HK CourtDB
HomeDirectoryMCP
Hong Kong CourtDB
Back to directory
Construction and Arbitration Proceedings2023

WING LOK CONSTRUCTION & ENGINEERING CO LTD v. TECHOY CONSTRUCTION CO LTD

Files (2)

[2025] HKCFI 5546-EN-2025-11-28

WING LOK CONSTRUCTION & ENGINEERING CO LTD v. TECHOY CONSTRUCTION CO LTD

HTML content

HCCT 2/2023

[2025] HKCFI 5546

IN THE HIGH COURT OF THE

HONG KONG SPECIAL ADMINISTRATIVE REGION

COURT OF FIRST INSTANCE

CONSTRUCTION AND ARBITRATION PROCEEDINGS NO 2 OF 2023

___________________

BETWEEN

 WING LOK CONSTRUCTION & ENGINEERING CO., LIMITEDPlaintiff

and

 TECHOY CONSTRUCTION CO. LTD.
(德材建築工程有限公司)
Defendant

____________________

Before:Deputy High Court Judge Gary CC Lam in Court
Date of Hearing:27, 28 and 30 October 2025
Date of Judgment:28 November 2025

________________

J U D G M E N T

________________

I. INTRODUCTION

1.  This is the trial of the claim by the Plaintiff (“Wing Lok”) as subcontractor against the Defendant (“Techoy”) as the main contractor in respect of certain construction works at the West Wing of the former Central Government Office under a main contract it entered into with the Government (the “Main Contract”), and the trial of Techoy’s counterclaim against Wing Lok for certain contra-charges.

2.  By an agreement dated 20 September 2016 between Wing Lok and Techoy (the “Sub-Contract”), Wing Lok agreed to carry out and complete certain demolition works. On 15 December 2018, the works were completed.

II. DISPUTES

3.  The disputes between the parties are concerning various items of works. The parties have prepared a Joint Scott Schedule for the purpose of the trial. With the sensible assistance by Mr KM Chong, counsel for Wing Lok and Mr Solomon Lam (leading Mr Kevin Wong), counsel for Techoy, the dispute was narrowed down to the following items:-

(1) Item 2: Works under TCL808-WI-0074 (“WI74”) issued by Techoy to Wing Lok on 16 December 2016;

(2) Items 3 and 10: Fines for non-compliance with Site Safety Codes under the Sub-contract; and

(3) Items 4 and 11: Costs of Labour and Plant to carry out the Works due to the Defendant’s Default.

4.  For convenience, I shall refer to these items by reference to the item numbers in the Joint Scott Schedule, that is, Item 2, Items 3 and 10, and Items 4 and 11.

III. ITEM 2

5.  The dispute in Item 2 arises from WI74. It provided:-

“Works description and location: 13/F - G/F 打地台喜樓堅及地台石矢,各層大樓陣旁及陣底打石矢事宜,約數28,000 m2,由Q.S. 實量實度決定。28/12/2016”

6.  Wing Lok’s claim on this work item is based on quantum meruit. The burden of proof lies upon Wing Lok to make good its claim on quantum meruit. Mr Chong, for Wing Lok, seems to submit that the burden lies upon Techoy to prove that it was entitled to pay at the rates assessed by its surveyor. With respect, I disagree, because it is now Wing Lok who alleges that a different rate should apply and thus it has to commence the present claim, and the burden therefore lie upon Wing Lok to prove why the rate should be a different rate to sustain its claim.

7.  There is no dispute that this work item was an additional work, outside the Sub-Contract. There is also no dispute that this work was completed. The only dispute is how much the Plaintiff should be paid for this work. Upon completion of this work item, Techoy’s quantitative surveyor assessed the rate to be HK$103/m2 for 10,541 m2 of the work and HK$54/m2 for 4,518 m2. The difference in the rates arose from his assessment that not all the floor had cellocrete.

8.  What the rates should have been are a matter for expert evidence. However, no expert directions have been sought, and so there is no expert evidence. Wing Lok’s only witness, who is a factual witness, Choi Kin Ping (“Choi”), is one of the directors of Wing Lok. His evidence here is, in gist, the work under WI74 is similar to the work item “tilling and backing, screeding and paving, etc to floors” (the “Tilling Work”) under the Sub-Contract, which was agreed to be at the rate of HK$200/m2, and therefore the rate for the quantum meruit claim should also be HK$200/m2. The similarity point is not pleaded and thus strictly speaking, it is not a point Wing Lok should be permitted to run. In any event, both parties have adduced evidence on this point, and I should deal with the evidence insofar as admissible for the sake of completeness.

