HK CourtDB
HomeDirectoryMCP
Hong Kong CourtDB
Back to directory
Construction and Arbitration Proceedings2024

CS v. HKR

Related cases with same parties

  • CAMP142/2021CS v. WCT
  • CAMP93/2021CS v. WCT
  • FCMC1930/2019CS v. WCT
  • FCMC5660/2020CS v. WDT

Files (3)

[2026] HKCFI 1611-EN-2026-03-19

CS v. HKR

HTML content

HCCT 72/2024

[2026] HKCFI 1611

IN THE HIGH COURT OF THE

HONG KONG SPECIAL ADMINISTRATIVE REGION

COURT OF FIRST INSTANCE

CONSTRUCTION AND ARBITRATION PROCEEDINGS

NO 72 OF 2024

____________________

 IN THE MATTER OF THE ARBITRATION ORDINANCE (CAP 609)
 and
 IN THE MATTER OF AN ARBITRATION

____________________

BETWEEN

 CSPlaintiff
  (Respondent in Arbitration)
 and 
 HKRDefendant
  (Claimant in Arbitration)

____________________

Before: Hon Mimmie Chan J in Chambers
Dates of Written Submissions: 12 and 16 February 2026
Date of Decision: 19 March 2026

_____________

D E C I S I O N

_____________

1.  This is an unusual application made by the Plaintiff in these proceedings instituted by its Originating Summons issued on 24 June 2024 (“OS”). By its summons of 7 November 2025, the Plaintiff seeks what the Defendant described as a “Voluntary Payment Order”, for the Plaintiff’s own payment into court of the interest awarded under a Second Award dated 30 October 2025 (“2nd Award”) made in the Arbitration which is the subject matter of the proceedings.

2.  In the OS, the Plaintiff applied for leave to appeal against the Amended Interim Award on Liability and Quantum dated 27 May 2024 (“1stAward”), on specified questions of law, pursuant to section 6(1)(b) of Schedule 2 (“Schedule”) to the Arbitration Ordinance (“Ordinance”). 4 questions of law were identified for the application for leave to appeal. By its Decision on 22 November 2024, this Court refused leave (“Refusal of LeaveDecision”).

3.  The Plaintiff applied for leave to appeal against the Refusal of Leave Decision. By the Decision dated 7 February 2025, this Court granted leave to the Plaintiff to appeal to the Court of Appeal against the Refusal of Leave. This was on the basis that it is reasonably arguable that the tribunal’s decision on Question 1 (as defined in the Refusal of Leave Decision) is in substance a matter of construction of the relevant Subcontract, and the tribunal had erred in law by failing to consider the effect of the Subcontract provisions and the drawings. Leave to Appeal was also granted for the Court of Appeal to consider whether leave to appeal on Question 3 (double recovery) should also be granted.

4.  There are now pending before the Court of Appeal the substantive appeals against the Refusal of Leave Decision with regard to Questions 1 and 3, and whether leave to appeal from the 1st Award should be granted for Questions 2 and 4.

5.  According to the parties, the appeal on Questions 1 and 3 is scheduled for hearing in late March 2026, and the renewed application for leave to appeal on Questions 2 and 4 was heard in February 2026, with judgment pending.

6.  The Plaintiff highlighted the fact that it has in fact made full payment to the Defendant of the amount allowed under the 1st Award, as a result of the statutory demands threatened by the Defendant, and to avoid any enforcement action including winding up proceedings being taken against it on the basis of the 1st Award.

7.  The 2nd Award was for interest and costs, on the basis of the findings made and the principal sums awarded in the 1st Award.

8.  The Defendant on its part emphasized that there has been no application made by the Plaintiff to challenge the 2nd Award, whether by way of setting aside, or seeking leave to appeal on any question of law. However, the Plaintiff pointed out that the Defendant itself has not yet made any application for leave to be granted by the Court to enforce the 2nd Award.

9.  To avoid any threat of winding up and any enforcement action on the 2nd Award, the Plaintiff has taken the initiative to apply for an order from the Court for it to give security for the payment of the interest allowed under the 2nd Award, by payment into court within 21 days, which payment will remain in court pending the final determination of the Plaintiff’s appeal to the Court of Appeal in respect of the 1st Award, and any consequential award or order on the questions of law identified in the OS, and if necessary, for consequential amendments to the 2nd Award as a result of the 1st Award being set aside, varied or remitted, upon the determination of the appeal.

10.  The Defendant claims that the Plaintiff has no entitlement to seek the Voluntary Payment Order, nor does the Court has jurisdiction or power to make the order sought by the Plaintiff - when there is no challenge or appeal against the 2nd Award. That is the gravamen of the submissions made for the Defendant, ie since there is no challenge against the 2nd Award, the entire sum awarded by way of interest and costs should be paid to the Defendant under a final award of the tribunal, and there should not be any condition attached to the Defendant’s recovery by the money being paid into and retained in Court until the conclusion of the appeal proceedings. It was argued that the Defendant should not be hampered in its liberty to choose the method and location of seeking recovery under the 2nd Award by way of enforcement. That would be the practical effect, as Counsel for the Defendant contended, if the Court should allow the Plaintiff to keep the money representing the 2nd Award in the Hong Kong court, when the Defendant should be able to seek recovery elsewhere.

11.  Dealing with this last point first, I can appreciate the Defendant’s concerns, but so long as it has not received the amount allowed under the 2nd Award in its pocket, it cannot be said that it has recovered the amount, or has been paid. The Defendant should still be entitled to take other enforcement steps against any available assets of the Plaintiff elsewhere. It can only be argued that it has “security” in Hong Kong, in the sense that it will be able to look to the payment in court eventually, when the appeal has been disposed of and the Plaintiff is held liable to make payment to the Defendant out of the money paid into court. This would be relevant if the Defendant wishes to seek other security short of or before full payment by the Plaintiff. Viewed this way, any prejudice to the Defendant in its choice of remedies is more academic than real.

