another version of such clause.  The notification of claim provision is of sufficient general prevalence, to be of general importance in the construction industry.  I am prepared to accept the test of “at least open to serious doubt” applicable under s 6 (4) (c) of the Schedule to the Ordinance.

26.  The Plaintiffs have highlighted that in the arbitration, the primary case of the Defendant was that the unforeseen ground conditions gave rise to a variation of the work scope under the Sub-Contract, so as to entitle the Defendant to claim additional payment under the express variation provisions in the Sub-Contract.  In the alternative, the Defendant had made a “like rights” claim under Clause 21.1.1 of the Sub-Contract. The Arbitrator rejected the Defendant’s primary claim, that the actual ground conditions gave rise to a variation.  This can be seen from paragraph 177 of the Award.

27.  However, the Arbitrator found in favor of the Defendant on the unforeseen ground conditions claim on the basis of a “like rights” entitlement. He found (paragraph 330 of the Award) that the Defendant had sent letters on 1 and 2 August 2011, which constitute the requisite notices under Clause 21.1, and further found (paragraph 334) that the Defendant had sent further letters and details of the claims on 19, 20 and 25 August 2011, and at the latest by 29 August 2011, so as to have complied with Clause 21.2.2.  This was on the basis of the Arbitrator’s finding that the notice required under Clause 21.1 is simply a notice of intention to claim, without the need to specify which of Clauses 21.1.1 to 21.1.6 the claim is made under. 

28.  At paragraph 332 of the Award, the Arbitrator stated:

“I consider that both as a matter of sympathy and as a matter of construction, the contractual basis of the claim stated in the Clause 21.2 notice does not have to be the contractual basis on which the party in the end succeeds in an arbitration. First, to expect a party to finalize its legal case within the relatively short period and be tied to that case through to the end of an arbitration is unrealistic. Secondly, what is important from the point of view of the contractor is to know the factual basis for the claim so that it can assess it and decide what to do.”

29.  The Arbitrator further stated in paragraph 334 that to the extent needed for a Clause 21.2.2 notice, the Defendant’s letter of 29 August 2011 referred to the “contractual basis” although that did not prevent the Defendant from pursuing the claim on a different contractual or legal basis.  His conclusion was that although the Defendant had made its claims on the basis of a variation, the Defendant was still able to make the claim on a new contractual or legal basis, based on the notices given by reference to a different basis.

30.  The service of notice of intention to claim and the written submission of the contractual basis of the claim are both expressed in Clause 21.1 and Clause 21.2 to be “condition precedents”.  Further, Clause 21.3 expressly and clearly provides for the loss of right as a result of non-compliance with the notice requirement, by stating that the Sub-Contractor “shall have no right” to any additional or extra payment, loss and expense, any claim for an extension of time or for damages, “unless Clauses 21.1 and 21.2 have been strictly complied with”.  On its plain reading, the Defendant has no right under Clause 21.3 to any additional payment, loss and expense or any claim for damages under the Sub-Contract, if Clause 21.2 was not complied with “strictly”. If there was no submission in writing made in compliance with Clause 21.2, by giving the contractual basis of a claim to be pursued, there cannot be a claim which can be made, or pursued in the arbitration.

31.  On the materials before me, I consider that the decision of the Arbitrator as to compliance with the conditions set out in Clause 21, for a claim to be pursued and an award to be made, is open to serious doubt, such that leave to appeal should be granted.

Founding levels

32.  The 3rd question of law relates to the Arbitrator’s finding that the founding levels determined from the pre-drill results and accepted by the Engineer at that stage formed the prescribed Sub-Contract Works, so that any further excavation constituted a variation.

33.  There is no claim that the 3rd question of law identified is a matter of general importance.  The threshold of “obviously wrong” is therefore applicable, for leave to appeal to be granted.

34.  Sub-Contract Drawing No 823B/T/000/OAP/C01/004B provides for the “permanent diaphragm wall founding criteria”, and states that “all permanent diaphragm walls shall satisfy either of the following founding criteria”, as therein set out.  Essentially, the criteria require the diaphragm wall panels to be founded in category 1 (c) rock, or category 1 (d) rock.