9.  Specifically, in his oral evidence, Choi said that the work procedure under WI74 was the same as the Tiling Work, namely, removing the tiles and the material underneath with drills and transporting out the removed materials, despite his admission during cross-examination that cellocrete was lighter in terms of weight and that the materials in the work under WI74 were not identical to Tilling Work under the Sub-contract.

10.  Further, Choi confirmed in the cross-examination that on 3 July 2017, he signed a “Measurement for BQ Item 3.1/9 A (Hacking off finishings to floor)” [that is, the Tilling Work] dated 14 June 2017, and a “Measurement of Asbestos Investigation Report” dated 3 July 2017. The former measured the total area for hacking of cellocrete to be 5,784 m2, and the latter measured the total area of hacking to be 15,095 m2. Choi also confirmed that for the work item under WI74, cellocrete was found in approximately 70% of the area of 15,095m2. This means that for the remaining 30% of the area, no or little cellocrete was found. This 70-30 is consistent with Techoy’s method of calculation: (1) about 70%, or 10,541 m2 was at one rate, and (2) about 30%, or 4,518 m2 was at another rate (see §7 above), reflecting that the different natures of areas under this work in WI74.

11.  Mr Chong stresses that the work under WI74 consisted of three types of hacking work as appears from the description of the work, namely, (1) cellocrete; (2) concrete on the floors and (3) floor slab concrete, concrete on side of pillars on all floors. Built on this, Mr Chong submits that because the Tilling Work was the only hacking works with an agreed rate under the Sub-contract, the same rate should be the reasonable rate adopted for the purpose of quantum meruit.

12.  Choi may or may not have a point in the evidence (or more accurately, his opinion) that the rate should be the same. Mr Chong’s submissions are also put attractively. However, leaving aside the absence of pleadings, in the light of (1) the evidence that cellocrete was lighter in terms of weight and that the materials in the work under WI74 were not identical to Tilling Work under the Sub-contract; (2) the area under WI74 itself contained different materials, in my view, expert evidence would be required to explain why despite all these, the rate should be the same. In the circumstances, I am unable to accept Choi’s evidence or opinion on the rate, as he is not an expert evidence, but a factual witness.

13.  In terms of Techoy’s evidence in this regard, Techoy’s quantitative surveyor has not given any evidence. The evidence of Techoy’s factual witness Lam Kin Wing Eddie, the chairman of Techoy, in this area is essentially hearsay evidence from what he allegedly came to know from the surveyor. I give no weight to his evidence in this area.

14.  In other words, there is no good evidence to sustain Wing Lok’s claim on the rates and the amounts, and there is no good evidence to sustain the assessment of the surveyor. However, since the claim here is Wing Lok’s claim, so, as mentioned above, Wing Lok carries the burden of proof. Given the status of the evidence as I have considered above, Wing Lok has failed to discharge the burden of proof and therefore its claim on Item 2 is not established.

15.  It remains for me to say that:-

(1) The reliance placed by Mr Chong, counsel for Wing Lok, on Clauses 59(5) and 61 of the “General Conditions of Contract for Building Works 1999 Edition” for his proposition that similar rate as Tilling Work should be applicable is impermissible as not pleaded in the Statement of Claim. Reference to these clauses was made only in the Joint Scott Schedule in the column Plaintiff’s comments on liability. It must be borne in mind that the Joint Scott Schedule is not a pleading, and parties cannot shuffle into the Joint Scott Schedule issues not appearing from the pleadings as if they were issues crystallised from the pleadings. They take their own risk in not properly pleading their cases rather than relying on the Joint Scott Schedule. In any event, in the present case, even if those clauses could be relied upon, still, Wing Lok would not have the requisite evidence to prove that despite the apparent differences in additional work under WI74 and the Tilling Work, similar rates should apply.