No Challenge to 2nd Award?

12.  It is true that there has been no application to challenge the 2nd Award. However, the matter has to be considered in its proper context.

13.  The Plaintiff applied for leave to appeal against the 1st Award on points of law. There is a pending appeal as to whether such leave should be granted. If the Court of Appeal decides that leave should properly be granted on Question 1 and/or Question 3, then the appeal will be heard, and if the appeal results in the 1st Award being set aside, in whole or in part, or varied, or remitted, pursuant to section 5(5) of the Schedule to the Ordinance, the principal amount awarded under the 1st Award may well be reduced. If the principal amount of damages is varied or reduced, the amount of interest awarded in the 2nd Award must incidentally be affected and reduced.

14.  Hence, by challenging the 1st Award in the way it did, the Plaintiff is incidentally challenging the 2nd Award. Of course, the more appropariate procedure is for the Plaintiff to make the necessary formal challenge against the 2nd Award, but in this regard, the Plaintiff was right to point out that the Defendant has yet to apply for leave to enforce 2nd Award, because at that stage, the Plaintiff can oppose the enforcement.

15.  I therefore cannot fully accept the Defendant’s contention, that there is no challenge against the 2nd Award, although I consider that even before any application is made to the Court for leave to enforce, the 2nd Award is a valid award which is binding on the Plaintiff unless and until it is set aside or varied by the Court on appeal in this case, or by the tribunal.

Any basis to make application and power to make order?

16.  On behalf of the Defendant, it was contended that the Plaintiff has no entitlement to apply for the Voluntary Payment Order, and the Court has no power to make the order sought.

17.  The Plaintiff relies on sections 5-7 of the Schedule, Order 73 rule 2 and Order 1B RHC, as well as the inherent jurisdiction of the Court, to make its application. The Defendant claims that none of these is applicable, when there is no action to challenge the 2nd Award (for which the Voluntary Payment is proposed).

18.  With regard to the submissions made for the Defendant, I agree with the Plaintiff that these proceedings were commenced by the OS which seeks relief relating to the 1st Award, as well as “any consequential award or order of the Arbitrator”, including an order for remitting the 1st Award “and any consequential award or order of the Arbitrator” for his reconsideration, pursuant to section 5 of the Schedule. This will include the 2nd Award on interest, consequential to the findings made in the 1st Award.

19.  The Summons for the Voluntary Payment Order was issued in the proceedings commenced by the OS.

20.  It cannot be said that there is no action concerning the 2nd Award, and that the Court’s inherent jurisdiction cannot extend to the 2nd Award. The OS makes it clear that the relief sought includes any necessary variation or remittal of a “consequential award or order of the Arbitrator”, which will extend to the 2nd Award.

21.  The paragraph relied upon at U1/114/50 of the Hong Kong Civil Procedure cannot assist the Defendant, as it only states generally that section 7 of the Schedule (and the orders which the Court can make thereunder) applies to challenges to an award and appeals on questions of law under sections 4-6 of the Schedule. The OS was issued expressly under sections 4-7 of the Schedule. The challenge to/appeal sought against the 1st Award made under the OS can extend to the award of interest made in the 2nd Award.

22.  Any appeal allowed in respect of the principal sum awarded under the 1st Award will affect the interest allowed under the 2nd Award, so it cannot be said that when there is no challenge against the 2nd Award, no order can be made by the Court.

23.  Citing JJ Argo Industries (P) Ltd v Texuna International Ltd [1994] 1 HKLRD 89, the Defendant relies on the doctrine of severability of an award to claim that the 2nd Award should be enforced as a whole, rather than to permit a stay of enforcement of a part of the interest related to the claims which are sought to be challenged by appeal on the 4 Questions identified in the leave to appeal application. Counsel for the Defendant highlighted the fact that as the Plaintiff has accepted, only a sum of $21,674,357 represents the interest payable on the claims affected by Questions 1 to 4. The balance of the interest allowed in the 2nd Award is approximately $8 million. According to the Defendant, it would be contrary to the doctrine of severability to refuse enforcement of the whole of the 2nd Award, when there are parts of the award which are not in issue.

24.  It has not been clearly shown how the principles set out in JJ Argo are applicable to the facts of this case to prevent the Voluntary Payment proposed. To the extent that the part of the 2nd Award on interest for claims affected by the determination on appeal of Questions 1-4 is severable from the part of the 2nd Award of interest on claims which are not affected, that cannot be disputed. If it is contended that this means that the Plaintiff should not be permitted to make a payment exceeding the $21,674,357 into court, but should only pay a smaller amount, I fail to see how it will alter the Defendant’s position – apart from the fact that the Defendant will be secured to a lesser extent than the Voluntary Payment offered.

25.  On its part, the Plaintiff’s case is that the whole amount of interest under the 2nd Award should be paid into court as security for both parties - on the basis that if payment should now be made directly to the Defendant, the Plaintiff would be at risk as the Defendant’s repayment capacity is (on the evidence) in doubt in the event that any amount of the principal awarded (and paid) and the interest thereon is reversed on appeal.

26.  What has not been addressed, which I take to be not in dispute, is that there is no express order for stay of enforcement or execution sought on the 1st or 2nd Award, whether by the Summons, or in the OS or any order so far made by the Court.