35.  The Plaintiffs placed reliance on and maintain the significance of the fact that the founding levels shown on the contract drawings were stated to be “tentative only”.  They maintain that it was the obligation of the Defendant to excavate until suitable founding material was encountered to verify the founding level required under the Sub-Contract.  The Plaintiffs refer to drawing 823B/T/000/OAP/C001/003B, which provides as follows:

“All founding levels of diaphragm wall panels shown on the drawings are tentative only. For diaphragm wall panels acting as temporary works, the contractor shall propose the founding level of each diaphragm wall panel and his temporary works design which shall be subject to the acceptance of the Engineer prior to diaphragm wall construction. For permanent diaphragm walls, the contractor shall propose the founding level of each diaphragm wall panel which shall satisfy the founding criteria of permanent diaphragm wall as specified and drawing no 823B/T/000/C01/004. The accepted founding levels shall be further verified for approval by the Engineer on site during excavation of each diaphragm wall panel.” (Emphasis added)

36.  It cannot be disputed that the tentative founding levels specified in the Sub-Contract Drawings were based on assumed rock profiles.  The Plaintiffs argued that there was a two-stage process to be followed to ascertain the founding levels.  Before excavation, the Defendant was required to carry out pre-drilling to identify the likely depth of rock head and hence the tentative level to which the Defendant would need to excavate.  Then, when excavation reached the tentative level, the material extracted was inspected by the Engineer to verify, for his acceptance that the relevant specified founding criteria had been achieved and, if not, further excavation had to be carried out in order to achieve it.

37.  Essentially, the Plaintiffs argued that the Engineer’s acceptance on verification of the founding level proposed by the Defendant was only part of the verification process, and that the Arbitrator was wrong in finding that one of the steps necessary for ensuring that the panels were founded in the contractual category 1 (c) or 1 (d) level can amount to a variation. 

38.  I have carefully reviewed paragraphs 228 to 265 of the Award, which set out the Arbitrator’s identification of the issues in dispute between the parties, the submissions made by the parties, his analyses of the relevant Sub-Contract Drawings and the notes thereto, and his findings on the purpose and effect of the relevant Sub-Contract provisions on the founding level criteria, the contractor’s proposal of the founding level, the verification process, and the Engineer’s acceptance of the founding levels. 

39.  The Arbitrator accepted that the founding levels shown in the relevant drawings were tentative.  He found that the detailed contractual procedure to establish the founding levels was that first, the Contractor had to propose the founding level of each wall panel for acceptance by the Engineer.  To propose the founding level, there was to be pre-drilling, the purpose of which was to establish the founding levels based on the specified founding criteria.  The appropriate founding criteria, based on the ground investigation by pre-drilling, would then be used to establish the level proposed by the Contractor.  The Arbitrator considered that the use of pre-drilling was recognized in the GEO Publication No 1/2006.  The further verification of the accepted founding levels, on site and during excavation, was considered by the Arbitrator to be for the purpose of verifying that the material at the founding level was consistent with the contractually prescribed category 1 (c) or 1 (d) material, but at that stage, the original and tentative founding levels had already been replaced by the founding levels accepted by the Engineer, such that if the Engineer should decide that further and additional work was required, that was a change in the accepted founding level, to amount to a variation.

40.  I regret that I cannot see, from the Arbitrator’s analysis, that he can be said to be “obviously wrong”.  This is a high threshold, and I pay heed to the observations made in paragraphs 5 and 6 of this Decision.

Valuation of variation at cost

41.  The last question of law identified is the Arbitrator’s finding that in respect of a variation for the construction of the diaphragm wall panels located at Kam Tin Road, the variation should be valued at “‘cost’ plus OH&P”, which he assessed and allowed at an amount which included an item of “cost” of equipment, which was not actually incurred by the Defendant.

42.  The Defendant was awarded around HK$y for the variation, and as this is a substantial sum, I accept that the decision substantially affects the rights of the parties.

43.  The valuation was made pursuant to clause 19 of the Sub-Contract.  This provides as follows:

“19.1 The value of any Variation, Sub-Contract Variation or Sub-Contract Change required pursuant to Clause 17 to be implemented by the Sub-Contractor shall be ascertained and determined by the Contractor in accordance with the following principles:

19.1.1 any work added or omitted which is the same as or similar in character to and executed under the same or similar conditions to any item of work priced in the Sub-Contract Pricing Document shall be valued at the Sub Contract Rate for that item of work. Provided that if the nature or extent of any Variation or Sub-Contract Variation relative to the nature and extent of the whole of the Sub-Contract Works shall be such that any Sub-Contractor Rate for any item of work is rendered unreasonable or inapplicable in such manner that the Sub-Contractor is unable to achieve the same return on his employed resourced as if such work would have not varied, such Sub-Contract Rate shall be varied and a new rate shall be determined taking into account all the relevant circumstances as may be reasonable and appropriate;

19.1.2  any work added which is not the same as or of a similar character or is not executed under similar conditions to work priced in the Sub-Contract shall be valued at a rate or price based on the Sub-Contract Rates so far as may be reasonable, failing which, at a rate or price agreed between the Parties as being a fair and reasonable rate or price. If the Parties are unable to agree a fair and reasonable rate or price, such rate or price shall be determined by the Contractor for preliminary and interim provisional payment until the final rate will have been agreed mutually or under the dispute regulation / determination.”