(2) Mr Chong submits that even the amount based on Techoy’s rates have not been paid at all. His submissions are that Techoy’s pleading pleads that this sum (the “WI74 Sum”) was included in the agreed contract sum under the Sub-contract, and therefore, the WI74 Sum was actually not paid but the inclusion of the WI74 Sum into the contract sum means that the work under WI74 was counted as work already included in the Sub-contract. In my view, first, Wing Lok has not pleaded this, and the attempt to make amendment to reflect such submissions has been rejected by Mimmie Chan J on 29 July 2025 in [2025] HKCFI 3310 and then by me at the outset of the trial. Second and in any event, such submissions have no merits at all, based on a misunderstand of Techoy’s case. Techoy’s case is that the contract sum had been paid and included the WI74 Sum because taking into account the contra-charges Techoy is entitled to charge against Wing Lok, the amount of the contract sum itself is more than sufficient to cover the work in the Sub-contract and the WI74 Sum. If there can be no contra-charges and no set-off, then the contract sum would not be sufficient to cover the WI74 Sum, and Techoy would have to pay Wing Lok the WI74 Sum. Whether Techoy is entitled to the contra-charges is a dispute I will have to resolve in Items 3-11. But it is wrong for Mr Chong apparently to say that because WI74 Sum should be for additional work, so the WI74 Sum could not be included in the contract sum, and, therefore, Wing Lok should be entitled to a full sum of HK$3 million odd based on its calculation, a claim not pleaded in any event.

IV. ITEMS 3 AND 10

16.  Items 3 and 10 are penalties or fines charged by Techoy against Wing Lok for breaches of regulations and guidelines issued by the relevant authorities. The contractual clauses for such penalties or fines are set out in Schedule 1 to the Defendant’s Re-Amended Defence and Counterclaim, which I shall not repeat here. Wing Lok puts Techoy to strict proof of the breaches. In terms of evidence, Techoy has been detailing the breaches in the interim payments nos 1 – 20 issued to Wing Lok in the past with reference to dates. Although they were interim in nature and I agree with Wing Lok that all these were subject to final discussion, there is no positive evidence from Wing Lok to say, for example, it had taken certain steps to comply with the relevant regulations by purchasing insurance policy. On balance, I find that there were indeed those breaches as detailed by Techoy.

17.  The main defence raised by Wing Lok is that these penalties or fines are not enforceable.

18.  To determine whether a penalty clause is enforceable, the Court of Appeal (Lam VP, Yuen and Chu JJA) in Law Ting Pong Secondary School v Chen Wai Wah [2021] 3 HKLRD 185 has set out the following legal principles:-

(1) The burden of proof lies upon the one who alleges that the clause is an unenforceable penalty clause: see §62.

(2) “The true test was held to be whether the clause is out of all proportion to the innocent party’s legitimate interest in enforcing the contract”: see §69.

(3) “[A]n innocent party could have a legitimate interest in the performance of the contract or some appropriate alternative to performance that goes beyond the compensation”: see §69.

(4) “The court should first identify the legitimate interest of the innocent party, that is being protected by the clause, and then assess whether the clause is out of all proportion to the legitimate interest by considering the circumstances in which the contract was made”: see §70.

(5) “Notions of whether the clause has a deterrent purpose or whether it is a genuine pre-estimate of loss would be subsumed by the broader enquiry into the legitimacy of the interest that supports the provision”: see §70.

(6) There is a difference between a review of a primary contractual obligation to pay and a jurisdiction to regulate a secondary contractual obligation to pay remedy for breach of contract. The latter should not be transformed into reviewing the contents of primary obligations to pay. See §71.

19.  In the present case, Mr Yeoh Kin Hok (“Yeoh”), the compliance manager of Techoy, was cross-examined on the following evidence of legitimate interests identified in §11 of his Reply Witness Statement filed on 20 March 2025 in respect of compliance with environmental and safety regulations:-

“(a) Additional administrative expenses to enhance inspections due to the Plaintiff’s consistent non-observance of safety and environmental regulations.

(b) Increased risks of workers’ injuries, which could potentially lead to substantial penalties imposed by the relevant Government Department, as well as higher insurance premiums or additional insurance coverage costs for the Defendant.

(c) Loss of reputation for the Defendant due to adverse reports issued by consultants, site auditors, or regulatory bodies, which could affect future opportunities for the Defendant to secure contract.