27.  In all the circumstances of this case, bearing in mind the nature of the 2nd Award, that the amount of interest on the principal sum awarded to the Defendant is affected by the application for leave to appeal against the 1st Award, I cannot agree that the Court does not have power to make the Voluntary Payment Order sought by the Plaintiff, whether under section 7(6) of the Schedule, or under the wider management powers of the Court under Order 1B RHC. As Counsel for the Plaintiff submitted, the power of the Court to order security under section 7(6) serves the purpose of preserving in Court money payable under arbitral awards pending challenges made under sections 4 or 5 of the Schedule. The Voluntary Payment Order preserves the status quo pending the appeal, and also saves the Court’s time in assessing the potential reduction of the principal sum and interest in the event that the arbitrator is shown to have erred on questions of law. Overall, the payment into court is a fair and reasonable method which can ensure that neither party is prejudiced.

Disposition

28.  For the above reasons, I accede to the Plaintiff’s application and make an order in terms of paragraphs 1 to 3 of the Summons.

  (Mimmie Chan)
Judge of the Court of First Instance
High Court

Mr Peter Clayton SC, instructed by Pinsent Masons, for the plaintiff

Mr Solomon Lam, instructed by Wong & Lawyers, for the defendant

[2025] HKCFI 611-EN-2025-02-07

CS v. HKR

HTML content

HCCT 72/2024

[2025] HKCFI 611

IN THE HIGH COURT OF THE

HONG KONG SPECIAL ADMINISTRATIVE REGION

COURT OF FIRST INSTANCE

CONSTRUCTION AND ARBITRATION PROCEEDINGS

NO 72 OF 2024

____________________

 

IN THE MATTER OF THE ARBITRATION ORDINANCE (CAP 609)

 

and

 

IN THE MATTER OF AN ARBITRATION

____________________

BETWEEN  
 CSPlaintiff
  (Respondent in Arbitration)
 and 
 HKR Defendant
   (Claimant in Arbitration)

____________________

Before: Hon Mimmie Chan J in Chambers
Dates of Written Submissions: 20 December 2024,9 January 2025 and 16 January 2025
Date of Decision: 7 February 2025

_____________

D E C I S I O N

_____________

1.  By order of 22 November 2024 (“Decision”), I refused to grant leave to the Plaintiff to appeal against an arbitral award on points of law. By summons issued on 6 December 2024, the Plaintiff sought leave to appeal against the Decision.

2.  The facts are already set out in the Decision the nomenclature of which I adopt herein.

3.  In the Grounds set out in the draft Notice of Appeal, the Plaintiff contends that this Court was plainly or obviously wrong in deciding that the questions for which leave to appeal was sought in the initial application were either not questions on which the tribunal had been asked to decide, or were not obviously wrong or open to serious doubt. It further contends in the alternative that there is some special reason for leave to appeal to be granted under section 6(6) of the Ordinance.

4.  In an application for leave to appeal to the Court of Appeal (“CA”), all that the Plaintiff has to establish is that the grounds of appeal have reasonable prospects of success (Maeda Kensetsu Kogyo Kabushiki Kaisha (Maeda Corp) v Bauer Hong Kong Ltd[2019] HKCFI 1427. The Defendant’s case is that the Plaintiff has not been able to meet this threshold.

5.  For the Defendant, Counsel also submitted that there is no special reason involved in this case for section 6(6) of the Ordinance to apply, since the mere fact that substantial sums may be involved in the Award cannot constitute any special reason or exceptional case to warrant leave to appeal to the CA. The Defendant further contends that there are in fact no questions of law for leave to appeal to be granted.

6.  Having considered the submissions made by the parties, I am persuaded that it is reasonably arguable on appeal to the CA that the tribunal’s decision on Question 1 (as identified in the Decision) is in substance a matter of construction of the Subcontract, its provisions and the drawings, and the parties’ obligations thereunder, and that the intended appeal is not merely against the Arbitrator’s finding of fact as to what the parties had agreed as a result of their meetings and discussions. It is reasonably arguable that when the Arbitrator decided Question 1 as to whether the parties had agreed on the maximum use of sand, but failed to consider the effect of the Subcontract provisions and the drawings, and whether or how these can be affected by the tender meeting discussions, it is reasonably arguable that the Tribunal had erred in law, and that the decision can be said to be obviously wrong.

7.  For the above reasons, I grant leave to appeal on Question 1.

8.  If the tribunal had accepted a valuation of an expert, on the entirety of the evidence adduced before it, I am not satisfied that its decision can be said to be obviously wrong or open to serious doubt simply because it may be inconsistent with its own other findings. As explained at paragraphs 29 to 34 of the Decision, I do not accept that the Arbitrator’s decision on Question 2 constitutes a decision on law or an error in his ascertainment of the law. As the court had explained in The Chrysalis [1983] 1 WLR 1469 at 1475, at the stage when the arbitrator makes his decision in the light of the facts and the law ascertained, an element of judgment is involved “and there is no uniquely ‘right’ answer to be derived from marrying the facts and the law, merely a choice of answers, none of which can be described as wrong”.

9.  The Arbitrator in this case explained why he decided to adopt the assessment of the Defendant’s expert, and bearing in mind the fact that the Arbitrator was an experienced quantity surveyor competent and possessing the expertise to decide the highly technical issues raised in the Arbitration on measurement of works and the calculations of the amounts claimed, the Plaintiff has not, for the purpose of the intended appeal to the CA, established that it is reasonably arguable that the Arbitrator’s decision on Question 2 is obviously wrong on a question of law. I decline leave to appeal.

10.  On the question of double recovery, I accept the submission that it is reasonably arguable that if the Award and the amount allowed thereunder actually results in the Defendant obtaining double recovery, the Tribunal erred in law and the determination is one that is out of conformity with the only correct answer or lies outside the range of correct answers (The Chrysalis [1983] 1 WLR 1469), and can be made the subject of an appeal on a question of law arising from the Award.