44.  The Defendant pointed out that Clause 19 of the Sub-Contract was the subject of negotiations between the parties which resulted in amendments to the provisions of the clause.  The Defendant highlights the point that Clause 19 is differently worded to the variation provision contained in the Main Contract.  It also points out that the standard form contracts referred to by the Plaintiffs incorporate valuation provisions which are not in fact identical to those in Clause 19.

45.  Nevertheless, the standard form contracts used by the Government, the Hong Kong Airport Authority and the Institute of Surveyors/Architects adopt variation provisions which refer to valuation at “fair rates”, or “fair valuation” or to rates “as may be reasonable”.  I therefore accept that the construction of the meaning of variation at rates “as may be reasonable”, or “as being a fair and reasonable rate” is a matter of general importance to the construction industry.  I adopt the threshold of “at least open to serious doubt” for granting leave to appeal.

46.  At paragraphs 679 and 680 of the Award, the Arbitrator referred to the difference in the valuation of the variation work, as made by the expert for the Plaintiffs and the expert for the Defendant.   The cost of the equipment included by the Defendant’s expert was considered to be unreasonable by the Plaintiffs’ expert, because the Defendant in fact incurred no costs in respect of such equipment.  At paragraph 684 of the Award, the Arbitrator stated:

“Whilst it seems that (the Defendant) did not have to pay for the items of plant during the period, I am concerned with the valuation of a variation and the issue of whether a party has or has not paid for a piece of plant does not determine the issue of the value of the piece of plant. I consider that in valuing the variation it is the ‘cost’ in terms of what it would cost which is the relevant information and that the issue does not depend on questions of payment…”

47.  The Plaintiffs argued that a “fair valuation” should not give the contractor more than his actual costs plus expected overheads and profit, and that anything more would give the contractor an additional windfall profit and be unfair to the employer. 

48.  Whilst the Arbitrator accepted that the Defendant did not have to pay for the items of plant during the period in question, he nevertheless allowed for the “cost” of such plant, as it was his decision that for the purpose of valuing the variation, “cost” is in terms of “what it would cost” the Defendant, and not actual payment made by the Defendant.  The Defendant sought to rely on Floods of Queensferry Ltd v Shand Construction Ltd [1999] BLR 319 and on paragraph 11.90 of Construction Contract Variations by Sergeant and Wieliczo, to support the decision of the Arbitrator, that valuation is a contractual entitlement and does not require proof of actual loss.

49.  On its part, the Plaintiffs refer to the following passage in the judgment in Floods of Queensferry Ltd v Shand Construction Ltd (at p 324):

“The guiding principle is that set out in clause 9 (2): the valuation must be fair and reasonable. Where, in general, contract rates and prices are not available or appropriate and where the contractor’s actual costs of labour, plant and materials reasonably and properly incurred can be established with an acceptable degree of certainty then those figures, together with an appropriate addition for site and head office overheads and profit, would produce a fair and reasonable valuation.”

50.  There is no reference in the Award to the absence or inapplicability of the evidence of the Defendant’s actual costs of labour, plant and materials incurred.  It would appear on the face of the Award that there was in fact evidence of that, in the evidence reviewed by the experts.  At this stage, I consider that the Arbitrator’s decision, of allowing costs not incurred by the Defendant in his valuation of the variation as “fair and reasonable”, to be at least open to serious doubt.

Disposition

51.  I grant leave to the Plaintiffs to appeal on the questions identified as questions 2 and 4.  Since the matter will proceed to the 2nd stage of determination on the merits of the appeal, I have refrained from making further comments on the substance of the appeal, save for stating the reasons why I considered that the threshold of “at least open to serious doubt” was met on the relevant questions of law.

52.  The costs of the application for leave will be in the cause of the appeal.

 (Mimmie Chan)
 Judge of the Court of First Instance
 High Court

Mr Peter Clayton SC, instructed by Pinsent Masons, for the plaintiffs

Mr Philip Boulding QC and Mr James Niehorster, instructed by Haley Ho & Partners, for the defendant