(d) Actual and potential delays in project timelines caused by the Plaintiff’s breaches, leading to further costs such as liquidated damages or penalties imposed by the client.

(e) Additional material wastage due to improper handling or poor compliance with safety and environmental standards, resulting in increased project costs for the Defendant.

(f) Loss of productivity caused by the need to divert resources to address the Plaintiff’s non-compliance, which impacted the overall efficiency of the works.”

20.  Although the above was set out for compliance with environmental and safety regulations, they are relevant to other regulations as well. Thus, Mr Chong cross-examined Yeoh also with reference to compliance with other regulations. For example, he asked Yeoh why wearing proper uniform would be relevant to the above identified interests.

21.  Despite Mr Chong’s cross-examination, I accept Yeoh’s evidence in this aspect. His evidence is, in my view, coherent with common sense. Further, as to one of the main lines of the cross-examination was in respect of (b) and (c) above that it would be the subcontractor but not the main contractor who would suffer loss, such line missed the point that the main contractor could also be liable as an occupier of the site, as is very often in personal injuries cases that the main contractor is sued for breach of occupiers’ liabilities.

22.  (a) – (f) of Yeoh’s evidence above, which I have accepted, clearly constitute legitimate interests for Techoy to ensure that Wing Lok would comply with the relevant regulations. Further, the potential loss suffered by Techoy mentioned in (b), (c) and (f) is difficult, if not impossible, to quantify. The penalties or fines, varying mainly from a thousand to a few thousands Hong Kong dollars, with a few thousand over HK$10,000, cannot be said to be “out of all proportion”, and on the contrary, in my view, proportionally served as disincentive for Wing Lok to breach the regulations, or as incentive for it to comply with the regulations.

23.  In the circumstances, I am not satisfied that these penalties or fines are unenforceable. Techoy is entitled to these contra-charges.

V. ITEMS 4 AND 11

24.  Items 4 and 11 are costs incurred by Techoy to rectify the works done by Wing Lok or its failure to carry out the works required under the Sub-contract. Techoy has detailed such rectification works. While putting Techoy to strict proof, Wing Lok does not have any positive case and evidence, for example, that it had done the works properly such that no rectification works would be required. Having considered the evidence, on balance, I find that the rectification works were indeed necessary and completed at the expense of Techoy.

25.  Wing Lok’s positive defence is, in summary, that there was a trade practice in the field that before the main contractor would incur costs chargeable against the subcontractor, the main contractor must inform the subcontractor of the necessity and intention to do so. However, it was not pleaded that consent was required, although in Mr Chong’s opening and closing submissions, it seemed to be suggested that consent was also required. This is impermissible as not pleaded. In any event, there is no expert evidence or evidence of a person experienced in the field for such trade practice. While Choi alleges that there was such a trade practice, he has not given any particulars or examples of such trade practice in the past. Further, such alleged trade practice, in my view, does not make much commercial sense as a prerequisite, as opposed to a good practice. It is a good practice, of course, to inform the subcontractor that certain costs would be incurred and chargeable against it, and even better practice to obtain prior consent from the subcontractor so as to avoid any dispute over the liability and amount. However, it is another thing to say that prior notification and consent is a prerequisite before the main contractor could be reimbursed by the subcontractor. If the main contractor would have to obtain consent before carrying out the work to rectify the subcontractor’s defective work, unnecessary and substantial delay may result. On the evidence, I find that there was no such trade practice.

26.  Further, legally speaking, the question is who has the liability to pay, and such liability is not preconditioned upon notification, unless there is any contrary agreement. Since the rectification works, by nature, means that Wing Lok’s works were defective, it was therefore Wing Lok’s liability in the first place to rectify and so it was liable to pay for such rectification works.