11.  Finally, on Question 4, the Plaintiff has totally failed to demonstrate how the Arbitrator’s decision, based on his clear rejection of the Plaintiff’s claims of critical delay on the evidence, for the reasons given in the Award, can be said to be obviously wrong or open to serious doubt. I reject the contention that there are reasonable prospects of success on this ground of appeal and refuse to grant leave.

12.  I grant leave to appeal on Questions 1 and 3 only.  I can see no other special reason to grant leave to appeal on Questions 2 and 4.

13.  The costs order nisi I make is that the Plaintiff should pay half of the costs of the application for leave, and the balance of the costs will be in the cause of the appeal to the CA.

 (Mimmie Chan)
  Judge of the Court of First Instance
 High Court

  

Mr Peter Clayton SC, instructed by Pinsent Masons, for the plaintiff

Mr Douglas Lam SC and Mr Solomon Lam, instructed by Wong & Lawyers, for the defendant

 

 

[2024] HKCFI 3366-EN-2024-11-22

CS v. HKR

HTML content

HCCT 72/2024

[2024] HKCFI 3366

IN THE HIGH COURT OF THE

HONG KONG SPECIAL ADMINISTRATIVE REGION

COURT OF FIRST INSTANCE

CONSTRUCTION AND ARBITRATION PROCEEDINGS

NO 72 OF 2024

____________________

 IN THE MATTER OF THE ARBITRATION ORDINANCE (CAP 609)
 and
 IN THE MATTER OF AN ARBITRATION

____________________

BETWEEN

 CSPlaintiff
  (Respondent in Arbitration)
 and 
 HKRDefendant
  (Claimant in Arbitration)

____________________

Before: Hon Mimmie Chan J in Chambers
Dates of Written Submissions: 5, 13 and 20 September 2024
Date of Decision: 22 November 2024

_____________

D E C I S I O N

_____________

Background

1.  This is an application made by the Plaintiff for leave to appeal against the Interim Award on Liability and Quantum of the Arbitration published on 3 May 2024, as amended on 27 May 2024 (“Award”). The application is made pursuant to s 6(1)(b) of Schedule 2 (“Schedule”) to the Arbitration Ordinance (“Ordinance”). 4 questions of law are identified for the intended appeal.

2.  Under s 6(3) of the Schedule, the Court “must” determine an application for leave to appeal without a hearing unless it appears to the Court that a hearing is required. Under s 6(4), leave to appeal is only granted if the Court is satisfied of three cumulative conditions. These are that (a) the decision of the question will substantially affect the rights of one or more of the parties; (b) the question is one which the arbitral tribunal was asked to decide; and (c) on the basis of the findings of fact in the award, the decision of the tribunal on the question is “obviously wrong”, or the question is one of general importance and the decision of the tribunal is “at least open to serious doubt”.

3.  In this regard, I wish to repeat the observations made in P v C[2019] HKCFI 2625, at paragraphs 4 to 5:

“4. It has to be borne in mind that an application for leave to appeal on a question of law arising out of an award is a filtering process. As highlighted in the decision of Mustill J (as His Lordship then was) in Vinava Shipping Co Ltd v Finelvet AG (The “Chrysalis”) [1983] 1 Lloyd’s LR 503, the court at the first stage, of the application for leave, gives effect to the policy whereby “the interests of finality are placed ahead of the desire to ensure that the arbitrator’s decision is strictly in accordance with the law.” As His Lordship explained:

‘Some examination of the merits takes place at this stage, because the stronger the applicant’s case for saying that the arbitrator was wrong, the better his prospect of obtaining leave to appeal. But the examination of the law is summary in nature, and does not lead to any definite conclusion. The exercise is discretionary throughout; the mesh of the filter is fine; and it must, I think, he recognized that some cases will be caught in the filter which would, if the appeal had been allowed to go forward, result in a decision that the award could not stand.’

5. The judgment in The Chrysalis also contains a helpful summary on the 3 stages of an arbitrator’s process of reasoning, with the reminder that only the second stage of the process is the proper subject matter of any appeal on law:

‘(1) The arbitrator ascertains the facts. This process includes the making of findings on any facts which are in dispute.

(2) The arbitrator ascertains the law. This process comprises not only the identification of all material rules of statute and common law, but also the identification and interpretation of the relevant parts of the contract, and the identification of those facts which must be taken into account when the decision is reached.

(3) In the light of the facts and the law so ascertained, the arbitrator reaches his decision.’”

4.  On 4 July 2024, I gave directions for parties to file succinct written submissions confined to 3 pages for each question of law, with 1 page in reply.

5.  The Originating Summons (“OS”) filed in support of the application in this case goes up to a staggering 56 pages. Whilst I would not rule (as the Defendant submits) that the OS and the affidavit in support amount to an abuse of process, I agree that they ignore paragraphs 17 to 19 of Practice Direction 6.1, which require the statement of each ground of appeal to be “succinct”. It also defeats the object and principles of the Ordinance, and goes against the criteria set out in section 6 for the grant of leave to appeal against an award, to require the Court to sieve through the lengthy OS, in order to identify firstly the questions of law decided by the tribunal and then, the errors of law claimed to have been made.

6.  This Court is no stranger to the complex nature of construction disputes and the need to file detailed submissions to elucidate the issues. However, parties must not lose sight of the fact that an application for leave to appeal on a question of law arising out of an award is a filtering process, intended to be summary in nature. Where lengthy written submissions and a prolix OS are filed, that may work to the detriment, as opposed to benefit, of the appellant. This is because the onus is on the appellant to demonstrate, quickly and easily, without meticulous argument, that the decision of the tribunal is “obviously wrong” or “at least open to serious doubt”: W v Contractor[2024] HKCFI 1452 §7. On either test, the threshold is high. What has to be demonstrated to the Court, quickly and easily, without meticulous legal argument, is that the decision of the tribunal simply cannot be right, or that there are serious doubts as to the correctness or reasoning of the award, according to the appropriate tests (Chun Wo Construction & Engineering Co Ltd v The Hong Kong Housing Authority[2018] HKCFI 147, paragraph 13).

7.  It is also pertinent to bear in mind the observations made by Lam VP in Maeda Kensetsu Kogyo Kabushiki Kaisha (also known as Maeda Corporation) and China State Construction Engineering (Hong Kong) Limited v Bauer Hong Kong Limited HCMP 1342/2017, 4 September 2017, that the assessment of whether the decision of the tribunal is at least open to serious doubt can be subjective, and different judges can reasonably come to different views. In a matter concerning the construction of a contractual document, the court dealing with the application for leave to appeal may have a different view as to the possible meaning of a provision, but it does not follow from that, that the meaning ascribed by the tribunal to that provision was “obviously wrong”.

8.  As this Court already pointed out in Maeda Kensetsu Kogyo v Bauer[2019] HKCFI 1006 (at paragraph 70), Order 41 rule 5 RHC contains the general statement that an affidavit may contain only such facts as the deponent is able of his own knowledge to prove. Submissions and arguments should not be made in affidavits filed in proceedings, as these should properly be made by counsel or the advocate, in skeleton arguments which should comply with the practice directions and any specific directions which may be made by the court.

9.  Affidavits made by the solicitors acting for the parties, containing lengthy submissions and arguments on the issues, questions and errors of law, and on what is or is not claimed to be relevant or correct, are totally unnecessary and inappropriate, whether or not such submissions and arguments are then referred to or repeated in part by Counsel in their skeleton submissions, and responded to by the other side. This manner of presenting and dealing with the case is totally unhelpful to the court’s efficient consideration and disposal of the questions to be decided. Apart from the scanty matters of facts contained in the affidavits filed in these proceedings, no reference has been made to the affidavits as it is not necessary to do so, and only the submissions made in Counsel’s skeletons have been considered.

10.  The affidavits and the costs incurred were totally unnecessary, and in the usual course if and when costs are considered on taxation, I would consider that such costs should not be allowed on taxation, and would further regard such costs imposed on the lay clients to be unreasonably incurred. In this case, however, my order for costs (as shown in paragraph 51 below) is that the costs of the application are to be paid by the Plaintiff to the Defendant.

The questions of law

11.  The 4 questions of law claimed by the Plaintiff to have been decided by the tribunal and which contain errors relate to:-[1]

a.  The environmental requirement and the subcontract obligation on the part of the Defendant to maximise the use of public fill to 30% of the overall Type A fill (“Question 1”);

b.  Whether there was an error in the adoption of an assessment methodology and computation on MM17.14 (“Question 2”);

c.  Whether the tribunal erred in allowing double recovery for non-material costs under BQ item no 19 and then again as extra works under BQ item no 20 (“Question 3”);

d.  Interpretation of GCSC 31 concerning the omission of the remaining seawall work on 7 July 2014 (“Question 4”).

Question 1

12.  Question 1 targets paragraphs 44 to 54 of the Award, which is titled “BQ Item 17 – Sandfill (Material supplied by HKR)”. It is framed as a question of contractual interpretation, namely “What was the requirement, in light of the Environmental Permit and HKR’s subcontract obligations, for the use of public fill in the reclamation deposited by HKR from the seabed at -2.0mPD to +2.5mPD and, the extent of HKR’s entitlement to be paid for the public fill and the sand fill within the overall Type A fill”.

13.  First, I accept that this question substantially affects the rights of the parties. The Award includes the Defendant’s entitlement to payment for public fill, which was assessed at a rate much cheaper ($47 per cu m) than that of sand fill ($150 per cu m). If the Arbitrator is shown to have erred, the Award would be reduced by a significant sum (more than $22 million), to substantially affect the rights of both parties.

14.  However, I do not accept that this is a matter of general importance. Even if I accept the Plaintiff’s submission that GCSC 3(1) and GCSC 3(2) are commonplace in the construction industry and are present in many standard form subcontracts, construction of these isolated provisions is of no general utility as each contract has to be read as a whole, and to be construed against the factual matrix and the circumstances of the case, and then applied to the individual facts of the case. I therefore apply the “obviously wrong” test.

15.  Counsel for the Defendant argued that Question 1 was not a question which the tribunal was asked to decide in the Arbitration, as there was no dispute as to the requirement for the use of public fill in the reclamation in question. According to the Defendant, there was no issue as to the meaning of the Environmental Permit (“EP”), which stipulated that “not more than 30% public fill shall be used for reclamation filling below+ 2.5mPD, unless otherwise agreed by the Director”. Nor had the Defendant disputed the applicability of the EP requirement to the Sub-Contract between the Plaintiff and the Defendant (“Sub-Contract”).

16.  Having considered the Lists of Issues submitted in the Arbitration, I would accept that the dispute submitted to the tribunal for determination included the question of (a) whether or not the Plaintiff had given instruction to the Defendant to use public fill as a component of the reclamation fill to be deposited to beneath+ 2.5mPD; (b) the proportions thereof; and (as proposed by the Plaintiff) (c) whether there had been incorporated into the Sub-Contract the obligation for “public fill to be used whenever possible” (as specified in the Main Contract), and for the “maximization of use of suitable public fill”. Whilst questions (a) and (b) may be purely factual, question (c) is legal or a mixed question of fact and law, which would inevitably require the tribunal to consider the relevant terms and conditions governing the contractual obligations of the Defendant with regard to the use of public fill, the proportion to be used in its works, and the legal effect of such terms and conditions. The relevant terms and conditions include but are not restricted to the requirement under the EP which the Defendant claims to be undisputed.