27.  In the premises, I reject this defence of trade practice.

28.  Therefore, Techoy is entitled to contra-charge Wing Lok Items 4 and 11.

VI. CONCLUSION

29.  In the circumstances, my findings on the items of the Joint Scott Schedule are as follows, which I adapt from §101 of the written closing submissions of Mr Lam, for Techoy:-

Joint Scott Schedule Item No.DescriptionAmount (HK$)
 P’s Claims 
Item 1Balance under the Sub-Contract (undisputed)1,028,094.00
Item 2Hacking of cellocrete under mastic matdisallowed
Item 5Item 3 of SOC 3rd Schedule (undisputed)78,800.00
Item 6Item 4 of SOC 3rd Schedule (undisputed)10,000.00
 Sub-total1,116,894.00
 D’s Counterclaims 
Item 7Charge of Disposal Chit (undisputed at closing submissions)(573,336.90)
Item 8Cost of supply of safety goods and other materials (undisputed at closing submissions)(66,864.00)
Item 9Administration Cost due to the Claim under the Employee Compensation Insurance Policy (undisputed at closing submissions)(60,000.00)
Items 3 & 10Fines for Non-Compliance with Site Safety Codes Under the Sub-Contract (allowed)(242,000.00)
Items 4 & 11Cost of Labour to carry out the Works due to the Defendant’s Default (allowed)(373,426.20)
Item 12Deduction of Levies (undisputed)(178,272.48)
 Sub-total(1,493,899.58)
 Net Sum(377,005.58)

30.  In the circumstances, Wing Lok should pay Techoy HK$377,005.58.

31.  I therefore order that:-

(1) Wing Lok shall pay Techoy HK$377,005.58;

(2) There shall be pre-judgment interest thereon at an interest rate at 1% p.a. above HSBC prime rate since the date of the amended Counterclaim (which pleaded substantially the amount Wing Lok is now being awarded), that is, 23 March 2023;

(3) There shall be post judgment interest rate until payment; and

(4) A costs order nisi that Wing Lok shall pay Techoy the costs of this action (including all costs reserved), to be taxed if not agreed.

32.  Lastly, I thank Mr Chong, counsel for Wing Lok, and Mr Lam and Mr Wong, counsel for Techoy, for their assistance.

 (Gary CC Lam)
 Deputy High Court Judge

Mr K.M. Chong, instructed by Samuel Chow Solicitors, for the Plaintiff

Mr Solomon Lam and Mr Kelvin Wong, instructed by Gilbert Tang & Co., for the Defendant

  

[2025] HKCFI 3310-EN-2025-07-29

WING LOK CONSTRUCTION & ENGINEERING CO LTD v. TECHOY CONSTRUCTION CO LTD

HTML content

HCCT 2/2023

[2025] HKCFI 3310

IN THE HIGH COURT OF THE

HONG KONG SPECIAL ADMINISTRATIVE REGION

COURT OF FIRST INSTANCE

CONSTRUCTION AND ARBITRATION PROCEEDINGS NO 2 OF 2023

___________________

BETWEEN

 WING LOK CONSTRUCTION & ENGINEERING CO LIMITED Plaintiff
 and 
 TECHOY CONSTRUCTION CO LTDDefendant
 (德材建築工程有限公司) 

____________________

Before: Hon Mimmie Chan J in Chambers (open to public)
Date of Hearing: 25 July 2025
Date of Decision: 29 July 2025

_____________

D E C I S I O N

_____________

Background

1.  This is the opposed application for leave to amend the Statement of Claim filed in this action, for payments said to be outstanding under a Sub-Contract between the Plaintiff and the Defendant for demolition works (“Sub-Contract”). The Sub-Contract is one for works to be completed by the Plaintiff for an agreed lump sum of $25,020,000 (“Agreed Costs”).

2.  The original Statement of Claim (“SOC”) filed in January 2023 was a simple claim for payment of the Agreed Costs less interim payments made (“Balance”), being $1,028,094, and for payment of the costs of additional works said to have been executed by the Plaintiff on the instructions of the Defendant (“Additional Works”).

3.  The pre-trial review (“PTR”) of the action is set to take place on 4 September 2025, with trial to commence on 27 October 2025.

4.  On 28 April 2025, the Plaintiff issued its summons for leave to amend the SOC with an amended version of the pleading attached. On 9 May 2025, the Plaintiff issued a summons for leave to amend its Amended Reply and Defence to Counterclaim, with the draft amended pleading attached. On 7 July 2025, the Plaintiff issued a third summons seeking leave to amend the SOC, in a version different to that attached to the 28 April summons. The Plaintiff maintained at the hearing that only the third summons and the draft amended SOC attached to the third summons are relevant, and that the Defendant and the Court can and should ignore the version attached to the first summons issued on 28 April 2025.