17.  Having read paragraphs 44 to 54 of the Award, however, I agree with the Defendant that the intended appeal on Question 1 is nothing more than a challenge to the Arbitrator’s findings of fact, disguised as a purported error of law.

18.  I accept the Defendant’s submissions, that the Arbitrator found that, notwithstanding the EP requirements, the Plaintiff was not entitled to contend that Type A fill had to be 30% public fill because the Plaintiff had already agreed at the tender meeting that Type A fill would be 100% sand (which is more expensive than public fill) (paragraph 48 of the Award). At paragraph 47 of the Award, the Arbitrator referred to the fact that the agreement reached at the tender meeting was reflected by the Plaintiff’s change of the description of BQ Item No 17 from “Type A fill to +2.5mPD” to “Sand fill (material supplied by Sub-contractor) in the Subcontract booklet”.

19.  At paragraph 48 of the Award, the Arbitrator referred to the witnesses’ testimony in the Arbitration, accepting the evidence of the Defendant that as a result of the exchange between the parties as to the type of material they were proposing under Type A fill and the price therefor, the Defendant had proposed 100% sand to be used, and that such proposal had been accepted by the Plaintiff, as otherwise the Plaintiff “should have requested (the Defendant) in the tender meeting to quote for Type A fill, namely maximum 30% public fill or even different rates for different % public fill, rather than changing the description of BQ Item No 17”. This is a finding of fact made by the Arbitrator on the evidence adduced and on the submissions made in the Arbitration.

20.  The Arbitrator further rejected the Plaintiff’s argument that Note 1 of the construction drawings required the maximization of public fill to 30% overall in the reclamation, finding that it was the Plaintiff which was responsible for the settlement design and to instruct the Defendant to use the appropriate percentage of the two fills, but that the Plaintiff had never done so (paragraphs 46 to 50 of the Award).

21.  In particular, the Arbitrator explained at paragraph 48 of the Award that what Note 1 specified was:

“To maximize the use of public fill, Type A fill (sand fill with public fill) will be adopted for filling below + 2.5mPD. The actual use of public fill will depend on the settlement design, site progress, and availability of filling materials etc. In any case, the Type A fill should contain no more than 30% of public fill.”

The Arbitrator proceeded to state, as follows:

“It does not say type A fill must be 70% sand and 30% public fill. The main contract is a design and build contract and (the Plaintiff) must have design responsibility. On the other hand, the Subcontract is a remeasurement contract so that (the Defendant) should not be responsible for any design, including the settlement design. As the actual use of public fill will depend on the settlement design and progress as stated in Note 1, I find that (the Plaintiff) would have requested (the Defendant) to quote for type A fill under different % of public fill had (the Defendant) not accepted 100% sand to be used as type A fill in the tender meeting. Accordingly, I find that (the Plaintiff) had accepted (the Defendant’s) proposal to use 100% sand as type A fill under BQ Item 17 in the tender meeting, perhaps to suit its progress. That was the reason why (the Defendant) and (the Plaintiff) referred to sand fill in the minutes of meeting.” (Emphasis added)

22.  From the reasons given, it is clear that the Arbitrator found that the parties had agreed at the tender meeting that Type A fill would be 100% sand, and that the Plaintiff had the obligation under the Sub‑Contract, but had failed to stipulate, what proportion of sand fill and public fill the Defendant was required to use. I accept the Defendant’s submission, that the Court is not entitled to interfere with these factual findings of the Arbitrator.

23.  It would also appear that on the question of whether the obligation to maximize the use of public fill had been incorporated into the Sub-Contract, the tribunal answered it by construing the obligation in the manner set out at paragraph 48 of the Award, and finding that (even if the obligation had been incorporated) there was no breach by the Defendant of such obligation. The Plaintiff has not persuaded me on the materials, and on the reading of the Award, that “on the basis of the findings of fact in the award the decision of the tribunal on the question is obviously wrong”.

24.  In any event, I am not satisfied that the Arbitrator’s conclusion was either “obviously wrong”, or (if I am wrong on the applicable test) “open to serious doubt”, for the following reasons:-

a.  The Environmental Permit provides that “not more than 30% public fill shall be used for reclamation filling below +2.5mPD”.

b.  ER 1.31F(4) and CS 6.09(14) required the maximisation of public fill, but did not stipulate how it was to be maximised.

c.  In other words, it was not a contractual requirement that the reclamation filling below +2.5mPD must be 30% public fill.

d.  The tribunal was entitled to find as a matter of fact that the parties had reached a different agreement as to the percentage of public fill, namely (1) the Defendant agreed at the tender meeting that Type A fill would be 100% sand, and (2) although the Plaintiff bore the responsibility for settlement design under Note 1 of G/3, it did not reject HKR’s proposal of using 100% sand as type A fill in the tender meeting (paras 46-50 of the Award).

25.  I do not grant leave to appeal on Question 1.

Question 2

26.  Question 2 addresses paragraphs 55 to 63 of the Award, entitled “BQ Item No 18 – Size 10mm to 37.5mm rock fill for the TWP (material supplied by HK River)”.

27.  While the Plaintiff does not dispute that the Arbitrator correctly interpreted MM 17.14, it submits that the Arbitrator had erred in his adoption of an assessment methodology and computation (paragraphs 5.19 to 5.20 of the OS). In other words, the Plaintiff’s case is that the Arbitrator identified the correct legal test, but applied it wrongly to the facts.

28.  I accept that Question 2 substantially affects the rights of the parties. There is a difference of some HK$20 million in calculation. I further accept that the correct interpretation and application of MM 17.14 was a question the tribunal had to decide. However, given that (as pointed out by the Defendant) MM 17.14 is a one-off clause which was specifically drafted by the Plaintiff for this Sub-Contract, I do not see how its interpretation and application can be a question of general importance. The “obviously wrong” test applies.

29.  The Plaintiff submits that although the tribunal correctly interpreted MM 17.14, it applied that test wrongly on the facts. On the Defendant’s part, it submits that Question 2 relates to the experts’ methodology and calculations and is a question of fact, and not of law.

30.  The methodologies in question are for the calculations of the quantities of rock fill reused in the construction of the TWP (ie Temporary Working Platform). As the Arbitrator pointed out at paragraph 56.1 of the Award, BQ18 is “principally a dispute on the interpretation and application of (the relevant mm)”. Different and alternative methodologies had been proposed by the experts called respectively by the Plaintiff and the Defendant in the Arbitration, and they formed part of the evidence before the tribunal. As the Defendant pointed out, the parties in the Arbitration had chosen to appoint an experienced quantity surveyor to be the arbitrator, for the purpose of deciding the highly technical issues raised in the Arbitration concerning the measurement of works and the calculations of the amounts claimed.

31.  The Plaintiff highlighted the fact that the Arbitrator had stated (at paragraph 61 of the Award) that he found the Plaintiff’s approach and interpretation of MM 17.14 more preferable, but that he adopted the “alternative assessment” of the Defendant’s expert, which (the Plaintiff claims) did not follow the methodology advocated by the Plaintiff.

32.  From reviewing paragraphs 55 to 62 of the Award, the tribunal had clearly considered the expert evidence, the formulae proposed by them (which included the experts’ primary and alternative assessments), and had compared the different assessments and the resulting figures produced by the two experts. At paragraph 61 of the Award, the Arbitrator had pointed out that the Plaintiff’s expert (Je) had agreed on the calculation of BQ No 18 based on the Defendant’s position. The Defendant’s expert (Nie) had also conducted an assessment based on the Plaintiff’s formula.

33.  The Arbitrator eventually decided to adopt the Defendant’s expert assessment, of $73,649,250. In essence, what the Arbitrator did was to consider different aspects of each expert’s methodology/calculations, and adopted parts thereof, whilst rejecting others, in arriving at his final award.

34.  I accept the submissions made for the Defendant, that expert evidence is part of the evidence to be considered when the court/tribunal reaches a conclusion of fact (paragraph 45-25, Phipson on Evidence (20th edition). As this Court explained in Employer v Contractor[2023] HKCFI 2911 (at paragraphs 33 to 38), and as Counsel for the Defendant in this case highlighted, an arbitrator is entitled to accept the valuation of one expert over another’s, and doing so is neither “plainly wrong” nor “open to serious doubt”. This naturally extends to where the arbitrator decides to accept one part of an expert’s valuation, and another part of another expert’s valuation, on the basis of the arbitrator’s own expertise.

35.  In my judgment, the Plaintiff has failed to show that the Arbitrator’s decision on Question 2 is obviously wrong.

Question 3

36.  Under Question 3, the Plaintiff submits that the tribunal erred in law by allowing double recovery for non-material costs, firstly under BQ 19 (at paragraphs 64-66 of the Award), and again under Extra Works 20 (at paragraphs 165-170 of the Award), for the same 23,059 cu m of the 40mm rock fill.

37.  The Plaintiff emphasized the fact that the Defendant has not challenged whether the issue of double counting is a matter of general importance. I accept that the issue substantially affects the rights of the parties.

38.  The question of law posed by the Plaintiff is “whether it is lawful to award the same subject matter twice (albeit at different rates), resulting in a double-recovery in favour of one party” (paragraph 6.1 of the OS). I agree with the Defendant that this question, formulated as such, was not one which the tribunal was asked to decide in the Arbitration.

39.  The Plaintiff does not dispute that the issue of double counting was never raised in the course of the Arbitration. Crucially, the Plaintiff accepts that this double recovery arose from neither party’s pleaded case and only arose in the Award. Reading paragraphs 165 to 170 of the Award which deal with the claim under Extra Works Item No 20, the parties had clearly made ample submissions in the Arbitration on the meaning and effect of the claim, and how the works in question should be assessed. The Arbitrator referred to the factual evidence adduced by the parties and to the expert evidence as to the work and quantities covered, and how they should be paid for. He explained that he found the conclusions made by the Plaintiff’s expert as to the material removed and how they had all been used to be unreliable and without factual basis, and found the Defendant to be entitled to $6,124,150 under the claim.

40.  The Plaintiff sought to correct the Award under the slip rule, on the basis that there had been double recovery as a result of the Arbitrator’s decision on the claim. The Defendant objected on the basis that this was a “new submission that blatantly violates the rules of the Arbitration, as it is not permitted to introduce such new submissions at this stage”. The Arbitrator obviously agreed, as he did not correct this part of the Award.

41.  It is therefore clear that the Plaintiff had never raised the issue of double recovery arising from the assessments contended for Extra Works No 20, and the valuation for BQ No 19, as now claimed.

42.  Since the Plaintiff cannot establish that the Arbitrator’s decision on Question 3 is one which the tribunal was asked to decide (as required under s 6(4)(b) of the Ordinance), I decline leave to appeal.