5.  The application for amendment is opposed by the Defendant. In gist, the grounds are that the amendments have not been properly formulated and particularized, the amended claims are bound to fail and are useless, and that the late amendments will have an impact on the milestone dates and cause delay and prejudice to the Defendant.

6.  Although the Plaintiff claims that the first summons for amendment of the SOC and the draft amended SOC attached to the first summons should be ignored, I agree with the Defendant that considering the original SOC and the lack of full particulars given in the original SOC and in the proposed amendments, the different amendments sought in the two different summonses only add to the confusion in the Plaintiff’s case and the Court’s difficulties in understanding the claim the Plaintiff seeks to make against the Defendant.

Delay

7.  At the forefront of the Court’s consideration, the trial is set to commence on 27 October 2025, and the PTR is scheduled for 4 September 2025. Counsel for the Plaintiff dismissed the importance of these on the basis that the trial is only in October 2025 and the PTR is two months away from the hearing of its three summonses, such that even if the Defendant should have to deal with the amended claims, it will have ample time to do so.

8.  I cannot agree.

9.  Parties should bear in mind the fact that under Order 25 rule 1A RHC, the Court expects the parties to be ready for trial by the PTR (see para 25/1A/13 of the Hong Kong Civil Procedure 2025). Parties should not labour under the misconception that they should still be able to have interlocutory summonses issued, or pending disposal, at or after the PTR.

10.  The Defendant in this case justifiably pointed out that if the amendments are allowed, it will need further and better particulars of the amended claims, further amendments to be made to its Defence and Counterclaim, and further witness statement (s) to be prepared in order to deal with the new and amended claims and to explain the different figures referred to in the evidence and now sought to be relied upon by the Plaintiff by the amendments. Counsel for the Defendant further pointed out that whereas the original claim for the Balance turns on the proper construction of the terms of the Sub-Contract and the applicable rates for the works carried out, the amendments sought to be made would likely require expert evidence to be called, and this would necessitate a more complex timetable for the instructions to the experts and preparation of expert reports for use at trial.

11.  According to the Defendant, it is impractical to expect that all the above can be finalized in time for the PTR in September 2025. Even if this was possible, the Defendant will be distracted from its preparations for the trial in October on the basis of the original claim, which Counsel for the Defendant highlighted was for the total sum of $3,238,228.20, whereas the proposed amendments bring the Plaintiff’s claim to $5,878,488.12, which affect the proportionate steps already taken and to be taken to defend the claim, including the decision on whether expert evidence should be called.

12.  In my judgment, the above is evidence of prejudice.

13.  It is indisputable that the Plaintiff’s applications for amendment are late. In such circumstances, it behoves any applicant seeking to introduce late amendments to pleadings or to make late discovery of documents (not applicable in this case) for use at trial to: (1) properly formulate its proposed pleadings/identify the new documents; and (2) justify its delay by showing good reasons for leave to be granted. I repeat the observations I made in Converge Design and Construction Company Limited v Mount Kelly International Limited[2020] HKCFI 2433, at para 2:

“The courts have emphasized on repeated occasions that CJR is about early preparation for trial, in order to achieve the objectives of the Rules. It needs no further reminder that delay itself is a ground to refuse a late application, either for discovery or for the introduction of new pleadings and evidence, when trial is imminent. The onus is on the applicant to justify its delay and to show good reason for leave to be granted. Whilst delay is to be weighed against the probative value and relevance of the pleadings and the evidence sought to be introduced, it need not be emphasized further that the primary aim in the Court’s exercise of its powers is to secure the just resolution of disputes in accordance with the substantive rights of the parties. Such just resolution of disputes requires due consideration of the time occasioned by last minute applications to introduce amendments to the pleadings and/or evidence on the eve of trial. Prejudice is inevitably caused, in the disruptions in the preparation for trial, the need to consider the new evidence and the need to respond thereto, coupled with the need to locate witnesses at the last minute to consider and if necessary to respond to the new evidence, and the last minute distraction from the proper focus and priority of the due preparation for trial. This is actual prejudice.” (Emphasis added)

14.  The explanation given by the Plaintiff for the delay is only that it discovered that there was a mistake in omitting the sum of $739,141 in the SOC, as the Plaintiff’s accounting staff wrongly believed that the sum had been paid or accounted for. It did not specify when the alleged mistake was discovered before the application for amendment was initiated.