43.  In any event, I accept the submissions made for the Defendant that on a proper reading and understanding of the Award, there was no overlap in the rates for Extra Work No 20, and the rates for BQ No 19. It was the Defendant’s case in the Arbitration that the former was concerned with the deposition cost and the rate for the formation of the rockfill, whereas BQ No 19 was concerned with measuring the quantity for excavating the rock fill. Whereas the Plaintiff had submitted in the Arbitration that the rate of BQ No 19 should apply for Extra Work No 20 as well, the Defendant had submitted that the rate for Extra Work No 20 should be the supply and deposition cost of rock fill minus the material cost of the excavated rockfill. As recited at paragraph 165.1 of the Award, the Defendant’s submission was that:

“165.1. ‘... 25,455m3 of rockfill were deposited before 31 October 2013 and 23,059m3 of rockfill were deposited after 31/10/2013. For the latter quantity of 23,059m3, they were reused rockfill. Mr. Chu agreed that prior to the instruction recorded in item 7.1 of the minutes of meeting no. 68 dated 18/12/2013, HKR had used new rockfill to TWP’ (see [Day12/20/20 to 21/6]) [#932 C Closing].

165.2. ‘Mr. Yu’s evidence was that before November 2013, new rockfill was imported to do the TWP and after November 2013, CSHK asked HKR not to import new rockfill’ (see [Day6/89/2-9]) [#933 C Closing].

165.3. ‘Therefore, for the former quantity of 25,455m3, it is submitted that they were newly imported rockfill and 25,455m3 rockfill shall be paid at $150/m3 in any event’ [#935 C Closing].

165.4. ‘In order to calculate the rate for BQ item 19, the tenderer had to estimate the quantity of reuse rockfill to be re-deposited to other marine works because the re deposition cost of such quantity will not be paid for’ [#939 C Closing].

165.5. ‘Since all these construction drawings, specification and GCSC do not show the 40mm rockfill to reclamation ch 550‑2070, the item coverage of redepositing the material for permanent seawall or any other marine works did not cover the work of the 40mm rockfill to reclamation ch 550-2070’ [#953 C Closing]

165.6. ‘HKR is entitled to 25,455m3 new rockfill at $150/m3, i.e. $3,818,250 in any event’ [#975 C Closing]

165.7. ‘In case the Tribunal considered that HKR is not entitled to use the 23,059m3 excavated rockfill as its own property, and therefore, the property right belonged to CSHK. Then CSHK is entitled to charge the material cost of the excavated rockfill against HKR’ [#977 C Closing].”

44.  The Defendant’s submission was apparently accepted by the Arbitrator, with the result that Extra Work No 20 was an award for the deposition cost, without any element of excavation. It cannot readily be seen that the Arbitrator’s decision was either “obviously wrong” or “open to serious doubt”.

Question 4

45.  Under Question 4, the Plaintiff submits that the question of law the Arbitrator was asked to decide was “the interpretation of GCSC 31 - in the context of the omission (or taking-away) by CSHK of the remaining permanent seawall works from HKR on 7 July 2014, in reliance on the state of affairs immediately prior to 7 July 2014.”. The interpretation of GCSC 31 is relevant to the Plaintiff’s counterclaim regarding the omission of the remaining permanent seawall from the Defendant’s scope of the Sub-Contract works on 7 July 2014.

46.  I accept the Plaintiff’s submission that the Arbitrator’s interpretation of GCSC 31 was relevant to assessing the Plaintiff’s entitlement in respect of the counterclaim, and therefore substantially affects the rights of the parties. However, as stated in paragraph 14 above, the decision on Question 4 is one of applying the relevant contractual provision to the facts of the case. I do not agree that this is a question of general importance, and the “obviously wrong” test is appropriate.

47.  The Plaintiff submits that if the Arbitrator had correctly interpreted GCSC 31, he would have held that the Plaintiff was entitled to take back/omit any part of the Sub-Contract Works if the Defendant had failed to carry out the Sub-Contract Works in accordance with the Plaintiff’s requirement. It further relies on the case of Maeda-China State JV v Bauer[2020] HKCA 158 to argue that the Arbitrator had ignored the clear language of the contractual provision and rewrote the provision.

48.  Having read paragraphs 187 to 192 of the Award, it is clear that the Arbitrator had simply rejected the Plaintiff’s counterclaim made on the basis of the Defendant’s “disastrous progress on the permanent seawall works”, for the reasons stated in paragraph 192: that the relevant work and delay was not critical (having rejected the report and evidence of the Plaintiff’s expert), that the Plaintiff had been obstructed in the execution of the relevant works, and that the Plaintiff had delayed the approval of rock material. These are all factual findings made on the basis of the expert and factual evidence before the tribunal, leading to the Arbitrator’s conclusion that in the absence of any delay, there was no failure on the Defendant’s part to carry out the works in accordance with the Plaintiff’s requirement, and no failure to perform the obligations stipulated in the Sub-Contract. On that basis, the Arbitrator found that the Plaintiff had no grounds to invoke GCSC 31, to remove the work from the Defendant and to incur any recoverable expense for the completion of the remaining permanent seawall.

49.  I see no basis for the Court to interfere with the findings made by the Arbitrator and see no obviously wrong decision on the interpretation of GCSC 31 to grant leave to appeal. Even if the “open to serious doubt” test should apply, my finding is that this standard has not been met.

Disposition

50.  For all the above reasons, I decline to grant leave to appeal on all 4 grounds.

51.  It follows that the Plaintiff is to pay the costs of the application for leave to appeal, on indemnity basis with certificate for two counsel.

  (Mimmie Chan)
Judge of the Court of First Instance
High Court

Mr Peter Clayton SC, instructed by J Chan, Yip, So & Partners, for the plaintiff

Mr Douglas Lam SC and Mr Solomon Lam, instructed by Wong & Lawyers, for the defendant



[1]  Nomenclature and abbreviations in the Award are adopted