15.  Counsel for the Plaintiff relies on the principle that amendments before trial should be permitted to correct any defect or error in the proceedings, and that such amendments ought to be allowed for the purpose of determining the real question in dispute between the parties. That is correct, but it has always to be weighed against the other relevant matters such as disruptions to milestone dates, and any prejudice to the opponent which cannot be compensated by costs alone.

The new claim of agreed costs for the Additional Works

16.  As this Court observed at the hearing, a disproportionate amount of time had to be spent at the hearing to understand the figures and claims set out in the original pleading, its Schedules, and the amendments. This would not have been necessary if the claims had been clearly and succinctly set out and explained by adequate particulars.

17.  The Defendant correctly summarized the Plaintiff’s intended pleading to be (at least on its face):

(1)  its claim of $739,141 as an agreed sum for Additional Works, as identified in the Defendant’s Summary and Assessment of Final Account (“Summary”) annexed to its email of 3 September 2020 to the Plaintiff (“Email”), and as (allegedly) agreed between the parties; and

(2)  its claim of $3,404,026.92, again as an item of agreed costs, on the basis of the same Summary and Email, for further and different items of Additional Works.

18.  The amendments are proposed on the pleaded basis of an alleged agreement of the parties, contained in or evidenced by the Email. Counsel for the Defendant pointed out that in the witness statement of the Plaintiff’s Choi Kin Ping (“Choi”) dated 19 February 2025, it was stated that there was a “settlement of account”, as the parties had agreed on the Final Account for the contract works, but that there were two items of work and costs which were disputed and which were to be resolved in due course. This dispute related to the Plaintiff’s assessment of the costs of the relevant works involved being $3,404,026.92, and the Defendant’s assessment thereof being $1,901,118.92. For the Defendant, Counsel highlighted that this was the real issue in dispute between the parties, the difference of the 2 assessments being $1,502,908.

19.  By seeking the amendments to claim the full sum of $3,404,026.92, on the basis of the parties having agreed on the sum, the amended claim totally contradicts the Plaintiff’s evidence contained in Choi’s statement of there being an agreed settlement of account. In this context, Counsel for the Defendant pointed out that on the Plaintiff’s own evidence, the new claim of $3,404,026.92 being the agreed costs of works is doomed to fail when the evidence in Choi’s statement is taken into account, namely, that any alleged agreement between the parties did not include the 2 items (including the $3,404,026.92) now said to have been agreed.

20.  The same goes for the claim of $739,141 being the allegedly agreed sum for the works in question. According to the Summary, there was agreement on the assessment of $739,141, but this was part of an overall agreement with the deductions and adjustments, and the Defendant argued that the Summary and the Email cannot be evidence of a “settled account” covering the works agreed or assessed at $739,141, without taking into account also the other matters agreed, such as the deductions to be made, which the Plaintiff now ignores in making its amended claim. For example, the Plaintiff had agreed to the deduction of $1,916,870.30 as adjustments for the Type 3 works. Counsel for the Defendant pointed out that if the Court accepts that there was an agreement on the sum of $739,141, there should also be agreement on a deduction of $1,916,870.30, which will result in a negative amount due to the Plaintiff.

21.  Counsel for the Defendant relies on para 20/8/24 of Hong Kong Civil Procedure 2025 which states:

“Immaterial and useless amendments (rr 5, 7 and 8) - The court will always look at the materiality of the proposed amendment. An inconsistent or useless amendment will not be allowed …… nor an addition of some irrelevant matters or an amendment which fails to give the necessary material facts or particulars …… nor to make any other amendment raising a case which must fail…”

22.  The Defendant further relies on the observations made by the Court in Bank of China v Leigh Hardwick HCA 1110/2006, 28 August 2013, at para 2 of the judgment:

“The arguments in this appeal turn upon whether the new defences deployed in the Amended Defence are bound to fail. There is no dispute that if they are bound to fail, no leave should be granted for the amendment. For the purpose of this appeal, there is also no dispute that this court should take the pleaded defences at the highest.”

23.  I accept the Defendant’s submission, that on the evidence contained in Choi’s witness statement, the proposal set out by the Plaintiff in the Email cannot evidence any agreement having been reached over the alleged “settled account”, and the sums now asserted by the amendments. As Counsel submitted, the proposed amendment to seek the full sum of $739,141 without taking into account the deduction of $1,916,870.30 is bound to fail. To admit the proposed amendment of the agreed sum of $739,141 is useless, and confuses the real issues in dispute for determination at trial.

Lack of particulars of the intended claim

24.  In any event, I agree that the claims of the agreed sums of $3,404,026.92 and $739,141 are lacking in particulars, as to how the sums were calculated. Neither the SOC nor the proposed Amended SOC gives particulars of what the 2 figures comprise. It was Counsel for the Defendant who referred to the Summary attached to the Email which contained the figures in various tables. It is not known, from the draft amended SOC and the Plaintiff’s evidence, whether the Plaintiff’s intended amended claim is based on these computations, and if not, how these figures were arrived at. This is so notwithstanding the lateness of the application for amendment when it behoves the Plaintiff to make clear its intended claim so close to trial.

25.  It is wrong for Counsel for the Plaintiff to assert that the Plaintiff’s case should have been known to the Defendant, or that any documents with further and better particulars of the amended claim would be in the possession of the Defendant. That is not how pleadings work, and that is trite. Any objection to particulars on the ground that the relevant facts are within the applicant’s own knowledge is misconceived (para 18/12/65, Hong Kong Civil Procedure 2025), as “each party is entitled to know the outline of the case that his adversary is going to make against him, and to bind him down to a definite story”.

26.  As the oft-quoted judgment of Bokhary JA (as he then was) in Aktieselskabet Dansk Skibsfinansiering v Wheelock Marden & Co Ltd [1994] 2 HKC 264 makes it clear, the purpose of particulars and pleadings is to inform the other side of the nature of the case they have to meet, to prevent the other side from being taken by surprise at trial, to enable the other party to know with what evidence they ought to be prepared and to prepare for trial, to limit the generality of the claim and the evidence, and to tie the hands of the party so that he cannot without leave go into any matters not included.

27.  As Counsel for the Defendant submitted and I agree, the Plaintiff’s position has been shown to be evolving from the original SOC, to the different versions and formulation of its claim and figures according to the draft amendments annexed to the Plaintiff’s two summonses of April and July 2025, which makes it more important for it to be bound to any case it intends to pursue at trial.

28.  As held by the Court in Build King Construction Limited v Sam Woo Bore Pile Foundation Ltd[2025] HKCFI 894, it is wrong in principle to allow the Plaintiff to amend its pleadings without properly formulated and fully particularized claims. As His Lordship observed (at para 41 of the judgment):

“The lack of a properly formulated claim is a concern with merits. In my view, it is inappropriate to grant an amendment application which is keenly contested with the hope that proper particulars will be provided after amendment (none has in fact been offered). That is wrong in principle. Amendment application should be supported by a properly formulated set of amendments.”

Disposition

29.  Having given proper regard to the delay in the application for amendment, the unparticularised claims sought to be made, and the merits of the intended claim, and the effect of the amendment on the milestone dates in this case, I refuse leave. The two summonses for amendment of the SOC are dismissed, with costs to the Defendant in any event, with Certificate for Counsel.

30.  As for the summons to amend the Reply and Defence to Counterclaim, Counsel for the Defendant rightly pointed out that only paragraph 5A is a consequential amendment as a result of the Re-Amended Defence filed by the Defendant. That is not objected to, and is allowed.

31.  The other amendments are based on the amendments to the SOC being allowed on the Plaintiff’s summonses, and/or on claims which are based on the alleged agreement held to be doomed to fail. Since the amendments to the SOC have not been allowed, the proposed amendments to the Reply and Defence to Counterclaim are inappropriate and are not allowed as the proposed pleading stands. Paragraph 9A adds little to the original paragraph 9, and is unnecessary.

32.  The costs of and occasioned by the Plaintiff’s summons of 9 May 2025 are to be paid by the Plaintiff to the Defendant, with certificate for Counsel.

  (Mimmie Chan)
Judge of the Court of First Instance
High Court

Mr KM Chong, instructed by Samuel Chow Solicitors, for the plaintiff

Mr Solomon Lam and Mr Kelvin Wong, instructed by Gilbert Tang & Co, for the defendant